Quang Ngai: Construction continues throughout Tet holiday on 4 border boarding school projects.

On February 15th, Mr. Vo Dai Tan, Director of the Project Management Board for Investment and Construction of Transportation, Civil and Industrial Works in Quang Ngai Province, stated that he had instructed contractors to deploy construction forces throughout the Tet holiday, striving to complete the four border boarding school projects before August 31st as planned.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng15/02/2026

Accordingly, Quang Ngai province is investing in the construction of four boarding schools for primary and secondary levels in the border communes of Ro Koi, Mo Rai, Sa Loong, and Duc Nong. These projects have a total of 151 classrooms, meeting the learning needs of approximately 5,164 students, with a total investment of over 870 billion VND.

At the construction site of the Rờ Kơi Commune Inter-level Boarding School (Primary and Secondary levels), workers are pouring concrete for the third floor of the boarding dormitory.

Â1.jpeg
Workers pour concrete for the third floor of the dormitory at Rờ Kơi Commune's Inter-level Boarding School (Primary and Secondary levels).
A3.jpeg
Construction of the Rờ Kơi Commune Inter-level Boarding School (Primary and Secondary) is being accelerated.

At the construction site of the Mo Rai Commune Inter-level Boarding School (Primary and Secondary levels), the contractor is focusing resources, machinery, and personnel on completing the foundation.

B1.jpeg
Construction workers are working at the construction site of the Mo Rai Commune Inter-level Boarding School (Primary and Secondary levels).
B2.jpeg
Mr. Vo Dai Tan, Director of the Project Management Board for Investment and Construction of Transportation, Civil and Industrial Works in Quang Ngai Province (on the left), inspects the construction site of the Mo Rai Commune Inter-level Boarding School (Primary and Secondary levels).
B4.jpeg
The Quang Ngai Provincial Project Management Board for the construction of transportation, civil, and industrial works (on the left) inspects and monitors the progress of the Mo Rai Commune Inter-level Boarding School (Primary and Secondary levels).

Mr. Le Van Hung, Deputy Director of Dat Viet Construction and Installation Services Co., Ltd. (the contractor for the Mo Rai Commune Inter-level Boarding School for Primary and Secondary Students), said that during the Lunar New Year holiday, the company deployed 25-30 workers to the construction site, ensuring their income, living conditions, accommodation, rest, and organizing New Year celebrations right at the site. After the 6th day of the Lunar New Year, the company will increase the workforce to further accelerate the progress.

B3.jpeg
Mr. Vo Dai Tan (center), Director of the Project Management Board for Investment and Construction of Transportation, Civil and Industrial Works in Quang Ngai Province, presents gifts and encourages the construction unit to arrange workers to work throughout the Tet holiday at the Mo Rai Commune Inter-level Boarding School (Primary and Secondary levels).

Source: https://www.sggp.org.vn/quang-ngai-thi-cong-xuyen-tet-4-cong-trinh-truong-noi-tru-bien-gioi-post838841.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Di sản

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Autumn in Hanoi

Autumn in Hanoi

Beautiful Vietnam

Beautiful Vietnam

Finish line

Finish line