| Component 3 of the Ring Road 3 Project - Ho Chi Minh City, the section passing through the province, is about 11km long. Of which, the expressway section, about 5km long, is required by the Prime Minister to be technically opened to traffic before December 19, 2025. Photo: Pham Tung |
![]() |
| To complete the goal, these days, contractors are racing against time to speed up construction progress. On weekends, the construction site still maintains a bustling pace. Photo: Pham Tung |
![]() |
| Machinery and equipment were mobilized to work during the day off to complete the technical traffic opening goal. Photo: Pham Tung |
![]() |
| The entire project has 3 construction packages. Up to now, the total construction output of the 3 packages has reached more than 60% of the signed contract value. Photo: Pham Tung |
![]() |
| Many sections of the route have now been completed by contractors with asphalt concrete paving. Photo: Pham Tung |
![]() |
| In parallel with the construction of construction packages, contractors are currently implementing the installation of the median strip system between the expressway sections of the project. Photo: Pham Tung |
![]() |
| Workers install a median strip system on the section of the Ring Road 3 - Ho Chi Minh City expressway passing through the province. Photo: Pham Tung |
![]() |
| The road sign system is also being installed. Photo: Pham Tung |
![]() |
| Workers install traffic signs on Ring Road 3 - Ho Chi Minh City section passing through the province. Photo: Pham Tung |