Implementation of construction of Quang Tri 500 kV transformer station and connection lines
On March 20, 3, in Hai Lang district, Quang Tri province, EVNNPT and the Central Power Project Management Board (CPMB) organized the construction of the Quang Tri 2024 kV transformer station and connection lines. Quang Tri – turn to Vung Ang – Da Nang.
Strengthen the assurance of electricity supply for Quang Tri province and the region
The Quang Tri 500 kV transformer station project and the Quang Tri - Vung Ang - Da Nang connection line were assigned by Vietnam Electricity Group (EVN) to the National Power Transmission Corporation (EVNNPT) as the investor. , Central Power Project Management Board (CPMB) manages the project on behalf of EVNNPT.
The project has a total investment of 965 billion VND. This is an urgent power project in the National Power Development Plan with the goal of ensuring power supply for regional loads; release the capacity of power plants in the region into the national grid system; Improve reliability and safety of power supply to the regional power grid.
The total investment of the project is 965 billion VND. |
The 500 kV transformer station was built in Hai Truong commune, Hai Lang district, Quang Tri province, about 500 km northeast of the existing Vung Ang - Da Nang 2,5 kV line. The station has transmission voltage levels of 500 kV and 220 kV, transformer capacity includes 02 500 kV - 2x(3×300) MVA transformers installed outdoors, the first phase is installed in advance of 01 transformer (3× 300) MVA.
The 500 kV line connecting the 500 kV Quang Tri substation is connected in and out on the existing 500 kV Da Nang - Ha Tinh and Da Nang - Vung Ang lines, including branch A about 3,1 km long and branch B long. about 2,8 km.
The 220 kV line connecting the 500 kV Quang Tri substation is connected in and out on the 220 kV Dong Ha - Hue line and the existing Dong Ha - Phong Dien line including branch A about 3,2 km long and branch B about 2,9 km long.
In recent times, aware of the importance of the project, CPMB has urgently implemented procedures for selecting contractors for related bidding packages of the project. Along with that, with the attention and direction of the Provincial Party Committee, Quang Tri Provincial People's Committee, departments, branches, and localities, EVN, EVNNPT, and CPMB have completed procedures to implement the project's construction.
Efforts to ensure project progress
Speaking at the construction implementation ceremony, EVNNPT Member Board of Directors Vo Hoai Nam thanked the close attention and direction of the Quang Tri provincial government; The support and coordination of departments, branches and districts as well as the people who gave up land for EVNNPT to implement the project.
EVNNPT's leaders hope to continue to receive the attention and support from authorities at all levels as well as people in the province so that EVNNPT's projects deployed in the area will be completed, constructed and operated on schedule.
Project Model. |
EVNNPT leaders praised CPMB for their efforts and good coordination with the authorities of Quang Tri province and Hai Lang district in agreeing on route alignment, design approval, compensation for site clearance... to organize and implement the construction project. project work. At the same time, CPMB is required to focus on management and administration, closely monitor quality, and coordinate well with local authorities during the construction process so that the project is completed on schedule and strictly complies with regulations. law.
EVNNPT leaders also requested construction contractors to fully arrange human resources, materials, vehicles, machinery and equipment on the construction site, take advantage of favorable weather, and be ready to accelerate progress. In which, proactively coordinate with CPMB and local authorities at all levels in compensation and site clearance for construction, promptly reflecting difficulties so that all parties can participate in solving them; Organize construction with the goal of acceptance and energizing in the second quarter of 2025.
The project quality supervision consulting unit arranges forces to supervise and accept construction steps, ensuring the construction progress of construction contractors. Implement immediate acceptance of items once completed to shorten the acceptance schedule for completion of energization and handover. The design consulting unit sends author supervisors to be regularly present at the site to promptly handle arising problems and ensure the contractor's construction progress.
Mr. Le Duc Tien, Vice Chairman of the People's Committee of Quang Tri province, said that the province is always aware of the importance and urgency of the Quang Tri 500 kV transformer station project and the connection line passing through the province and has instructed Leading departments, branches and localities to actively participate to hand over the site to the investor to implement the project. At the same time, we commit to always accompany and support work sharing with the Electricity industry to work together to complete the Project on schedule.
Mr. Tien also requested the departments and branches of the People's Committee of Hai Lang district to coordinate in completing procedures for handing over details of the line, promoting propaganda to the people, to prevent houses and structures from arising in the corridor of the line. it has come to an agreement; Approve the unit price of compensation for site clearance; create maximum conditions for investors in compensation work, meeting project progress goals; ensure enough land fund for project implementation; create conditions to support construction units related to compensation for construction; Allow construction units to use inter-village, inter-commune, inter-district roads... to transport materials and equipment for construction with the highest goal of completing the project on schedule.
Quang Tri 500kV Transformer Station Project and connection lines
– Investor: National Power Transmission Corporation (under EVN);
– Project management and administration: Project Management Board of power projects in the Central region;
– Design consulting unit: Electricity Construction Consulting Joint Stock Company 2;
– Verification consulting unit: Institute of Energy;
– Construction and installation unit:
+ Construction and installation of transformer station (not including installation of 500kV transformer): Joint venture contractor PC1 Thang Long Joint Stock Company and Alphanam E&C Joint Stock Company.
+ Construction and installation of connection lines: Joint venture of Viet Trung Investment and Construction Joint Stock Company and YK Construction and Trading Company Limited
+ Unit installing transformers and measuring line parameters: Power Transmission Technical Services Company.
– Operational management unit: Power transmission company 2.