Negotiated prices for 40 transitional renewable power projects, highest level 908 VND/kWh

Báo Thanh niênBáo Thanh niên28/05/2023


Also on the weekend, EVN will submit a document to the Ministry of Industry and Trade for consideration and approval for all 40/40 investors of renewable energy projects to transition to this temporary price proposal.

According to Decision 21 of the Ministry of Industry and Trade on the transitional price framework for solar and wind power plants, the ceiling price of the price framework (excluding value added tax) applied to ground-mounted solar power plants is VND 1,184.9/kWh; floating solar power plants VND 1,508.27/kWh; onshore wind power plants VND 1,587.12/kWh and offshore wind power plants VND 1,815.95/kWh.

With the proposed provisional price of 50% of the ceiling price, the electricity purchase price for the above 40 projects is estimated at 754 - 908 VND/kWh (excluding VAT). To date, the Ministry of Industry and Trade has approved provisional prices for 19 projects, with a total capacity of 1,347 MW. Thus, 21 projects are waiting for the Ministry of Industry and Trade to approve provisional prices and sign power purchase contracts.

Đã đàm phán giá 40 dự án điện tái tạo chuyển tiếp, mức cao nhất 908 đồng/kWh - Ảnh 1.

Price framework for power generation of transitional renewable energy projects issued with Decision 21 of the Ministry of Industry and Trade dated January 7, 2023

Đã đàm phán giá 40 dự án điện tái tạo chuyển tiếp, mức cao nhất 908 đồng/kWh - Ảnh 2.

There are currently 16 grid-connected renewable energy projects being tested...

According to the Electricity Trading Company, there are currently 16 grid-connected projects that have been and are being tested. Of these, 5 projects have completed testing and are carrying out COD (commercial operation date) procedures for commercial power generation. 19 projects have been accepted by competent State management agencies for the entire plant/part of the plant; 26 projects have been granted electricity operation licenses for the entire plant/part of the plant.

Up to now, there are still 32/85 projects, with a total capacity of 1,576.05 MW, that have not yet submitted documents to the Power Trading Company to negotiate electricity prices and power purchase contracts.



Source link

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product