(HBO) – The project of high-class ecological urban area, resort and entertainment at Lake Kha and Doi Thung in Quy Hoa commune (Lac Son) are two key projects that are expected to create tourism products. , high quality services, contributing to the economic restructuring of the province. The province and functional agencies, together with Lac Son district are focusing on directing solutions to remove difficulties in site clearance work, carrying out relevant procedures to start the project as planned.
Planning area of Kha lake project, Quy Hoa commune (Lac Son).
Lac Son district has established a steering committee, assigning tasks to members. Up to now, the steps to announce the zoning planning and decide on the investment policy of the project have been implemented in accordance with regulations. The district strengthens propaganda, advocacy, captures people's thoughts and aspirations, and organizes contact and dialogue to implement the steps of land acquisition, site clearance, construction of resettlement areas, publicity of planning, etc. consult the population community… according to regulations.
In early March 3, Lac Son District People's Committee held a conference to support promotion and create jobs for people in Quy Hoa commune. Next, the investor (Hoa Binh Sun Co., Ltd.) organized for 2023 students who are residents of Kha and Doi hamlets to study and train in tourism in Hanoi. At the beginning of June 37, continue to organize for 6 trainees who are commune women's members to take cooking and baking classes in the commune. Sun Group sponsors the entire cost of studying, accommodation and meals. After graduating, Sun Group will accept to work at tourist resorts under the system.
For site clearance and construction of the cemetery, Quy Hoa Commune People's Committee is currently surveying and selecting a location for implementation. Regarding the results of the land and property review for the site clearance of the Kha lake project, 84 households with houses had to move; So far, all 84 households have been reviewed and counted and are preparing an estimate of the compensation plan. The district has completed the census of agricultural land, but there are not enough grounds to publish the data.
For the project at Doi Thung, the households have not yet agreed and coordinated to review and inventory land and assets, so it has not been implemented. For the project households in the Kha lake area, they have basically agreed on the site clearance to implement the project, but it is proposed to consider adjusting the unit price to be equal to the unit price of Tan Lap and Tuan Dao communes.
According to Mr. Bui Van Khanh, Vice Chairman of Lac Son District People's Committee, the district is continuing to dialogue with officials, party members and people to propagate and mobilize support for the project. However, there are still difficulties and problems. Although the unit price of property compensation has been detailed and specified by the Provincial People's Committee, in fact many types of assets of the people are larger than the prescribed norm. Many property items still do not have a unit price to apply the compensation price, such as yellow apricot trees, myrtle trees, forest tea trees; There are plants that can both harvest wood and harvest fruits, but in the new unit price, they are only counted for harvesting for wood such as crocodile, filling, doi ...
For households that have not yet agreed to the project implementation policy in Doi Thung due to the limited legal understanding of the people, which leads to some bad objects taking advantage and inciting opposition; The district continues to propagate so that people can better understand the role and meaning the project brings to the people of Quy Hoa commune in particular and Lac Son district in general. Consider measures to handle objects that propagate and incite people to oppose the project implementation policy. Regarding the unit price, volume and type of property to be compensated, after completing the declaration and tally, the District People's Committee will summarize and classify for handling. command.
Lac Son district requested departments and branches to speed up the consultation, appraisal and submission to the Provincial People's Committee for approval of investment policies and soon implement bidding to select investors to build technical infrastructure of the resettlement area according to regulations. approved planning contents; competent authorities to change the purpose of using rice land to implement the project.
LC