According to EVN, as of July 14, 72/85 renewable energy (RE) projects with a total capacity of nearly 3,931.9 MW have submitted documents to the Electricity Trading Company to negotiate electricity prices and power purchase contracts. Of these, 60 projects (with a total capacity of 3,331.4 MW) proposed a temporary price equal to 50% of the ceiling price of the price range (according to Decision No. 21/QD-BCT dated January 7, 2023 of the Ministry of Industry and Trade ).
EVN and investors have completed price negotiations and signed PPA contracts for 58/60 projects; the Ministry of Industry and Trade has approved provisional prices for 58 projects with a total capacity of 3,181.4 MW.
There are 14 factories/parts of factories with a total capacity of 686.12 MW that have completed COD procedures and are generating commercial electricity to the grid.
EVN data shows: The cumulative electricity output of transitional renewable energy projects since COD reached about 115 million kWh. Of which, the average daily electricity output is about 3.2 million kWh, accounting for about 0.4% of the total mobilized power output.
20 projects have been accepted by competent state management agencies for the construction/part of the construction; 27 projects have been granted electricity operation licenses for the entire plant/part of the plant; 37 projects have had decisions to extend investment policies.
There are still 13 projects with a total capacity of 802.70MW that have not yet submitted negotiation documents.