(QNgTV) - The Quang Ngai - Hoai Nhon Expressway project has a total length of more than 88km, of which the section passing through Quang Ngai province is more than 60km long. The project started on January 1, 2023, is expected to open on September 30, 2025 and be completed and put into operation in December 2025.
At this time, contractors organized 50 main construction teams, with a total of 1,150 machines and equipment and 3,100 personnel. The cumulative output of construction packages reached 9,750/13,343 billion VND, reaching 73% of the contract value. Of which, the road item has been filled with more than 11/11.4 million m3, reaching nearly 98%; crushed stone construction is about 70 km, crushed stone layer reinforced with cement is 64 km. The volume of asphalt concrete pavement is more than 50 km.
Regarding the traffic safety category on the route, the unit has produced and assembled 90% of the traffic safety components, and installed about 20% of the traffic safety components. The fence system along the route has been basically completed, while some locations are still under construction. 76/77 bridges have installed girders and are constructing the bridge deck.
Currently, there are still 9 locations where people are obstructing construction, related to construction using vibrating rollers and blasting causing cracks in houses. The investor and contractors committed to inspecting and making full statistics after completing the construction, ensuring compensation according to regulations, avoiding affecting the construction progress.
Source: https://quangngaitv.vn/dua-cao-toc-quang-ngai-hoai-nhon-vao-khai-thac-trong-thang-12-6505053.html