The Hoang Sa - Doc Soi road project has a total length of 26.88km, a total investment of 3,500 billion VND, invested by the Provincial Traffic Construction Investment Project Management Board. The project started in December 2023 and is expected to be completed in 2025.
Although it is a key project, site clearance has encountered numerous difficulties, and contractors have not yet completed procedures to exploit 9 sand mines designated by the Provincial People's Committee for the project, leading to the lack of conditions to carry out the project. Some contractors working on the construction site have moved equipment elsewhere. The work of calculating payment volume, refunding, and disbursing funds has also been delayed.
For half a year, the project was in a state of disrepair. Faced with that situation, on May 9, Mr. Tran Phuoc Hien - Vice Chairman of the People's Committee of Quang Ngai province signed a notice to send to many functional agencies, urging units to quickly speed up the project's construction progress. Mr. Tran Phuoc Hien assigned the investor to coordinate with the Department of Transport and related sectors and localities to develop a detailed project implementation schedule based on reality, in accordance with the handover situation (site, materials, capacity of the construction unit) at the construction site; ensuring completion according to the signed contract schedule.
In addition, while waiting for the designated sand source, the contractor proactively proposed a plan to accept losses and buy commercial concrete to immediately construct bridges, culverts, etc. to have output and speed up disbursement progress. With the investor's approval, the contractors mobilized maximum human resources and equipment to divide into many construction teams in the field. According to the investor's representative, the value of construction output in the past 15 days was recorded to be 3 times higher than the total of the previous 6 months combined.
According to the reporter's records at the North end of Bridge No. 2 - the largest bridge on the route, located in Binh Duong commune, Binh Son district, the construction atmosphere is urgent; many groups of engineers and workers are focused on constructing steel reinforcement, casting beams, bases and pouring concrete for bored piles... tankers carrying fresh concrete and heavy trucks carrying supplies and materials are lining up to enter and exit the construction site.
According to the investor representative, there are currently many construction sites on the site, stretching along the routes undertaken by each contractor in the joint venture. In the next few days, there will be more construction sites, thus speeding up the project's progress.
At present, the investor is actively coordinating with local authorities and compensation units to accelerate site clearance for the project. At the same time, the contractor consortium will coordinate with the investor and the Department of Natural Resources and Environment to urgently complete the submission to the Quang Ngai Provincial People's Committee for licensing the exploitation of 9 designated sand mines for the project.
Source: https://laodong.vn/xa-hoi/du-an-3500-ti-dong-o-quang-ngai-nhon-nhip-tro-lai-sau-nua-nam-diu-hiu-1359801.ldo