Proposal to spend over 900 billion VND to expand the Cù Mông tunnel on the North-South expressway.

The Project Management Board 85 has just submitted to the Ministry of Construction a proposal for appraisal and approval of the feasibility study report for the investment project to complete the Cu Mong tunnel, part of the North-South East Expressway.

Báo Hải PhòngBáo Hải Phòng09/02/2026

Deo Ca Group is constructing a tunnel through the mountain on the North-South expressway. (Photo: PV/Vietnam+)
Deo Ca Group is constructing the tunnel through the mountain on the North-South expressway.

Specifically, the Cu Mong Tunnel project has a total length of over 5 km. Of which, the Cu Mong tunnel itself is approximately 2.6 km long. In the initial phase, the project will involve expanding the roadbed from 2 lanes to a 4-lane highway, with a design speed of 80 km/h and a roadbed width of 22 m.

The right-hand tunnel, over 2,572 meters long, will undergo road surface renovation and adjustments to the tunnel's equipment system to suit one-way operation with two lanes. The left-hand tunnel, over 2,605 meters long, will have its components completed, including the tunnel lining, cement concrete road surface, drainage system, electrical and mechanical systems, fire protection, and operation.

The existing bridge will be widened from 10.5 m to 14.75 m, and a new bridge unit will be built to the left of the route, parallel to and 0.5 m away from the existing bridges, with a width of 14.75 m (3 lanes); ensuring the overall cross-section of the bridge has 6 lanes.

The project has a total investment of approximately over 915 billion VND from the State budget, including: compensation, support and resettlement costs of nearly 3.7 billion VND; construction and equipment costs of over 605 billion VND; equipment costs of nearly 90 billion VND; contingency costs of over 155 billion VND…

The investment project to complete the Cù Mông tunnel, once finished, will gradually complete the transportation infrastructure according to the approved planning scale; ensure compliance with the Road Traffic Law; guarantee traffic safety; and enhance operational capacity to meet transportation needs on the route.

QH (compiled)

Source: https://baohaiphong.vn/de-xuat-hon-900-ty-dong-mo-rong-ham-cu-mong-tren-tuyen-cao-toc-bac-nam-535421.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Celebrating 20 years in Ninh Binh

Celebrating 20 years in Ninh Binh

Watch the fishermen pull in their seine nets at Man Thai beach in Da Nang.

Watch the fishermen pull in their seine nets at Man Thai beach in Da Nang.

Steps of Glory

Steps of Glory