HomeNewsNews"Test run" of Long Thanh airport runway before April 30, 2025

"Test run" of Long Thanh airport runway before April 30, 2025

(Dan Tri) – The progress of Long Thanh airport runway is shortened by 3 months compared to the contract, and can be technically exploited on the occasion of the April 30, 2025 anniversary.

According to the report of Vietnam Airports Corporation (ACV), the runway project of Long Thanh airport will be shortened by 3 months and can be technically exploited before April 30, 2025.

“Technical exploitation” means that the runway is fully equipped with aviation signal information equipment and can deploy calibration flights with specialized aircraft.

Long Thanh airport runway test run before April 30, 4 - 2025
Long Thanh airport runway is taking shape (Photo: Hoang Binh).

 

In recent times, the airport system including runways, taxiways, and aprons of Long Thanh airport has been actively deployed by the contractor with more than 2.000 personnel, more than 500 machines, and 50 construction teams on the field. The construction volume to date has reached 42,23% of the contract value.

The runway section has been deployed to the cement concrete layer, expected to be completed and technically exploited before 30/4 next year.

For the passenger terminal, the contractor has completed the reinforced concrete structure of all 5 floors, is installing the steel frame for the roof system and building walls on the floors. The passenger terminal is expected to complete the construction part in December 2025, test run and complete the whole thing before August 31, 2026.

Regarding the two connecting routes, route 2 is expected to be completed in the month November 2025; the intersection between route 1 and Bien Hoa - Vung Tau expressway will be completed in the month August 2025; the intersection between route 1 and Ho Chi Minh City - Long Thanh - Dau Giay expressway will be completed in the month October 2025 and the entire route will be completed in the month December 2025.

Dantri.com.vn

Source: https://dantri.com.vn/xa-hoi/chay-thu-duong-bang-san-bay-long-thanh-truoc-3042025-20241111143020277.htm

Same topic

Long Thanh airport construction site speeds up at the end of the year

(Dan Tri) - The steel frame roof structure of the passenger terminal, runway, and connecting road to Long Thanh airport is being mobilized by contractors to the maximum of human and material resources for construction and installation, speeding up progress. In early December, at the construction site of Long Thanh airport's passenger terminal, more than 12 engineers, supervisors, and workers are urgently working on the items and projects to...

Investor of Long Thanh Airport's No. 1 Aircraft Maintenance Project Revealed

(NLDO) - The investor winning the bid for the No. 1 aircraft maintenance service investment and business project is the Aircraft Engineering Company Limited (VAECO) ...

6 large bid packages are looking for contractors to start construction in early 2025

From December to early 12, ACV continues to invite bids for 2025 packages at Long Thanh airport for wastewater treatment, airport management system, parking lot, port operator... ...

Aircraft repair service project at Long Thanh airport finds investors

The Ministry of Transport has just approved the results of selecting investors for the aviation equipment maintenance and repair service project and ground commercial technical services No. 2 under component 4 at Long Thanh International Airport.

Prime Minister's hot orders on Long Thanh Airport progress and connecting road

The Ministry of Transport (MOT) and investors of Long Thanh Airport's component projects are required to speed up the progress to be able to synchronously exploit the project before December 31, 2025. A series of urgent orders from the Prime Minister on the progress of Long Thanh Airport and connecting roadsThe Ministry of Transport (MOT) and investors of Long Thanh Airport's component projects are required to speed up...

Highlights

New Posts

Same author

200 test trains run every day before Metro No. 1 goes into commercial operation

Before commercial operation, Metro 1 will be tested with 200 daily trips to evaluate technical system factors. On 12/12, Ho Chi Minh City Urban Railway One Member Co., Ltd. (HURC1) announced that before commercial operation, Metro 1 (Ben Thanh - Suoi Tien) will enter the final test run with 200 daily trips. The test train will run 13-21/12, from 5am...

6 values ​​that make The Continental attractive

(Dan Tri) - With a vision of creating a classy living space, The Continental brings the vitality of a global destination, awakening the Co Loa heritage. The project possesses 6 unique values, affirming its pioneering position in shaping different living standards. The "heart" of the urban area Inter-City HubThe Continental is strategically located just 15 minutes from Noi Bai airport and the center...

Hanoi "locks in" banning and restricting many types of vehicles in Hoan Kiem and Ba Dinh

Highly polluting gasoline-powered vehicles are banned or restricted from entering low-emission zones. On the morning of 12/12, with the majority of delegates in favor, the Hanoi People's Council passed a Resolution on Regulations for implementing low-emission zones in the city. The resolution takes effect from January 1, 2025. Pilot in Hoan Kiem and Ba Dinh districts According to the resolution, the low-emission zone is part of the strictly protected area...

HCMC will continue to remove obstacles for more than 1.700 officetel apartments

(Dan Tri) - Ho Chi Minh City has removed obstacles for more than 43.000 apartments, including nearly 7.200 officetels. It is expected that by 2025, the city will complete the removal of difficulties and issue pink books for the remaining 38.000 apartments. A report by the Ho Chi Minh City People's Committee said that 8.918 officetel apartments in 29 projects in the area have not been issued pink books due to problems. As of December, the Department of...

Musician Ha Anh shares about the shock of composing for the first time

(Dan Tri) - In a recent music night, Ha Anh shared some interesting things when looking back on his journey to music. At the show, Ha Anh said that he had experienced many shocks when pursuing music professionally. "In 2020, I started writing music. The first song, I gave it to my brother to listen to, after only listening to a few lines, before the chorus, he...

