Busy from the beginning of the year
Right after the Tet holiday, the working atmosphere at the construction site to renovate and upgrade provincial road 395 and the road leading to Cay bridge to provincial road 394 in Binh Giang district was bustling. Dozens of engineers, workers, and machines were divided into many construction teams to simultaneously carry out many items. The Binh Giang District Construction Investment Project Management Board provided maximum support and created all conditions for the investor, contractor, and construction unit to implement the project. Taking advantage of favorable weather, the contractor paved the road surface, items, and work were urgently carried out, striving to open the entire route to traffic before the April 30 - May 1 holiday.
In 2025, Binh Giang district was assigned more than 400 billion VND of public investment capital to implement 43 projects, including 32 district-level projects and 11 commune-level projects. Some projects with large investment capital in 2025 in Binh Giang include: Renovation and upgrading of provincial road 395 (section from km16+750 - km23+930) and the road leading from Cay bridge to provincial road 394 in 2025, allocated 189,900.96 million VND; Renovation of 3-storey classroom building with 15 rooms, subject classroom building, principal's house and auxiliary items of Vu Huu Secondary School, allocated 7 billion VND...
Up to this point, some projects have disbursement data. According to the update on the progress of public investment disbursement on the software application for monitoring the plan and progress of public investment of Hai Duong province, from the beginning of February to February 17, Binh Giang district has disbursed 4 billion VND.
“From the first day and month of 2025, we have started to implement and closely follow the public investment disbursement scenario. With the experience from 2024 and the high determination of Party committees, authorities at all levels and units, we believe that the locality will continue to complete the public investment disbursement plan this year,” affirmed Mr. Nhu Van Chuyen, Vice Chairman of Binh Giang District People's Committee.
Experience to reach the finish line first
Binh Giang district has grounds to be confident with the 2025 target based on the experience of accelerating public investment in 2024. With active participation, the disbursement of public investment capital in Binh Giang district has made a spectacular breakthrough. If at the end of November 2024, the whole district had only disbursed more than 30 billion VND, reaching 33% of the total assigned capital, by January 25, 2025, it had disbursed 412 billion VND, reaching 100.1% and was the first locality in the province to reach the target of disbursing public investment capital according to the annual plan assigned by the province (as of January 31, 2025, the end of the 2024 public investment disbursement fiscal year, in addition to Binh Giang district, there were 2 other localities that disbursed public investment capital reaching 100% of the capital plan assigned by the province, namely Kim Thanh and Tu Ky).
One of the major projects of Binh Giang district to be implemented in 2024 is the Project to renovate and upgrade the sidewalk section from km0+300 to km2+760 of Provincial Road 392 (from the New Year intersection to the District Traditional House) and Dinh Tien Hoang Street. The project has a total investment of more than 17.5 billion VND.
By the end of August 2024, this project had only disbursed about 4 billion VND. Binh Giang District has directed units to urgently resolve difficulties and obstacles, focus on completing construction items, completing acceptance, payment and disbursement of capital to contractors. Strengthen coordination between relevant agencies and units to speed up construction and settlement progress. By January 10, 2025, the district had completed disbursement of 100% of the allocated capital and put the project into use.
Similarly, the Ke Sat Town Kindergarten Construction Investment Project has a total investment capital of more than 9.8 billion VND. In August 2024, the project has only disbursed 174 million VND. Binh Giang District has implemented many synchronous solutions such as assigning specific progress for each construction item; requiring construction contractors to commit and ensure the correct progress. Assigning staff of the District Construction Investment Project Management Board to be responsible for the construction progress and disbursement of the project. After completing each construction package, the investor, construction unit and related units urgently check the actual workload, complete the request for payment and settlement documents... By December 31, 2024, the project had completed 100% disbursement of capital.
Removing "bottlenecks" in land clearance
The project to renovate and upgrade provincial road 395 and the road leading from Cay bridge to provincial road 394 is a key project of Binh Giang district to implement the Resolution of the 28th District Party Congress for the 2020-2025 term. The project passes through Vinh Hung, Vinh Hong, Tan Viet, Hung Thang and Long Xuyen communes with a total investment of more than 1,000 billion VND.
The above project started in November 2023. To implement the project, Binh Giang district had to reclaim land from more than 400 households with a total area of over 226,000 m2 . During the site clearance process, the project received the consensus of most people. Many families and individuals have dismantled and relocated the construction, handing over the site to the construction contractor. However, there are still households that have not agreed to sign the land and property inventory records on the land, significantly affecting the construction progress and capital disbursement of the project.
Mr. Nhu Van Chuyen, Vice Chairman of Binh Giang District People's Committee, said that this project has the largest public investment capital in 2024 of the district, accounting for about 45% of the total capital allocated to the locality. Of which, the land clearance capital accounts for about 33%.
By December 2024, the project had only disbursed about 50% of the allocated capital and the biggest problem was site clearance. The Standing Committee of Binh Giang District Party Committee has closely directed the District Compensation and Resettlement Support Council, and socio -political organizations from the district to the grassroots have actively participated in propaganda and mobilization.
The district has established a Steering Committee for site clearance for important projects headed by the Secretary of the District Party Committee, and the District People's Committee has established a site clearance working group headed by the Vice Chairman, with members being representatives of departments, branches, and organizations. Many meetings, propaganda, and dialogues with households were organized. Not only departments, branches, and organizations, but also district leaders directly went to each household to learn and listen. As a result, households agreed to sign the plan and receive compensation and support. By the end of December 2024, 98% of the site of the Project to Upgrade Provincial Road 395 (section from km16+750 - km23+920) and the road leading from Cay Bridge to Provincial Road 394 had been completed.
Mr. Nhu Van Chuyen added that if in June 2024, the district did not have disbursement data for this project, by early January 2025, the site clearance for the above project had basically been completed and the disbursement of more than 183 billion VND of capital allocated in 2024 (reaching 100%). Currently, the project is being continued to be implemented by construction units.
In 2024, Binh Giang district will implement 29 public investment projects and works. Of these, 8 projects will be carried over from 2023 and 21 new projects will start construction in 2024. The projects will be implemented in accordance with legal regulations and will be effective during exploitation and use.
Source: https://baohaiduong.vn/binh-giang-giai-ngan-von-dau-tu-cong-ngay-tu-dau-nam-405430.html