| The working group inspected the site clearance work in Thanh Thinh commune. |
The working delegation of the Deputy Minister of Construction inspected the results of site clearance (GPMB), construction at the beginning of the route; inspected the construction of section Km0 - Km9; the mobilization of construction sites of Na Deo - Km6+767, Na Ban - Km7+536, Na Can - Km8+390, Song Cau - Km9+251 bridges; the construction situation of QL.3 intersection, Khuoi Quan bridge - Km9+709; the construction scope of the roadbed and the planned arrangement of Thanh Van intersection; the construction scope of the roadbed (corresponding to the DT.41 - Bac Kan intersection); inspected Km28+800 - the final intersection of the route...
![]() |
| Deputy Minister of Construction Le Anh Tuan (third person from left to right) discussed some contents with the investor and representatives of local leaders at the construction site. |
Speaking at the locations and checkpoints along the route, Deputy Minister of Construction Le Anh Tuan directed contractors to continue to adhere to the progress committed to the investor, as well as the commitment to the locality. Accordingly, the foundation construction must be completed in June before the rainy season, the bridge work in September, and the ground work will be completed in November and December, striving to open the route by the end of the year.
![]() |
| The working group inspected at Km0 - Km9. |
The Deputy Minister of Construction directed that by December 31, the relocation of public works, such as power lines and fiber optic cables, must be completed; and that all site clearance work must be handed over to the project by the end of March. For the final intersection at Bac Kan ward, he suggested that the investor consider extending the acceleration and deceleration points to increase safety for traffic participants.
![]() |
| Taking advantage of favorable weather, contractors are speeding up construction progress on the section passing through Thanh Thinh commune. |
The Deputy Minister of Construction requested Thai Nguyen province to continue paying attention to resettlement work and arranging dumping sites for excess soil and rock, because these two issues directly affect the project's progress...
| Site clearance work: - The route length is 28.8km, 26.45km of which has been handed over to Project Management Board 2. Of which: Thanh Thinh Commune 10.62km/12.5km; Thanh Mai Commune 10.37km/10.77km; Bac Kan Ward 5.46km/5.53km, - The total number of households, individuals and organizations within the land acquisition area is about 1,624 households. Of these, 1,564 households have been paid; 60 households have not yet received the money. - Total recovered land area is 261.8 hectares, of which 250.85 hectares have been handed over to Project Management Board 2. |
Source: https://baothainguyen.vn/thoi-su-thai-nguyen/202511/thu-truong-bo-xay-dung-le-anh-tuan-kiem-tra-tien-do-du-an-cao-toc-cho-moi-bac-kan-c522616/