Much read

Prime Minister issued an order to start construction of Ring Road 3 in Ho Chi Minh City and 2 highways

On the morning of 18/6, in Ho Chi Minh City, Prime Minister Pham Minh Chinh attended the ceremony and gave the order to start construction of 3, a series of important national transport projects. These are the 3 Ho Chi Minh City Ring Road; Bien Hoa - Vung Tau Expressway (1 phase) and Khanh Hoa - Buon Ma Thuot Expressway (1 phase). The event was held online...

Vietnam is among the world's cheapest destinations in 2024

Famous travel magazine Condé Nast Traveler lists the 21 cheapest destinations for tourists in 2024, including Vietnam. Tourists unexpectedly receive gifts when visiting Da Nang, Vietnam in early 2024. Photo: Thuy Trang According to Condé Nast Traveler, many factors to consider when planning a vacation, from finding cheap travel destinations, the safety of the destination to...

General Secretary and President To Lam went on a state visit to the People's Republic of China

Accepting the invitation of General Secretary of the Central Committee of the Communist Party of China, President of the People's Republic of China Xi Jinping and his wife, General Secretary of the Central Committee of the Communist Party of Vietnam, President Socialist Republic of Vietnam To Lam and his wife and the high-ranking delegation of our Party and State today left Hanoi, on their way...

Van Lang (Lang Son): Focus on equipping knowledge on gender equality, ensuring the advancement of ethnic minority women

Implementing Project 8, the National Target Program on Socio-Economic Development in Ethnic Minority and Mountainous Areas, Van Lang District, Lang Son Province pays special attention to equipping knowledge on gender equality (GEA) and skills in gender mainstreaming for officials in the political system, village elders, village chiefs and prestigious people in the community. Thanks to that, awareness has been raised...

Some images of typical activities of General Secretary Nguyen Phu Trong

On the afternoon of 18/7, the Party and State held a ceremony to award the Gold Star Order to General Secretary Nguyen Phu Trong at the 108 Central Military Hospital. General Secretary Nguyen Phu Trong with the people of Tay An commune, Tien Hai district, Thai Binh. The Party and State's awarding of the Gold Star Order to the General Secretary is the Party, State and people's recognition of his great contributions and merits...

Same category

Streamlining the Government apparatus

(CPV) - Implementing the request of the Central Steering Committee on summarizing Resolution 18-NQ/TW, the Government, ministries, ministerial-level agencies, and government agencies have urgently implemented the restructuring of the apparatus towards streamlining, effective and efficient operations. Up to now, ministries, ministerial-level agencies, and government agencies have basically completed the planned restructuring of the ministry...

Launching the contest 'Send a green future 2050' - spreading the green message to future generations

The Ministry of Education and Training has just coordinated with the Green Future Fund (Vingroup) to launch the contest "Send a Green Future 2050". The contest creates opportunities for students to express their creative and unique ideas through three forms: writing letters, drawing or making videos. This is a creative playground for primary and secondary school students nationwide, with the desire to arouse awareness...

Standard Chartered forecasts Vietnam's GDP to grow 6,7% in 2025

Standard Chartered experts said the USD is expected to strengthen in the second half of 2025 as tariff policies and fiscal measures under President Trump's second term. On December 12, 2024, Standard Chartered Bank released its latest economic update report on Vietnam, forecasting the USD to strengthen in 2 but weaken in the early part of the year. The bank also...

Upholding the spirit of 'Fatherland, ship, commander'

On the morning of 12/12, in Vung Tau city, the 171 Brigade, 2 Navy Region held the first conference of ship captains and political commissars of the 2024 year. The conference aimed to affirm and honor the position and especially important role of the ship captain and political commissar for each ship. These are the people who preside over, directly lead, command, and operate all activities on board. With the honor of "Organization...

Organizing activities to celebrate Vietnamese Language Day in the Vietnamese community abroad

The Government Office has just issued Document 9100/VPCP-QHQT conveying the direction of Deputy Prime Minister Bui Thanh Son on the implementation of Vietnamese Language Honor Day in 2025. Organizing activities to celebrate Vietnamese Language Honor Day in the Vietnamese community abroad - Illustrative photo Specifically, the Deputy Prime Minister assigned the Ministry of Foreign Affairs to preside over and coordinate with ministries, agencies, and localities to direct the...

New Posts

Proposal to add capital to Bai Vot Expressway Construction Project

(CPV) - On 12/12, the Department of Transport of Ha Tinh province sent a document to the Thang Long Project Management Board - the representative of the investor of the Bai Vot - Ham Nghi expressway, proposing to add VND 1 billion in capital to carry out site clearance work. ...

Sophisticated and unique with OCOP products from Van Ha wood, Dong Anh district

Van Ha Commune, Dong Anh District is famous for its woodworking craft and its participation in the One Commune One Product (OCOP) Program has created opportunities for Van Ha woodworking village products to "take off". Currently, many production facilities in Van Ha woodworking village have products that meet OCOP 3-4 standards...

Streamlining the Government apparatus

(CPV) - Implementing the request of the Central Steering Committee on summarizing Resolution 18-NQ/TW, the Government, ministries, ministerial-level agencies, and agencies under the Government have urgently implemented the restructuring of the apparatus towards streamlining, effective and efficient operations. Up to now, ministries, agencies...

Striving to become a hospital on par with the region and the world

(CPV) - Speaking at the 130 anniversary ceremony of the establishment of Hue Central Hospital, Minister of Health Dao Hong Lan suggested building a team of Hue Central Hospital staff with good medical ethics, deep medical theory and good medical skills, for the health of the people. On 12/12, at...

Responsibility not only of the education sector

(CPV) - English becoming the second language in schools is simply understood as both students and teachers communicate in English. Knowledge is imparted in schools through the English language. This is a major policy and needs a step-by-step implementation roadmap....

New Posts