Construction through the forest
Currently, contractors are making every effort to overcome difficulties and speed up the project's progress. Mr. Duong Tan Luyen - Project Manager, Son Long Thuan Trading Company Limited (the contractor for package 23, section from Km36 to Km41) said: "Continuous rain and landslides have greatly affected the project's progress. Complex geology and many underground water sources also require adjustments to construction solutions. As soon as the sun is out, we mobilize maximum mechanical equipment and workers, organizing construction day and night without rest to ensure the progress set by the investor."
The section through Ninh Son commune has been completed and put into use, creating favorable conditions for trade and travel. |
Up to now, the site clearance work has reached about 40.7km along the entire route. Regarding construction, the 17.1km section through Lam Dong province has completed 97% of the work volume. The 23.9km section through Khanh Hoa province, although facing many difficulties due to construction through forests and unusual weather, has also reached more than 70% of the work volume. To speed up the project's progress, the Provincial Construction Investment Project Management Board (investor) is closely coordinating with departments, branches, localities and contractors; organizing work with relevant units and localities to promptly remove difficulties and obstacles. Mr. Pham Minh Tan - Director of the Provincial Construction Investment Project Management Board said: "Currently, the collection of forest products on the route has been completed. We are actively urging construction units to work overtime to complete the project according to plan and ensure capital disbursement".
With a total length of 63.32km and a total investment of more than VND 1,495 billion, the road project from Ninh Son commune to Ta Nang intersection is divided into 2 components. Of which, component project 1 - the section connecting Ninh Son commune to Anh Dung commune has been completed and put into use since December 2023. Component project 2 - the section connecting Anh Dung commune to Ta Nang intersection has a total length of 41km, with a total investment of more than VND 1,095 billion. This is a challenging component as the road has to cross many deep forests, streams, and rugged terrain with steep hills and deep ravines, of which the section through Anh Dung commune is 23.9km long and the section through Ta Nang commune is 17.1km long. This road section is designed with a 9m wide roadbed, of which the road surface is 8m wide, the sidewalks on both sides are 1m wide; speed 50-60km/hour.
With great determination, 4 contractors are increasing more than 120 vehicles and more than 200 workers and engineers, synchronously deploying 8 construction projects. Mr. Le Van Sang - technical officer, Provincial Construction Investment Project Management Board emphasized: "Determining this as a key traffic project to create regional connectivity between Southern Khanh Hoa and the Southern Central Highlands provinces, we have urged and directed construction units to concentrate machinery, equipment and human resources to take advantage of the sunny weather to ensure construction progress. At the same time, we have directed consulting and supervising units to closely monitor the site to ensure quality and aesthetics so that the project can be completed and put into use in 2025 according to the plan set by the Provincial People's Committee, which is to open the route in early September and complete all construction items by the end of the year".
Inter-regional transport connections
When completed, the road project from Ninh Son commune to Ta Nang intersection will create a seamless, inter-regional traffic connection from the Southern Central Highlands to National Highway 20, National Highway 27, North-South Expressway, National Highway 1 and Ca Na General Seaport. Thereby, it will significantly shorten the travel distance, time and cost of transporting goods, strongly promoting trade and tourism .
The construction unit mobilized many machines to speed up the construction progress. |
Wherever the road is opened, the local appearance changes. Mr. Che Quang Dung - Head of the Economic Department of Anh Dung commune said: "The Ninh Son - Ta Nang route through Anh Dung commune accounts for 80% of the route length. When the route is put into operation, people will find it much more convenient to travel and transport goods. To exploit the potential of the route, the commune has planned both sides of the route to develop trade, services, and tourism, especially in the central area of the commune. From there, we aim to call on businesses to invest in development to promote the strengths of land funds, agricultural products as well as the conveniences of transport infrastructure."
The road project from Ninh Son commune to Ta Nang crossroads will be a driving force for economic development, creating many new opportunities for both the Southern Central Highlands and the southern part of the province. The efforts of the parties involved are turning the dream of a road through the forest into reality, opening up new opportunities for inter-regional development, creating favorable conditions for the community of residents in the project area to build a more and more prosperous life.
Mr. Tuan