Vingroup is mobilizing thousands of workers and machinery to work in "3 shifts, 4 teams" to achieve its goal of finishing in July 2027, in less than 20 months, aiming to become the fastest-built stadium in the world, breaking all records in the history of the global construction industry.

The massive construction site mobilized all resources, accelerating progress day and night.

Having lived in Thuong Phuc commune, Hanoi for 60 years, Mr. Pham Ngoc Phan has never seen his hometown change as rapidly as it is now. Just five months ago, the area was a vast expanse of land covered only in grass and water, but now it's a massive construction site, brightly lit all night long. Long lines of trucks carrying materials, machinery operating non-stop, and gigantic grandstands rising higher each day.

“Sometimes, when you wake up in the morning, the construction site looks completely different from the day before. The roads are being built very quickly, and the grandstands are getting taller and taller. Everyone around here is surprised by the incredibly fast pace of construction,” Mr. Phan recounted.

A1hfgshh.jpg
The area where the Hung Vuong Stadium is being built in Thuong Phuc commune was just an empty plot of land five months ago.

Construction began on December 19, 2025, and after exactly five months, the entire stadium site and auxiliary facilities have been leveled. The internal transportation system and main connecting routes are approximately 80% complete. The pile driving for the main structure is finished, while the foundation and first-floor slab are about 70% complete. The reinforced concrete grandstands are gradually taking shape.

A2ghdhđj.jpg
After a few months, the shape of Hung Vuong Stadium began to take form.

In June, the project will install the steel roof support structure – the most complex part. Vingroup aims to complete the roof by May 2027, before the entire project is finished in July of the same year, meaning it will only take 20 months to complete.

Simultaneously, a series of satellite projects are also being prepared for simultaneous implementation, such as a hotel of approximately 30 floors, a large-scale hospital with a sports medicine department, a complex of tennis and pickleball courts, and a 120-meter-wide boulevard directly connecting to the main traffic arteries in southern Hanoi.

A3hfdghdhd.jpg
The C grandstand area is nearing completion.