After the upgrade, the Nha Trang railway

Báo Xây dựngBáo Xây dựng22/02/2024


After more than a year since construction began, contractors have completed the replacement of sleepers and rails, and the renovation of the railway's superstructure. Some remaining work includes reinforcing the roadbed and constructing longitudinal drainage ditches.

The Nha Trang - Saigon railway renovation and upgrade project (phase 2) commenced at the end of January 2023.

Sau nâng cấp, đường sắt Nha Trang - Sài Gòn đạt tốc độ hơn 80km/h- Ảnh 1.

Two packages of the railway renovation and upgrade project on the Nha Trang - Saigon section are ahead of schedule (pictured: construction workers at the Thap Cham section).

The project comprises 3 construction packages, with a total estimated investment of over 1,098 billion VND.

According to Mr. Dang Xuan An, a consulting supervisor from Hanoi Transportation Construction Consulting Joint Stock Company, the contractor has completed the main line upgrade items, replacing the rails and sleepers with new ones.

Sau nâng cấp, đường sắt Nha Trang - Sài Gòn đạt tốc độ hơn 80km/h- Ảnh 2.

A section of railway passing through Thuan Bac district (Ninh Thuan province) has had its rails and sleepers replaced.

You may also like
Huggies proactively tests its products and found no formamide in diaper samples in Vietnam.
Huggies proactively tests its products and found no formamide in diaper samples in Vietnam.In response to consumer concerns regarding information related to formamide in baby diapers, Kimberly-Clark Vietnam Co., Ltd. announced that it has proactively sent samples of Huggies diapers circulating in Vietnam for independent testing. The results showed no formamide was detected in the tested samples.
10% discount on North-South passenger train tickets starting July 1st.
10% discount on North-South passenger train tickets starting July 1st.VHO - In order to share the benefits with passengers, the railway industry is implementing a 10% reduction in ticket prices for North-South passenger trains from July 1st to August 16th, 2026.
Pilot program to allow civil servants, public employees, and workers in Hai Phong City to commute to work by train.
Pilot program to allow civil servants, public employees, and workers in Hai Phong City to commute to work by train.Vietnam Railways Corporation has announced that it will conduct trial runs of a pair of trains to transport officials and employees of Hai Phong City to and from work.

Specifically, the Kà Rôm - Phước Nhơn, Phước Nhơn - Tháp Chàm, and Tháp Chàm - Hòa Trinh sections passing through Ninh Thuận province have basically completed the superstructure construction.

"At the Ka Rom - Phuoc Nhon section (Km 1382+246), the contractor is currently constructing 6km of drainage ditches along the route to expedite technical acceptance and handover to the investor," Mr. An said.

According to a leader of Thuan Hai Railway Joint Stock Company (the unit managing the railway section through Ninh Thuan), trains can currently travel at a speed of 80 km/h, and after acceptance testing, the train speed may be further increased.

Sau nâng cấp, đường sắt Nha Trang - Sài Gòn đạt tốc độ hơn 80km/h- Ảnh 3.

An automatic barrier has been installed at a railway crossing in Ninh Thuan province.

Mr. Nguyen Van Diep, in charge of the Nha Trang - Saigon section renovation and upgrade project (under the Railway Project Management Board), said that packages XL01 and XL02 are ahead of schedule compared to the contract, with 100% of the planned capital disbursement achieved.

The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.
The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.On the afternoon of July 2nd, at the Ministry of Foreign Affairs headquarters, Mr. Le Cong Dung, Director of the State Protocol and Foreign Interpretation Department, received a copy of the Letter of Credence from Ms. Jennifer Wicks, Ambassador of the United States of America to Vietnam.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.From June 28-30, the Vietnamese Ambassador to the United States, Nguyen Quoc Dung, paid a visit and worked in Minnesota.
Vietnam encourages US businesses to expand investment in high technology.
Vietnam encourages US businesses to expand investment in high technology.On the morning of June 26th, at the Government Headquarters, Deputy Prime Minister Ho Quoc Dung received Mr. Jeff Place, Supply Chain Director of Coherent Group (USA). During the meeting, the Deputy Prime Minister affirmed that Vietnam encourages US businesses to expand investment, especially in high-tech, innovation, and semiconductor industries.

Due to the unique construction requirements, which involve ensuring train safety while construction is underway, the contractor has focused on a phased approach. Because the project depends on the train schedule, each section is completed simultaneously to ensure it is ready for operation and maintains the designed speed.

Currently, the upgrade and expansion projects for Song Than and Di An stations are being urgently implemented.

Upon completion, the project will ensure traffic safety, improve the quality of railway infrastructure, and enhance the capacity for transporting passengers and goods.



Source: https://www.baogiaothong.vn/sau-nang-cap-duong-sat-nha-trang-sai-gon-dat-toc-do-hon-80km-h-192240221193108315.htm

Trending by Tag

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
New planting season

New planting season

Go to the market

Go to the market

SPRING FESTIVAL

SPRING FESTIVAL