Construction is being rushed on the La Son - Hoa Lien expressway upgrade project.

TPO - With the rainy and stormy season approaching, the Ho Chi Minh Highway Project Management Board has directed contractors to increase manpower and equipment to "race against time" and accelerate construction on the La Son - Hoa Lien section of the expressway expansion project passing through Hue City and Da Nang.

Báo Tiền PhongBáo Tiền Phong20/08/2025

tp-1-chay-nuoc-rut-cao-toc-la-son-hoa-lien.jpg
The project to expand the eastern section of the North-South Expressway from La Son to Hoa Lien is one of the key components of the eastern North-South Expressway, aiming to gradually improve the transportation infrastructure in the Central region, meet transportation needs, and alleviate congestion on National Highway 1.
tp-2-chay-nuoc-rut-cao-toc-la-son-hoa-lien.jpg
The project is managed by the Ho Chi Minh Highway Project Management Board. This expressway is approximately 65km long, with 4 lanes, a road surface widened to 22m, and a design speed of 60-80km/h according to expressway standards. The project passes through two localities: Hue City and Da Nang, with a total investment of over 3,010 billion VND from the State budget; the majority of which is allocated to construction and related technical infrastructure works...
tp-3-chay-nuoc-rut-cao-toc-la-son-hoa-lien.jpg
The project commenced in Hue City on May 29th, with a construction period of 240 days.
tp-3a-chay-nuoc-rut-cao-toc-la-son-hoa-lien.jpg
The main contract package XL01 - construction of the La Son - Hoa Lien section - has a contract value of over 2,700 billion VND.
tp-4-chay-nuoc-rut-cao-toc-la-son-hoa-lien-1.jpg
tp-4-chay-nuoc-rut-cao-toc-la-son-hoa-lien-2.jpg
According to the plan, the project must be completed by early 2026. Representatives from the Ho Chi Minh Highway Project Management Board stated that, to date, land clearance along the route has basically met the requirements for a 4-lane road from the previous La Son - Tuy Loan project; currently, only additional land clearance is needed for some local roads and canal extensions.
tp-5-chay-nuoc-rut-cao-toc-la-son-hoa-lien-2.jpg
tp-5-chay-nuoc-rut-cao-toc-la-son-hoa-lien-3.jpg
tp-5-chay-nuoc-rut-cao-toc-la-son-hoa-lien-1.jpg
tp-5-chay-nuoc-rut-cao-toc-la-son-hoa-lien-4.jpg
You may also like
Waterway traffic accident at pillar T5, Song Lo Bridge.
Waterway traffic accident at pillar T5, Song Lo Bridge.According to information from the Song Lo Bridge Repair Project Management Board, a waterway traffic accident occurred at 7:00 AM this morning (June 29th), resulting in a serious collision between two vessels. The collision site was identified at pillar T5, in the area of ​​the Song Lo Bridge currently undergoing repairs.
Invest in the connecting road section from Provincial Road 601 to Ho Chi Minh Highway, specifically the La Son - Hoa Lien section.
Invest in the connecting road section from Provincial Road 601 to Ho Chi Minh Highway, specifically the La Son - Hoa Lien section.The People's Committee of Da Nang City has just issued a decision approving the project for the connecting section from Provincial Road 601 to Ho Chi Minh Highway, specifically the La Son - Hoa Lien section (Hai Van Ward), with a total investment of over 225 billion VND. The project is scheduled for implementation from 2025 to 2028.
Vinachem promotes the development of the chemical materials industry.
Vinachem promotes the development of the chemical materials industry.On July 2nd, Vinachem, in collaboration with the Department of Sectoral Economics and the Central Committee for Policy and Strategy, co-organized the Workshop on the Development of the Materials Industry in Vietnam's Chemical Sector.
Currently, construction work is mainly focused on roadbeds, bridges, drainage culverts, and traffic safety systems. Construction teams are deployed simultaneously, running continuously in three shifts per day to ensure the project meets the set deadline and to race against time before the rainy season.
tp-6-chay-nuoc-rut-cao-toc-la-son-hoa-lien-1.jpg
tp-6-chay-nuoc-rut-cao-toc-la-son-hoa-lien-2.jpg
On the construction site, the contractors mobilized 54 construction teams with more than 570 workers, 76 engineers, and hundreds of pieces of equipment and machinery to participate in the simultaneous construction.
tp-7-chay-nuoc-rut-cao-toc-la-son-hoa-lien-3.jpg
tp-7-chay-nuoc-rut-cao-toc-la-son-hoa-lien-2.jpg
tp-7-chay-nuoc-rut-cao-toc-la-son-hoa-lien-1.jpg
tp-7-chay-nuoc-rut-cao-toc-la-son-hoa-lien-5.jpg
Notably, along the entire project route, 50 bridges have been expanded with the addition of new sections, combining them with existing sections.
tp-8-chay-nuoc-rut-cao-toc-la-son-hoa-lien.jpg
In many of the additional single-section bridges, the volume of bored piles – one of the complex items for the construction units – has reached 100% completion, such as the Ta Lang - Gian Bi bridge at Km51+741.79 with 21/21 piles completed; the bridge at Km41+950 with 10/10 piles completed; the bridge at Km60+986 with 14/14 piles completed…
tp-9-chay-nuoc-rut-cao-toc-la-son-hoa-lien.jpg
Representatives from the Ho Chi Minh Highway Project Management Board stated that, taking advantage of the dry weather, contractors are currently accelerating the progress of the project. The Board will continue to closely supervise the progress and quality of the work carried out by contractors and related units, ensuring absolute safety during the upcoming rainy season, and striving to complete the La Son - Hoa Lien expressway expansion project on schedule by early next year.
Construction begins on the Ho Chi Minh City - Moc Bai expressway and the Western section of the North-South expressway.

