Working while waiting for the land to be available.

Người Đưa TinNgười Đưa Tin31/10/2023


Late in the afternoon of October 30, 2023, we were present at the construction site of the Lai Xuan Bridge project connecting Thuy Nguyen District, Hai Phong City, with Dong Trieu Town, Quang Ninh Province. This is the second bridge crossing the Da Bach River (also known locally as the Da Bac River) connecting Hai Phong and Quang Ninh, along with the Lai Xuan Bridge.

According to observations, on the Dong Trieu town side in Quang Ninh province, the project remains stalled. On the Thuy Nguyen district side in Hai Phong city, the contractor is busy constructing a section over 200 meters long, stretching from the edge of the Da Bach river to the base of the dike.

Real Estate - 500 billion VND bridge connecting Hai Phong and Quang Ninh: Construction is underway while awaiting land acquisition.

Construction of the bridge piers for the Lai Xuan Bridge Project in Lai Xuan commune, Thuy Nguyen district, Hai Phong city (Photo: Sinh Pham).

Speaking to Nguoi Dua Tin about this situation, Mr. Dinh Duc Duy - representative of the unit supervising the Lai Xuan Bridge construction investment project, said that due to the lack of land handover, the contractor has not been able to organize the construction of the bridge approach road and the bridge on the Quang Ninh province side, even though they have ready manpower and have gathered some machinery and materials.

On the Hai Phong side, since the beginning of September 2023, due to the handover of additional land with a length of approximately 200 meters from position T4 to T7, the contractor has been urgently constructing the bridge piers. Previously, due to the lack of available land, from February to September 2023, the contractor only managed to construct the foundations of piers T9 and T8.

“Immediately after the project commenced on February 2, 2023, the contractor concentrated manpower, machinery, and materials for construction. Due to a lack of available land, nearly nine months after the commencement date, only about 20% of the work has been completed, falling behind schedule. For the project to be completed by the end of 2024, the local authorities must hand over all cleared land to the contractor in 2023,” Mr. Dinh Duc Duy informed.

Real estate - 500 billion VND bridge connecting Hai Phong with Quang Ninh: Construction is underway while waiting for land acquisition (Figure 2).

Lai Xuan Bridge is the second bridge over the Da Bach River connecting Hai Phong and Quang Ninh (Photo: Sinh Pham).

You may also like
Hue City authorities have decided to replace the investor for the delayed 1.143 billion VND road project.
Hue City authorities have decided to replace the investor for the delayed 1.143 billion VND road project.The leaders of the Hue City People's Committee have agreed to replace the investor of the 1.143 billion VND To Huu Road extension project to Phu Bai Airport, which is behind schedule, in order to improve management efficiency and accelerate project progress.
Thanh Hoa province directs the removal of obstacles to stalled projects.
Thanh Hoa province directs the removal of obstacles to stalled projects.The People's Committee of Thanh Hoa province has issued a plan to implement a special mechanism for resolving land-related issues, removing obstacles to stalled projects, and creating momentum to promote development.
Staying home all day is still comfortable in the summer: The secret lies in the doors, not just the air conditioner.
Staying home all day is still comfortable in the summer: The secret lies in the doors, not just the air conditioner.The main door is the "culprit" that makes the air conditioner run at full capacity but the house still feel stuffy. Eurowindow's EA60i, EA68i thermal break technology and Low-E double-glazed windows help block heat at the source, providing a sustainably cool, quiet, and energy-efficient space throughout the summer.

According to information from the People's Committee of Hai Phong City, Resolution No. 20/NQ-HĐND dated August 12, 2021, of the City People's Council decided on the investment policy for the Lai Xuan Bridge construction project and the renovation and expansion of Provincial Road 352. The project was approved by the People's Committee of Hai Phong City in Decision No. 2272/QĐ-UBND dated July 13, 2022.

The project has a total investment of over 1,300 billion VND and commenced construction on February 2, 2023. Of this, the construction of the Lai Xuan Bridge (Lai Xuan Bridge Project) alone accounts for nearly 520 billion VND. The Hai Phong City People's Committee assigned the Hai Phong City People's Committee to act as the investor's representative for the project.

The Lai Xuan Bridge project includes the following components: a bridge over the Da Bach River with a length of over 840 m, a main bridge and approach bridge width of 12 m with reinforced concrete structure; and approach bridges and access roads at both ends of the bridge with a length of nearly 1.6 km.

According to Mr. Do Tuan Anh, General Director of the Hai Phong Investment and Construction Project Management Board for Transportation Works, due to a lack of available land, as of October 27th, the contractor had only completed 104 billion VND worth of contract work out of a total of nearly 520 billion VND (approximately 20%).

Of these, 67 bored piles have been completed, and site leveling is currently underway for pier T4, bored piles for piers T5 and T7, pier shaft construction for T6, T8, and T9, and casting of super T girders.

To complete and put the project into operation by the end of 2024, the Hai Phong Investment and Construction Project Management Board for Transportation Works requests the authorities of Thuy Nguyen District, Hai Phong City, and Dong Trieu Town, Quang Ninh Province, to accelerate land clearance work and promptly hand over all cleared land to the construction contractor.

Real estate - 500 billion VND bridge connecting Hai Phong with Quang Ninh: Construction is underway while waiting for land acquisition (Figure 3).

Contractors are busy working on the sections where the land has been handed over for the Lai Xuan Bridge Project (Photo: Sinh Pham).

Strengthening the friendship between Vietnam and the United States.
Strengthening the friendship between Vietnam and the United States.On July 3rd, as part of the Pacific Partnership - Friends of the Pacific 2026 program, the U.S. Army Pacific delegation, led by Lieutenant General Joel Vowell, Deputy Commander of the U.S. Army Pacific, paid a courtesy visit to the Quang Tri Provincial Military Command.
The U.S. Army Pacific delegation visits the Quang Tri Provincial Military Command.
The U.S. Army Pacific delegation visits the Quang Tri Provincial Military Command.2026 marks the first time the Pacific Partnership-Friends of the Pacific program will be jointly organized in Quang Tri, creating a large-scale cooperation framework with 25 activities.
The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.
The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.On the afternoon of July 2nd, at the Ministry of Foreign Affairs headquarters, Mr. Le Cong Dung, Director of the State Protocol and Foreign Interpretation Department, received a copy of the Letter of Credence from Ms. Jennifer Wicks, Ambassador of the United States of America to Vietnam.

For a long time, travel between the residents of the area surrounding the project has been very inconvenient, mainly via the Lai Xuan ferry. The investment by Hai Phong City in the Lai Xuan bridge construction project and the renovation and expansion of provincial road 352 fulfills the aspirations of the people.

In addition, it contributes to creating an inter-regional transportation network, meeting the transportation needs between industrial zones and clusters in Thuy Nguyen district and Dong Trieu town in particular, and between Hai Phong and Quang Ninh in general.

At the same time, the project aims to gradually improve the transportation network of Hai Phong City, Quang Ninh Province, and the Northern key economic region. This will contribute to the socio-economic and cultural development of the localities in the project area .



Source

Trending by Category

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Happiness in the highlands

Happiness in the highlands

Together we reach the finish line. The elderly athlete who ran 42km received timely encouragement.

Together we reach the finish line. The elderly athlete who ran 42km received timely encouragement.

Military-civilian solidarity

Military-civilian solidarity