As of November 13, the handover of the 500kV Hai Phong - Thai Binh transmission line project has completed 92/99 foundation positions, reaching 92.9% of the volume. Of which, the section passing through Hai Phong city has handed over 45/52 positions; the section passing through Hung Yen has handed over 47/47 positions to construction contractors.
In Hai Phong city, there are still 7 locations that have not been handed over due to waiting for design adjustments and problems with households that have not agreed to receive money according to the compensation plan.
Regarding construction work, it is currently being deployed simultaneously at 92 foundation locations. Of which, foundation casting has been completed at 44 locations, construction is underway at 48 locations; column installation has been completed at 11 locations; column erection is underway at 7 locations.
The project started on August 17, implemented in the communes: An Quang, An Khanh, Quyet Thang, Lac Phuong, Nguyen Giap, Vinh Thinh (Hai Phong); communes: A Sao, Vinh Hoa, Minh Tho, Quynh Phu, Quynh An, Nguyen Du, Than Khe ( Hung Yen ).
The project is of special importance to ensure full, stable and reliable power transmission for the 500kV Hai Phong transformer station; meeting the load demand of Hai Phong city, Hung Yen province and neighboring areas. The project contributes to improving voltage quality, reducing technical losses and strengthening connectivity and flexibility in operating the 500kV power grid in the Northern region.