HomeEconomyConstruction industry8 months, nearly 60% of planned capital has not been...

After 8 months, nearly 60% of planned capital has not been disbursed yet.


After 8 months, nearly 60% of planned capital has not been disbursed yet.

Tính đến cuối tháng 8/2024, ước tính, đã có 274.501 tỷ đồng vốn đầu tư công được giải ngân, đạt 40,49% kế hoạch Prime minister Goverment giao. Như vậy, vẫn còn khoảng 50,5% vốn kế hoạch chưa được giải ngân, cần tập trung thúc đẩy.

There are still 34 ministries and 23 localities with low disbursement.

Lead data of Ministry of Finance, Ministry of Planning and Investment According to the Ministry of Information and Communications, the estimated payment of public investment capital from the beginning of the year to the end of August 8 is more than VND 2024 billion, reaching 274.501% of the plan assigned by the Prime Minister, lower than the disbursement level of 40,49% of the same period last year.

Of which, domestic capital is over VND 270.469 billion (reaching 41,11% of the plan assigned by the Prime Minister), foreign capital is over VND 4.031,4 billion (reaching 20,16% of the plan assigned by the Prime Minister). Of this, capital from the Socio-Economic Recovery and Development Program alone reached over VND 4.931 billion, reaching 79,32% of the plan assigned by the Prime Minister. The disbursed capital from national target programs is VND 13.812 billion, reaching 50,74% of the plan assigned by the Prime Minister.

Although this disbursement rate has not met expectations, it also reflects the general trend of public investment disbursement in recent years, which is often slower in the first months of the year and accelerated in the last months of the year.

However, it must be seen that the pressure to disburse public investment capital in the last months of the year is very large. Because with the disbursement rate of 8 months only reaching nearly 40,5%, there is still 50,5% of the planned capital that needs to be focused on disbursing. Even if the Government's target is to disburse 95%, this is still a rather heavy task.





Since the beginning of the year, the Government has held many conferences to remove obstacles and promote disbursement of public investment capital.

The report of the Ministry of Planning and Investment also said that in the 8 months, there were 9 ministries, central agencies and 32 localities with high disbursement rates (over 45% of the plan assigned by the Prime Minister). However, there were still 34 ministries, central agencies and 23 localities with disbursement rates below the national average (40,49%).

According to the Ministry of Planning and Investment, the average disbursement rate of the local sector is lower than the national average, including some localities whose planned capital for 2024 is assigned to account for a large proportion of the total state budget investment plan for 2024 but have a low disbursement rate, greatly affecting the overall disbursement rate of the whole country.

Notably, Ho Chi Minh City, the country's economic locomotive, was assigned a capital plan of VND2024 billion in 79.300, but the estimated disbursement in the first 8 months of the year only reached VND13.142 billion. Thus, compared to the same period in 2023, the disbursed capital in the first 8 months of Ho Chi Minh City decreased by about VND6.600 billion.

Similar, Hai Phong The capital plan for 2024 was assigned to be 17.000 billion VND, but the estimated disbursement in the first 8 months of the year was 7.800 billion VND, a decrease of about 2.400 billion VND compared to the same period.

Binh Duong, Bac Ninh, Quang Ngai, Binh Phuoc, Quang Ninh are also localities in this area. The planned capital for 2024 is large but disbursement is lower than the same period last year.

The Ministry of Planning and Investment believes that if the above 8 localities maintain the amount of disbursed public investment capital equivalent to the amount of capital disbursed in the same period of 2023 of that locality, the total disbursed capital planned for 2024 in the first 8 months of the year will be about 15.600 billion VND higher. 

Not fully allocated, quickly transfer capital

Not only has the disbursed capital not met expectations, but by the end of August 8, there is still a significant amount of capital that has not been allocated in detail.

Specifically, by August 31, 8, ministries, central and local agencies had allocated and assigned detailed capital investment plans for 2024 of more than VND 2024 billion, reaching 651.419% of the plan assigned by the Prime Minister. That is, there are still more than VND 96,1 billion that have not been allocated in detail.

A report from the Ministry of Planning and Investment shows that, of this, more than VND9.135 billion has been proposed for reduction by ministries, branches and localities (including VND8.001 billion of domestic capital and VND1.133 billion of foreign capital).

Currently, the Ministry of Planning and Investment is reporting to transfer this capital to supplement the corresponding important national projects, key projects, expressway projects, key projects with spillover, connectivity, and regional linkages that are meaningful in promoting rapid and sustainable socio-economic development. as well as projects that have not been allocated a central budget investment plan for 2024, and need additional capital to ensure project implementation progress...

In addition, the Ministry of Planning and Investment has also submitted to the Government permission for ministries, branches and localities to continue allocating the 2024 capital plan for new tasks and projects decided by the Prime Minister to adjust the medium-term public investment plan for the period 2021 - 2025.

Along with urging detailed allocation and capital transfer, the Ministry of Planning and Investment also recommended that the Government direct ministries, branches and localities to speed up the disbursement of public investment capital.

Accordingly, many solutions have been proposed, such as considering launching a 120-day and night movement to strengthen and accelerate the disbursement of public investment capital in 2024, striving to complete the disbursement target of over 95% of the plan assigned by the Prime Minister.

In addition, ministries, branches and localities with disbursement levels below the national average should focus on directing, urging and promoting disbursement of public investment capital.

