Prime Minister: Determined to open the expressway from Cao Bang to Ca Mau

Báo Tuổi TrẻBáo Tuổi Trẻ06/12/2024

The head of the Government requires that if there are any problems, it must be clearly stated what the problems are, where they are, who will solve them, and how long they will take to solve them; it must be clearly stated who is responsible if the implementation of the work is delayed.


Thủ tướng: Quyết tâm thông tuyến cao tốc từ Cao Bằng tới Cà Mau - Ảnh 1.

Prime Minister Pham Minh Chinh - Photo: VGP

On the afternoon of December 6, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired the 15th meeting of the Steering Committee.

According to the report of the Ministry of Transport, in recent times, ministries, branches and localities have made efforts and proactively overcome difficulties to implement work, most projects are being implemented closely following the set plan.

Target to complete at least 3,000km of highway

With the strong direction of the Prime Minister at the 14th meeting, localities have actively implemented site clearance work and there have been significant changes, with the handed-over area increasing by over 20%.

However, in some projects, the implementation progress is still slow, due to some difficulties and problems such as the remaining cleared area is mainly residential land, the implementation of determining the origin and compensation plan is complicated, so the volume in some localities is still very large, not meeting the requirements...

In his concluding remarks, Prime Minister Pham Minh Chinh said that 2025 is of special importance. Therefore, it is necessary to achieve the goal of completing at least 3,000km of expressway, opening the expressway from Cao Bang to Ca Mau, this is also a legal goal, included in the resolutions of the Party and the National Assembly.

In implementing the project, the Prime Minister emphasized the need to ensure progress, quality, technique, aesthetics, safety, and environmental sanitation. In particular, bidding should not be used as a safe haven for "blue and red troops".

"When checking and inspecting, the bidding is very grand and takes a lot of time, but there are still violations, officials still have to be disciplined and dealt with, and the project still drags on and costs increase," the Prime Minister said.

The head of the Government requires that if there are any problems, it must be clearly stated what the problems are, where they are, who will solve them, and how long they will take to solve them; it must be clearly stated who is responsible if the implementation of the work is delayed.

Localities must mobilize the combined strength of the entire political system, forces, people and businesses in the area, assigning work to local subcontractors to create conditions for local businesses to grow.

Anti-corruption, negativity

Investors must not divide bidding packages into smaller ones; prevent corruption and negativity in bidding, right from the method and approach; contractors who do well will be given priority to implement the next phase, the next construction, and the next project.

Mobilize the entire political system to participate, strengthen the mobilization of people to complete the handover of project sites on schedule; pay attention to ensuring people's lives. Contractors increase machinery, equipment, and construction personnel with the spirit of "overcoming the sun, overcoming the rain, not losing to storms".

Ministries, branches, agencies and localities review regulations to promptly overcome shortcomings in investment procedures, prevent corruption, negativity, fight embezzlement and especially practice thrift and prevent waste.

Tien Giang, Ben Tre, Vinh Long, Dong Nai provinces completed procedures for granting mines and increasing mine capacity; Lam Dong province urgently completed approval of the Tan Phu - Bao Loc and Bao Loc - Lien Khuong projects; Ho Chi Minh City People's Committee urgently completed the task of exploiting the Ben Thanh - Suoi Tien urban railway.

Regarding the investment project to build Long Thanh International Airport and connecting infrastructure, the Prime Minister requested urgent implementation of assigned tasks after the Prime Minister visited the construction site on December 3.



Source: https://tuoitre.vn/thu-tuong-quyet-tam-thong-tuyen-cao-toc-tu-cao-bang-toi-ca-mau-20241206211913918.htm

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product