On December 8, the People's Committee of Ninh Binh province sent Document No. 207/TTr-UBND to the Prime Minister and the Ministry of Construction on the Project to study the possibility of forming Ninh Binh International Airport. The project has a total preliminary investment of 23,216 billion VND, expected to start construction in 2027 and be put into operation from 2029.
According to the proposal, the airport was studied at 5 locations, in which the proposed location is located in Liem Tuyen ward and Binh Luc and Binh My communes. This location has convenient connections as it is about 7 km from Phu Ly city, 21 km from Nam Dinh city, 30 km from Ninh Binh province center; close to major tourist areas such as Tam Chuc pagoda (19 km) and Bai Dinh - Trang An (30 km).
Through research, Ninh Binh airport runway has a Northwest - Southeast direction with runway 1 3,800m long, runway 2 3,200m long; airport planning area is about 664ha.
In terms of scale, Ninh Binh airport is designed with level 4E (capable of operating Boeing 787, Airbus A350...) according to the standards of the International Civil Aviation Organization - ICAO, level I military airport.
The design capacity of Ninh Binh airport in 2030 is 5 million passengers/year, and by 2050 it is 10 million passengers/year.
The expected investment time for construction of Ninh Binh airport is from 2027, and it will be put into operation and exploitation by 2029.
Preliminary total investment for Ninh Binh airport is about 23,216 billion VND, including site clearance costs and excluding loan interest.
In which: state budget support and private sector capital (equity and commercial loans mobilized by investors). Expected payback period is about 27 years.
To invest in Ninh Binh airport under the public-private partnership (PPP) method, the People's Committee of Ninh Binh province has developed a financial plan based on the principle of mobilizing maximum non-budgetary capital to invest under the PPP method with a structure that ensures conditions for calling for investment, expected as follows:
By 2030: state budget capital (central and local) accounts for about 45.25% (about 6,776 billion VND), investor capital accounts for 54.75% (about 8,198 billion VND).
From 2031 - 2050: state budget capital (central and local) accounts for 2.8% (about 229 billion VND), investor capital accounts for 97.2% (about 8,013 billion VND).
To have a basis for implementing the next steps, the Ninh Binh Provincial People's Committee proposed that the Prime Minister and the Ministry of Construction consider and decide to add Ninh Binh International Airport to the master plan for the national airport system for the 2021-2030 period, with a vision to 2050.
The People's Committee of Ninh Binh province will urgently carry out the next steps in accordance with regulations, calling on domestic and foreign investors to pay attention and study the investment in Ninh Binh airport under the PPP method, meeting the set goals and requirements.