Construction begins on the Ho Chi Minh City - Moc Bai expressway and the Western section of the North-South expressway.

The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.
The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.On the afternoon of July 2nd, at the Ministry of Foreign Affairs headquarters, Mr. Le Cong Dung, Director of the State Protocol and Foreign Interpretation Department, received a copy of the Letter of Credence from Ms. Jennifer Wicks, Ambassador of the United States of America to Vietnam.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.From June 28-30, the Vietnamese Ambassador to the United States, Nguyen Quoc Dung, paid a visit and worked in Minnesota.
Vietnam encourages US businesses to expand investment in high technology.
Vietnam encourages US businesses to expand investment in high technology.On the morning of June 26th, at the Government Headquarters, Deputy Prime Minister Ho Quoc Dung received Mr. Jeff Place, Supply Chain Director of Coherent Group (USA). During the meeting, the Deputy Prime Minister affirmed that Vietnam encourages US businesses to expand investment, especially in high-tech, innovation, and semiconductor industries.
Over 537 billion VND will be invested in the project to connect National Highway 14B with the Da Nang - Quang Ngai Expressway.

Over 537 billion VND will be invested in the project to connect National Highway 14B with the Da Nang - Quang Ngai Expressway.

Inside the 1 trillion VND tunnel through the mountain on the Ha Tinh-Quang Tri expressway, soon to open to traffic.

Inside the 1 trillion VND tunnel through the mountain on the Ha Tinh-Quang Tri expressway, soon to open to traffic.

Source: https://tienphong.vn/gap-rut-thi-cong-du-an-len-doi-cao-toc-la-son-hoa-lien-post1770983.tpo

Trending by Category

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Hmong Flute Festival

Hmong Flute Festival

Happiness in the mountains and forests

Happiness in the mountains and forests

Celebrating the Lunar New Year at Phu Yen General Hospital

Celebrating the Lunar New Year at Phu Yen General Hospital