Deputy Prime Minister Tran Hong Ha requested to remove weak contractors from Long Thanh airport project.

VTC NewsVTC News16/10/2023


On the afternoon of October 16, Deputy Prime Minister Tran Hong Ha led a Government delegation to inspect the actual progress of the Long Thanh International Airport project ( Dong Nai ).

According to Vietnam Airports Corporation (ACV), relevant units have urgently mobilized and gathered machinery and human resources to construct the bid packages.

The project site mobilized nearly 3,000 people and machinery and equipment to focus on constructing 4 main packages, including: Drainage leveling package; passenger terminal; runway and taxiway area; and connecting traffic package.

Representatives of the Ministry of Transport reported the progress of component projects at the Long Thanh airport project to Deputy Prime Minister Tran Hong Ha.

Representatives of the Ministry of Transport reported the progress of component projects at the Long Thanh airport project to Deputy Prime Minister Tran Hong Ha.

ACV is focusing on mobilizing machinery to prepare for peak construction when the rainy season ends in November 2023.

At the field trip, Deputy Prime Minister Tran Hong Ha said that Long Thanh airport is a century-old project, of historical significance to the country, so the project must meet the expectations and development of the transport infrastructure construction industry.

Currently, the important items have been basically implemented, the site has been fully handed over, and the legal conditions have been completed. Therefore, the Deputy Prime Minister requested ACV to closely develop a general schedule for the entire project. The projects in the project are closely related to each other, and the delay of one project will affect the progress of the other projects.

"Legality and discipline must be ensured. Contractors who do well will be encouraged and rewarded, those who do wrong will be punished, and weak contractors will be eliminated," Deputy Prime Minister Tran Hong Ha emphasized.

The Deputy Prime Minister also noted to avoid the situation of "drums beating one way and trumpets blowing the other", it is necessary to clarify the responsibilities of relevant units, and units must have documents on plans to implement assigned tasks sent to the Government .

In addition, ACV must take responsibility for the entire project, and ministries must take responsibility for the assigned tasks. By the end of October, the Ministry of Transport will submit to the Government a general plan for the construction of the entire Long Thanh airport project.

Tue Lam



Source

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product