Repairing damage at Vung Ang II BOT Thermal Power Plant after storm No. 10

Storm No. 10 collapsed the roof of the coal warehouse of the Vung Ang II BOT Thermal Power Plant (plant), causing heavy damage.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng09/12/2025

Vung Ang II BOT Thermal Power Plant Project in Vung Ang Economic Zone, Ha Tinh Province
Vung Ang II BOT Thermal Power Plant Project in Vung Ang Economic Zone, Ha Tinh Province

On December 9, Mr. Hoang Trong Binh, Deputy General Director of Vung Ang II Thermal Power Company Limited, said that the contractor is mobilizing human resources and equipment to focus on overcoming the consequences of the recent storm No. 10, which collapsed two roofs of the plant's coal warehouse.

It is expected that the repair of the items will be completed around July or August 2026, to put the factory back into operation.

z7307129769444_46086387c3eb15d5ca0069cdb0acf3c7.jpg
The coal warehouse area of ​​the factory was damaged by storm No. 10.

Previously, on December 4, the Ministry of Agriculture and Environment also issued document No. 9949/BNNMT-MT requesting Vung Ang II Thermal Power Company Limited to urgently overcome the effects of storm No. 10, ensuring safety and environment of the entire plant.

During the period of repairing and operating the factory, the company must re-evaluate the actual storage capacity of all warehouses and compartments to ensure they meet the conditions of cover, safe structure, and environmental protection requirements to proactively adjust the coal import and export plan.

z7307129581392_2020e7a38ad5f5f5a852e98e7fb6159d.jpg
Some of the factory's infrastructure was damaged by storm No. 10.

Along with that, fully implement measures to minimize coal dust dispersion; have plans and collect all overflowing rainwater and wastewater generated from the coal storage process (if any) to the industrial wastewater treatment system for treatment.

Develop a plan to respond to environmental incidents during repair and operation.

z7307129664539_62baee7b061866b5c0ba250588f89346.jpg
The factory's coal warehouse area was damaged by storm No. 10.

Vung Ang II BOT Thermal Power Plant started construction in 2021, with a total investment of 2.2 billion USD, invested by Vung Ang II Thermal Power Company Limited.

This is a key project in Vung Ang Economic Zone (Vung Ang ward, Ha Tinh province).

Source: https://www.sggp.org.vn/khac-phuc-thiet-hai-tai-nha-may-nhet-dien-bot-vung-ang-ii-sau-bao-so-10-post827699.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy
Bui Cong Nam and Lam Bao Ngoc compete in high-pitched voices

Same author

Heritage

Figure

Enterprise

People's Artist Xuan Bac was the "master of ceremonies" for 80 couples getting married together on Hoan Kiem Lake walking street.

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC