2,100 people worked through the night to open the Can Tho - Ca Mau expressway in 14 days

Only 14 days to go until the Can Tho - Ca Mau Expressway is technically open to traffic. More than 2,100 workers and 1,150 machines are "overcoming the sun and rain", working day and night to complete more than 110km of the main route.

Báo Vĩnh LongBáo Vĩnh Long05/12/2025

Only 14 days left until the technical opening of the Can Tho - Ca Mau expressway. More than 2,100 workers and 1,150 machines are "overcoming the sun and rain", working day and night to complete more than 110km of the main route.

Many sections have installed median strips and built fences and bridge railings - Photo: THANH HUYEN
Many sections have installed median strips and built fences and bridge railings - Photo: THANH HUYEN

On December 5, a leader of the My Thuan Project Management Board said that in just 14 days, the Can Tho - Ca Mau expressway is expected to be technically open to traffic. This is the final piece connecting the North - South expressway axis from Lang Son to the southernmost tip of the country.

"Along the entire 110km main route, the construction atmosphere is "tense as a bowstring". Rain or shine, day or night, we are still working to ensure we reach the technical traffic opening date on December 19," said a leader of the board.

3 shifts, 4 shifts, not enough work during the day, work at night

More than 2,100 workers and 1,150 machines and equipment are working around the clock. The persistent rains often wet the road surface, making the work of paving asphalt sections stressful. But as soon as the weather dries, the construction teams immediately start: spreading crushed stone, compacting the base, paving asphalt, and covering with asphalt concrete.

"When it rains, we move on to other auxiliary blocks. When it's sunny, we start laying asphalt immediately, without wasting time," emphasized the leader of My Thuan Project Management Board.

IC12 interchange (the final intersection of the main highway) in Ho Thi Ky commune, Ca Mau province is gradually being completed - Photo: THANH HUYEN
IC12 intersection (the final intersection of the main highway) in Ho Thi Ky commune, Ca Mau province is gradually being completed - Photo: THANH HUYEN

According to the report of My Thuan Project Management Board, as of December 2, the priority items have reached 90%. The last meters of road are being constructed with the foundation and surface, completing the traffic safety system: painted lines, signs, guardrails, and drainage surface. Although the progress is very urgent, all technical standards on the compactness of the foundation, the flatness of the road surface, and construction safety are still strictly controlled by the consulting and supervising teams and supervising engineers.

A section of the highway is being paved, machines are working day and night - Photo: THANH HUYEN
A section of highway is being paved, machines are operating day and night - Photo: THANH HUYEN

To save time on commuting, most contractors have arranged for workers to have lunch and dinner right at the construction site. Rows of temporary shelters set up along the roadside have been bustling with workers for months.

Many workers took advantage of the time to eat at the construction site, then continued working - Photo: THANH HUYEN
Many workers took advantage of the time to eat at the construction site, then continued working - Photo: THANH HUYEN

In the remaining time, My Thuan Project Management Board requires construction units to mobilize all resources and closely monitor the weather to take advantage of every sunny hour for construction.

Installing median strips, completing the final steps to open the road to traffic - Photo: THANH HUYEN
Installing median strips, completing the final steps to be ready for technical traffic - Photo: THANH HUYEN

The completion of the Can Tho - Ca Mau Expressway not only upgrades the Western region's transport infrastructure to connect the Mekong Delta to the national expressway network, but also opens up new development opportunities, promotes economic and cultural exchange, and shortens the time and distance between the Western provinces and key economic zones.

Can Tho - Ca Mau Expressway in early December is like a bustling construction site day and night - Photo: THANH HUYEN
Can Tho - Ca Mau Expressway in early December is like a bustling construction site day and night - Photo: THANH HUYEN
Taking advantage of the sunny weather, the road rollers are working at full capacity to ensure progress - Photo: THANH HUYEN
Taking advantage of the sunny weather, the road rollers work at full capacity to ensure progress - Photo: THANH HUYEN

The Can Tho - Ca Mau Expressway project has a main route length of 110.85km (through Can Tho city, An Giang province and Ca Mau province) and a connecting route of 25.85km.

The project is divided into two component projects including the Can Tho - Hau Giang section and the Hau Giang - Ca Mau section, invested by My Thuan Project Management Board.

The total investment is 27,523 billion VND, started on January 1, 2023, and is planned to be completed by the end of 2025.

According to tuoitre.vn

Source: https://baovinhlong.com.vn/nhip-song-dong-bang/202512/2100-nguoi-lam-xuyen-dem-de-14-ngay-nua-thong-xe-ky-thuat-cao-toc-can-tho-ca-mau-dbe4064/


Comment (0)

Please leave a comment to share your feelings!

Same category

People's Artist Xuan Bac was the "master of ceremonies" for 80 couples getting married together on Hoan Kiem Lake walking street.
Notre Dame Cathedral in Ho Chi Minh City is brightly lit to welcome Christmas 2025
Hanoi girls "dress up" beautifully for Christmas season
Brightened after the storm and flood, the Tet chrysanthemum village in Gia Lai hopes there will be no power outages to save the plants.

Same author

Heritage

Figure

Enterprise

Hanoi coffee shop causes a fever with its European-like Christmas scene

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC