Spider-men in the air

Việt NamViệt Nam09/06/2024

The 500kV Line 3 project from Quang Trach (Quang Binh) to Pho Noi ( Hung Yen ) is entering a critical phase with time being counted by the day. Sticking to the project's schedule, regardless of the sun or rain, the technical team regularly works on hundreds of meters high electric poles and hangs in mid-air to perform especially difficult operations when erecting poles and pulling wires.

Spider-men in the air

According to a representative of the National Power Transmission Corporation, the 500 kV Circuit 3 Transmission Line Project from Quang Trach ( Quang Binh ) to Pho Noi (Hung Yen) always has about 8,000-10,000 officers, engineers, workers, and laborers working at the construction site.

Spider-men in the air

Installing the line positioning frame is the final step to complete the wire-pulled anchorages.

Spider-men in the air

Hanging in the air, the "spiders" are struggling to work in harsh weather conditions in Thanh Hoa without any means of protection.

Spider-men in the air

Contractor workers of Phuong Hanh Company Limited check the final items at column 76 in Nga Giap commune (Nga Son).

Spider-men in the air

On hot days, workers often start working from 5:30 a.m. and take turns every 2-3 hours to ensure their health.

Spider-men in the air

The wire pulling construction teams are professional forces, mobilized from many provinces to Thanh Hoa.

Spider-men in the air

Technical workers of the National Power Transmission Corporation increase manpower to install power lines for contractors.

Spider-men in the air

The special pose of the "spider-man" installing insulators in package 11 through Dai Loc commune (Hau Loc).

Spider-men in the air

Despite working at high intensity and in harsh weather conditions, technical workers are all very optimistic because they are honored to contribute to a key project of the whole country.

Spider-men in the air

Workers of Phuong Hanh Company Ltd. planted the national flag on the completed power line section passing through Nga Giap (Nga Son).

The 500 kV line 3 in Thanh Hoa province is 131 km long, passing through 11 districts and towns in the province, including 299 pole foundation positions and 137 anchorages. Currently, 243 steel poles have been erected on the line in Thanh Hoa province; 15 anchorages have been completed and 18 anchorages are being pulled.

Lighthouse - Tung Lam


Source

Comment (0)

No data
No data

Same tag

Same category

Ha Giang - the beauty that holds people's feet
Picturesque 'infinity' beach in Central Vietnam, popular on social networks
Follow the sun
Come to Sapa to immerse yourself in the world of roses

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product