The project has been approved for planning since 2017 and has adjusted locally the detailed construction planning at the scale of 1/500 of the existing central area from hill E to White Bridge in Ho Chi Minh City. Dien Bien Phu in Decision No. 3336/QD-UBND dated December 29, 12. The project is invested and built to form a multi-functional market, trade and service area, meeting business and trade needs, contributing to socio-economic development. At the same time, through the project to create an area with beautiful architectural landscape associated with conservation and embellishment of historical sites and overcome the encroachment on roads and relic land for market fairs, affecting the environment. landscape, urban architecture, potential insecurity and order.
The project is built on an area of more than 18.083m2 with the scale of technical infrastructure construction: Construction of public works (market hall, parking lot...), urban greenery, construction of urban roads market and hand over to local authorities for exploitation; building kiosks in Muong Thanh market for organizations to operate, exploit and trade (for lease). The land fund after construction investment is handed over to the local government for management of nearly 13.000m .2 and land fund, investors pay land use fees and land rents for business and exploitation of more than 5.000m2. The total investment of the project is more than 193 billion VND. Project implementation progress in 2 years. In which, in the first year, priority is given to construction of technical and traffic infrastructure. Particular priority is given to the technical infrastructure, traffic in the market area (expected in the third quarter of 2022), which can be deployed to build market items to soon stabilize business, trade and the lives of affected people. by Project. In the fourth quarter of 2022, implementing excavation, embankment, leveling, construction of market items. In the second year, continue to invest and complete the market item; invest in the construction of green trees, squares and trade and service items to complete and put into operation. In which, from the first quarter to the third quarter, investment in construction of technical infrastructure, traffic and trees, squares ... From the fourth quarter of 2023, the works will be put into operation, put into operation.
In order for the investor to speed up the construction progress, the Provincial People's Committee has authorized the City People's Committee. Dien Bien Phu decided to acquire land to implement the project. Accordingly, the City People's Committee organizes the implementation of work related to land acquisition to ensure the correct order and procedures; handle related problems. After completing the site clearance, urgently complete the dossier and send it to the Department of Natural Resources and Environment for appraisal and submission to the Provincial People's Committee to allocate land to investors for project implementation. The Department of Natural Resources and Environment shall assume the prime responsibility for, and coordinate with relevant agencies and units in, guiding, inspecting and supervising the City People's Committee. Dien Bien Phu, in the process of organizing the implementation of the decision on land recovery, shall report to the Provincial People's Committee according to regulations.
Although the roadmap is set out in detail on a quarterly basis, but after the groundbreaking ceremony and handing over the project site (September 14, 9), until now, the construction investment time is almost over, but the project still faces many challenges. many difficulties, obstacles, not in accordance with the proposed schedule. Up to now, the ground clearance work has only reached 2022%; construction investment work is almost not implemented. Recently made public listing of compensation, support and resettlement plans of 50 households with an area of more than 56m9.715.2 with a value of 35,2 billion dong; make, submit for appraisal and approve 5 compensation, support and resettlement plans of 20 households and 4 organizations (Muong Thanh Ward Police, Forest Protection Department, Health Station and People's Committee of Muong Ward) Thanh), total area of more than 15.396m2, with a value of 32,85 billion VND.
The reason for the delay was that some households built houses and ancillary works on an area of land that was not eligible for compensation for residential land, and there was no record of preventing construction from the People's Committee of Muong Thanh ward. The land fund to arrange resettlement for eligible households is within the scope of the Muong Thanh A Urban Area project. Because previously the Muong Thanh Market and Service Trading and Service Project was in the Muong Thanh A Urban Area project ( currently separate 2 projects). In order to carry out the site clearance, the People's Committee of the province has just recently issued a decision to withdraw the old project and re-implement the legal basis for the new project. Besides, the project is currently facing problems related to more than 2.000m .2 Previously, it had been compensated and handed over according to the old project, but due to the lack of strict management, people could re-occupy and use it.
In order to speed up progress, the representative of Quang Ninh NQT Construction and Trading Joint Stock Company proposed that relevant units soon organize the implementation and accompany and coordinate with investors to remove difficulties according to scope. responsibility. When there is a clean ground, the competent authorities will study and advise to allocate land in parts and grant construction permits in parts to investors to pay land rent, be eligible for construction of project items, ensure the progress as well as the current regulations of the State on project management and capital construction investment. At the same time, it is recommended that the province direct the City People's Committee. Dien Bien Phu coordinated with the Department of Natural Resources and Environment, the Provincial Civil and Industrial Project Management Board and related agencies and units to promptly handle problems and problems related to the construction of the project. compensation and site clearance.
Currently, the land estimate schedule of the People's Committee of Muong Thanh ward is being publicly listed, so for households using the land, the land has been recovered and assigned to the Project Management Board for Civil and Industrial works. province (the investor of the project of building dams, embankments and building infrastructure for parks along the Nam Rom river); The City Land Management Center in collaboration with the People's Committees of Muong Thanh Ward, Him Lam Ward, the Project Management Board of Civil and Industrial Works of the province informed the households that received the full amount of compensation and support. approved; dismantling and moving assets and architectural objects to return the ground to the investor to implement the project.