The project to upgrade and expand Road Z30A, Tra Tan commune has a length of 8km, roadbed width of 14m, road surface width of 13m, and sidewalks on each side of 0.5m wide. The total investment capital is 69.9 billion VND, invested by the Duc Linh Area Construction Investment Project Management Board, from the provincial budget.
The project implementation period is 3 years. The construction contractor is Quan Trung Trading and Production Company Limited. The project started construction on December 27, 2024 and was extended to December 31, 2025, and is currently applying for an extension.
As of December 2, 2025, the project still has 7 households with land clearance problems, of which 4 households are stuck with fences. The Duc Linh Area Construction Investment Project Management Board is coordinating with the People's Committee of Tra Tan Commune to speed up the progress of mobilizing land clearance for households stuck with gates and fences.

Through reports and field inspections, Vice Chairman of the Provincial People's Committee Nguyen Minh directed to urgently complete site clearance for the upgraded and expanded Z30A road, Tra Tan Commune People's Committee coordinated with the investor, the Duc Linh Area Construction Investment Project Management Board.
Vice Chairman of the Provincial People's Committee Nguyen Minh requested the road construction unit to complete the project before January 20, 2026. The contractor has committed to focusing on human resources and equipment, speeding up progress to complete 100% of the contract volume in 2025 and complete the road according to the direction of the province...

The N26 route project has a starting point connecting with Provincial Road 720, and an ending point connecting with the road to Dong Me village (Tanh Linh commune). The route length is 1.215km, the roadway width is 15m, the sidewalk width on each side is 6m, and the median strip width is 4m.
The project consists of two bridges: Suoi Cat Bridge, 45.37m long, and Suoi Lao Bridge, 17.4m long. The total investment is more than 156 billion VND, supported by the central budget.

At the N26 road construction site (Tanh Linh commune), many vehicles are busy working. Vice Chairman of the Provincial People's Committee Nguyen Minh encouraged the workers and engineers working at the construction site. The project is regularly urged to be implemented on schedule.
Vice Chairman of Tanh Linh Commune People's Committee Nguyen Minh Dung said that the Commune People's Committee has completed land prices to carry out compensation work, carry out site clearance for some remaining households and support people to resettle as soon as possible.
Reporting to the Vice Chairman of the Provincial People's Committee, the Tanh Linh Area Construction Investment Project Management Board said that the project has disbursed 141/156 billion VND, reaching 90.3% of the plan.
Through the actual inspection, Vice Chairman of the Provincial People's Committee Nguyen Minh requested the People's Committee of Tanh Linh commune to complete site clearance for the entire route before December 20. The Management Board of Construction Investment Project No. 2 must regularly check the progress.
The supervision consultant must also be present regularly. The construction unit must submit a weekly workload for the supervisors to monitor and report to the Provincial People's Committee. The Tanh Linh Area Construction Investment Project Management Board must strive to disburse 100% of the capital...
Source: https://baolamdong.vn/doc-thuc-tien-do-2-du-an-giao-thong-trong-diem-phia-dong-nam-lam-dong-406671.html