This morning, October 18, Standing Vice Chairman of the Provincial People's Committee Ha Sy Dong inspected the progress of the My Thuy Port Project Phase 1 and the production and business activities of VICO Quang Tri Investment and Mineral Joint Stock Company.

Checking the progress of My Thuy Port project and production activities at VICO Quang Tri Investment and Mineral Joint Stock Company

Standing Vice Chairman of the Provincial People's Committee Ha Sy Dong inspected the progress of the My Thuy Port project - Photo: LA

The My Thuy Port Construction Investment Project is a special maritime project invested by My Thuy International Port Joint Stock Company (MTIP Company). The investment scale of phase 1 includes the construction of 4 berths for ships with a capacity of up to 100,000 DWT with a total berth edge length of 1,300 m. The total investment of phase 1 is 5,902 billion VND. Implementation period is from 2024 to 2027.

Regarding construction progress, for package XL-01: construction of the dike stem, the eastern breakwater, to date, the construction of the storage yard, the casting yard with an area of 2.36 hectares, casting 362/362 temporary wharf blocks, 308/308 12-ton wave-breaking blocks. Construction of 260 m/320 m of the breakwater body. Currently, the contractor is completing 260 m of the breakwater body according to the design; implementing the construction of the remaining 60 m to be completed in the first quarter of 2025 according to plan.

For package VL-01: supplying ready-mixed concrete for the project, completed the installation of equipment for 2 mixing stations with capacity of 90 m3 /h and 180 m3 /h, well drilling and installation of power station. Concrete mix design is underway. For package XL-02: wharf and embankment behind wharf 1, 2 and package XL-03: breakwater and sand barrier embankment on the east side of the remaining section, package design has been completed, contractor selection is underway.

Regarding site clearance, the total area of phase 1 is 133.67 hectares. Of which, there has been a decision approving the compensation and support plan for 132.55 hectares; a decision to reclaim 129.2 hectares; and a decision to allocate 104.71 hectares.

Currently, MTIP Company is coordinating with the GPMB Council, Hai Lang District People's Committee and consulting units to implement land recovery and GPMB procedures for the additional area of phase 1 of 43.44 hectares and phases 2 and 3.

At the inspection, the representative of MTIP Company also proposed that the Provincial People's Committee direct departments and localities to promptly hand over the clean site for the remaining 4.47 ha area of phase 1 that has not completed site clearance.

For the additional land acquisition area of phase 1 and phases 2 and 3, after completing the measurement procedures and land recovery regulations, Hai Lang District People's Committee is requested to implement the land acquisition and recovery procedures to hand over the clean site to MTIP Company in the second quarter of 2025.

Propose that the Provincial People's Committee soon approve the policy of the location of temporary dredging waste storage sites as a basis for MTIP Company to implement the next steps. Renovate, upgrade, and expand the traffic system and related infrastructure to ensure the project's operational requirements.

Checking the progress of My Thuy Port project and production activities at VICO Quang Tri Investment and Mineral Joint Stock Company

Standing Vice Chairman of the Provincial People's Committee Ha Sy Dong inspected the field of My Thuy Port Area project - Photo: LA

After the field inspection, the Standing Vice Chairman of the Provincial People's Committee, Ha Sy Dong, emphasized that the My Thuy port project is an extremely important project to serve the socio -economic development of the province, increase revenue, as well as create confidence for other investors. Therefore, it is recommended that the investor and contractor increase human resources and equipment; open more bidding packages, select qualified contractors to speed up the project's construction progress.

Request Hai Lang district to focus on completing land acquisition procedures, striving to complete the handover of clean land in phase 1 in October 2024. The Department of Natural Resources and Environment develops a plan to remove obstacles in the implementation of common construction material mines.

Regarding the location of the temporary storage site for dredged waste during construction, Permanent Vice Chairman of the Provincial People's Committee Ha Sy Dong agreed with the plan and location of the temporary storage site for dredged products as proposed by MTIP Company.

Specifically, the white sand part of about 988,000 m3 was gathered in the 25-hectare area after the mine closure of VICO Quang Tri Investment and Mineral Joint Stock Company and neighboring areas; the dredged products that can be used as filling materials of about 12.33 million m3 were gathered in the areas within the scope of phases 1, 2, and 3 of the project.

Require MTIP Company to commit to arranging locations to receive dredged products in accordance with the project's investment progress, without affecting the construction progress and operational functions of the project's functional areas.

Checking the progress of My Thuy Port project and production activities at VICO Quang Tri Investment and Mineral Joint Stock Company

Standing Vice Chairman of the Provincial People's Committee Ha Sy Dong inspected the production and business activities at VICO Quang Tri Investment and Mineral Joint Stock Company - Photo: LA

Inspecting the production and business activities of VICO Quang Tri Investment and Mineral Joint Stock Company (VICO Quang Tri Company), Permanent Vice Chairman of the Provincial People's Committee Ha Sy Dong highly appreciated the methodical investment, modern technology and machinery, green - clean - beautiful environment; creating stable jobs for about 300 local workers; contributing a large amount to the local and central budget.

VICO Quang Tri Company is located in Tra Tri Phu village, Hai Hung commune, Hai Lang district, licensed by the Ministry of Natural Resources and Environment to exploit minerals in 2011 with a capacity of 601,150 tons/year on a total area of 446 hectares, exploitation period of 29 years.

Since its operation in 2016, the company's annual mining output has reached 51,000 - 217,000 tons. According to the licensed capacity, the company's annual land use demand for mining is about 16.7 hectares, provided that this area has completed legal procedures such as changing the purpose of forest use and land acquisition.

However, from 2016 to June 2024, the area granted to the company annually only reached about 9.98 hectares. This led to the company often having to stop production due to lack of raw materials. Affecting the company's production and business plans.

To ensure the continuous production of raw materials for VICO Quang Tri Company, Permanent Vice Chairman of the Provincial People's Committee Ha Sy Dong requested departments, branches and localities to quickly implement administrative procedures.

The Department of Agriculture and Rural Development accelerates procedures for converting forest use purposes. The Department of Natural Resources and Environment shall preside over granting additional exploitation areas within the areas licensed by the Ministry of Natural Resources and Environment; guide and support VICO Quang Tri Company in registering for inclusion in the annual land use plan list with an area guaranteed for each 5-year cycle, avoiding having to stop production while waiting for raw material areas for exploitation and production.

Le An



Source: https://baoquangtri.vn/kiem-tra-tien-do-trien-khai-du-an-khu-ben-cang-my-thuy-va-hoat-dong-san-xuat-tai-cong-ty-co-phan-dau-tu-va-khoang-san-vico-quang-tri-189103.htm

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product