On the afternoon of June 22, Prime Minister Pham Minh Chinh inspected, visited and encouraged construction workers at the 500kV transmission line circuit 3 Quang Trach - Pho Noi project in Thanh Hoa province. Accompanying him were Mr. Do Trong Hung, Secretary of Thanh Hoa Provincial Party Committee and leaders of ministries, departments, branches and Vietnam Electricity Group (EVN).
Under the hot weather, the Prime Minister inspected and encouraged workers at the 500kV transformer station in Thieu Phuc commune, Thieu Hoa district. According to EVN's report, as of June 20, compensation and site clearance work had been completed, handing over the site for all 1,177/1,177 column foundation locations. Regarding the route corridor, 513/513 anchorage spaces had been handed over. Regarding the supply of steel columns, there were a total of 75 bid packages implemented by 18 contractors/joint ventures, including 1,177 column locations, equivalent to nearly 139,000 tons of steel. Currently, materials and equipment for the projects have been basically handed over.
Regarding construction, the foundations have been cast at all 1,177/1,177 locations, 686/1,177 pole locations have been erected, 408/1,177 locations are being erected, 80/513 anchorage spans have been completed, and 46/513 anchorage spans are being pulled. For the remaining tasks such as erecting poles and pulling wires, EVN and EVNNPT continue to make efforts to overcome adverse weather conditions, implementing many solutions such as gathering materials and equipment to the construction site, adjusting work schedules according to the weather, arranging accommodation for workers near the construction site, increasing mechanical construction at locations with convenient traffic, etc.
Visiting and presenting gifts to workers, engineers and laborers at the construction site, Prime Minister Pham Minh Chinh emphasized: The 500kV transmission line project circuit 3 Quang Trach - Pho Noi is an important project in supplying electricity to the regions. Therefore, the Prime Minister requested the construction units to be highly determined, make great efforts, and take drastic actions 'clearly identifying people, clearly identifying work, clearly identifying time, clearly identifying products', and the investor must promptly and adequately allocate capital sources.
The Prime Minister requested attention to the anchorage areas and the work related to forest land clearance. During the construction process, it is necessary to seek the support of local people and stick with the people because strength comes from here. Large projects must also be implemented in this direction.
The Prime Minister highly appreciated the progress of the construction of the Thanh Hoa 500kV Transformer Station, affirming that this is a testament to 'turning nothing into something, turning the impossible into possible, turning the difficult into the easy'. The Prime Minister welcomed the deployment of more union members to support the project and stated: Through these projects, people will understand and be more impressed with the image of cadres and workers in the Electricity and Construction sectors working day and night on the project.
Handing over to the workers OCOP products and Thanh Hoa specialty fruits that people had donated, the Prime Minister thanked all forces participating in the project, especially the human resources of units of the electricity sector across the country who came to support the project. With the spirit of 'overcoming the sun, overcoming the rain', 'only working, not backing down', the Prime Minister hoped that the construction unit would make every effort to complete the project by June 28.
On the local government side, the Prime Minister asked the leaders of Thanh Hoa province to pay attention to, visit and encourage units participating in construction projects in the province.
On the afternoon of June 22, the Prime Minister continued to inspect and encourage workers at the position of column VT117 (in a cluster of 7 support columns and 2 anchor columns, 8 column intervals) of the Nam Dinh I - Thanh Hoa transmission line project and inspected the construction status of the cable pulling at anchor intervals 109-117 in Cau Loc commune, Hau Loc district.
Source: https://daidoanket.vn/thu-tuong-pham-minh-chinh-vuot-nang-thang-mua-co-gang-dua-du-an-500kv-mach-3-ve-dich-truoc-28-6-10283899.html