[Image] Inside the 'heart' of Long Thanh Airport

(Dong Nai) - The construction and equipment installation package for the passenger terminal, considered the "heart" of the Long Thanh International Airport Project Phase 1, is currently being accelerated to meet the plan for putting the project into commercial operation.

Báo Đồng NaiBáo Đồng Nai16/05/2026

The Long Thanh Airport passenger terminal is designed to international 5-star standards, inspired by the image of a lotus flower. The skylight glass roof in the center of the terminal not only allows for natural light but also serves as an architectural and artistic highlight of the building. Photo: Pham Tung
Currently, the consortium of contractors is continuing to complete the construction of the attic ceiling beneath the skylight roof at the central passenger terminal. Photo: Pham Tung
Currently, the consortium of contractors is continuing to complete the construction of the attic ceiling beneath the skylight roof at the central passenger terminal. Photo: Pham Tung
Construction workers are finalizing the details of the station's roof before installation. Photo: Pham Tung
Construction workers are finalizing the details of the station's roof before installation. Photo: Pham Tung
At the passenger terminal's various levels, construction work on the ceiling is also being carried out simultaneously. Photo: Pham Tung
At the passenger terminal's various levels, construction work on the ceiling is also being carried out simultaneously. Photo: Pham Tung
Workers are constructing the attic ceiling on the second floor of the Long Thanh Airport passenger terminal. Photo: Pham Tung
Workers are constructing the attic ceiling on the second floor of the Long Thanh Airport passenger terminal. Photo: Pham Tung
A section of the attic ceiling on the 3rd floor, part of the central roof of the Long Thanh Airport passenger terminal, has been largely completed, adding to the building's beauty and modern appearance. Photo: Pham Tung
The consortium of contractors is also simultaneously installing equipment and systems for the passenger terminal. Engineers are checking and comparing the ventilation system installation with the design drawings. Photo: Pham Tung
The consortium of contractors is also simultaneously installing equipment and systems for the passenger terminal. Engineers are checking and comparing the ventilation system installation with the design drawings. Photo: Pham Tung
According to the Long Thanh Airport Project Management Board, approximately 3,000 officials, engineers, and workers are currently involved in the construction of the Long Thanh Airport passenger terminal. Photo: Pham Tung
According to the Long Thanh Airport Project Management Board, approximately 3,000 officials, engineers, and workers are currently involved in the construction of the Long Thanh Airport passenger terminal. Photo: Pham Tung
Due to the insufficient number of construction workers for the passenger terminal project, the construction work has encountered some difficulties. Photo: Pham Tung
Nevertheless, the Long Thanh Airport Project Management Board has worked with contractors to adjust the schedule to meet the completion and operation plan of the project. Photo: Pham Tung
Nevertheless, the Long Thanh Airport Project Management Board has worked with contractors to adjust the schedule to meet the completion and operation plan of the project. Photo: Pham Tung

Pham Tung (compiled)

Source: https://baodongnai.com.vn/kinh-te/202605/anh-ben-trong-trai-tim-san-bay-long-thanh-1500f02/


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Phan Dinh Phung Street

Phan Dinh Phung Street

Clouds drift over the mountains

Clouds drift over the mountains

The sun sets.

The sun sets.