At the same time, speed up the progress of site clearance, review the progress of disbursement according to the assigned capital plan, proactively handle issues within the authority; coordinate with specialized agencies to review and resolve difficulties and problems.

“It is necessary to improve the quality of project investment preparation, closely follow the processing process of specialized agencies to promptly explain and complete documents according to regulations, overcome the situation of “capital waiting for projects”, and prepare the best conditions to implement the 2025 public investment plan immediately after being assigned the capital plan by competent authorities”, emphasized the Ministry of Planning and Investment.





Sources: https://baodautu.vn/8-thang-van-con-gan-60-von-ke-hoach-van-chua-duoc-giai-ngan-d224320.html

Same topic

Capital transfer if disbursement of road maintenance capital is slow

Emphasizing that the disbursement progress of maintenance capital has only reached 59%, in...

Quang Nam transfers 222 billion VND from slow disbursement projects to projects with good disbursement progress

Focus on removing difficulties for businesses. In the fourth quarter, the province will focus on strictly and effectively implementing key tasks and solutions on investment capital disbursement according to the direction of the Prime Minister. Continue to focus on removing difficulties and obstacles for businesses and people...

Ho Chi Minh City divides 5 project groups to spend 63.000 billion VND of public investment capital in 4 months.

Ho Chi Minh City divides into 5 project groups to spend 63.000 billion VND of public investment capital in 4 months. From now until the end of January 1, Ho Chi Minh City must disburse 2025 billion VND of public investment capital. Secretary of the City Party Committee Nguyen Van Nen also requested that this be considered a top priority in the remaining months of 63.000. At the 2024rd Conference...

Quang Nam determined to transfer capital for slow-progressing projects

The disbursement rate of public investment capital in 2024 only reached 39%. The Chairman of the People's Committee of Quang Nam province requested to resolutely transfer capital to slow-progressing projects and promptly replace weak officials, causing difficulties in capital disbursement progress. The Office of the People's Committee of Quang Nam province issued the conclusion of Mr. Le Van Dung, Chairman...

The Secretary of Ho Chi Minh City will be like ChatGPT, receiving information at any time, even at midnight.

This afternoon, the Ho Chi Minh City People's Committee held a regular meeting to review the socio-economic situation in the first 9 months of the year. Speaking at the opening of the meeting, Chairman of the Ho Chi Minh City People's Committee Phan Van Mai said that in general, the city still maintains its growth rate but has not made any breakthroughs. In particular, public investment disbursement is still very low, reaching only 20% of the annual plan so far (according to the General Statistics Office, as of...

Highlights

New Posts

Same author

Dry cough can warn of cancer

After a month of dry cough with increasing severity, the male patient went to the doctor and was found to have large cell neuroendocrine carcinoma combined with squamous cell carcinoma. According to the patient, for the past month, male patient CTH (76 years old, Bac Ninh) had symptoms of dry cough, the condition lasted for...

National Highway 51 through Dong Nai, Ba Ria

Vietnam Road Administration proposes emergency repairs to National Highway 51 The total cost required to carry out emergency repairs to key locations on the Km1+800 – Km43+190 section of National Highway 51 to ensure traffic safety is 51,6 billion VND. National Highway 51 through Bien Hoa City has been severely damaged for a long time and has not been...

Long An strives to ensure social housing needs

Solving social housing, especially housing for workers, is identified by Long An province as one of the key tasks in socio-economic development. High demand for housing According to the Long An Economic Zone Management Board, the province currently has 36 industrial parks (IPs) established with a total area of...

Establish a new business for only 0 VND

With the support packages for public digital signatures, electronic invoices, seals... being implemented, business households in Thua Thien Hue province will have the opportunity to not incur costs when establishing new businesses in 2024. Thua Thien Hue Department of Planning and Investment said that FPT IS Company Limited is currently...

Foreign capital is returning to Vietnamese stocks.

In the stock market, recent positive net buying sessions in large stocks show signs that Vietnamese stocks are attracting foreign capital flows back. Large stocks attract foreign investors Except for net buying of more than a thousand billion VND in the first month of the year, since February 2, foreign investors have always maintained...

Much read

Dong Thap approves planning tasks for Song Hau 2 Industrial Park and Cao Lanh III Industrial Park

Dong Thap approves the planning task of Song Hau 2 Industrial Park and Cao Lanh III Industrial Park. The People's Council of Dong Thap province, term X, 2021 - 2026, has just issued a Resolution on approving the task of making a general planning for the construction of Song Hau 2 Industrial Park and a Resolution on approving the task of making a subdivision planning for the construction of Cao Lanh III Industrial Park. ...

Ministry of Transport requests Binh Phuoc and Dak Nong to review the apparatus and personnel managing the Gia Nghia Expressway Project.

Reviewing the management apparatus of Gia Nghia - Chon Thanh expressway with a capital of 25.500 billion VND. The investment project to build the North - South expressway in the West, Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) section, must speed up the implementation progress so that it can be basically completed in 2026 and put into operation in 2027. Coordinate...

Join Huyen Phi in spreading love with Free Health Checkup Day

In late September and early October, Huyen Phi Cosmetics Company Limited organized a free general health check-up program for parents of senior distributors in the three regions of the North, Central and South on September 9, 10, 20 and October 26, 09 respectively.

Industrial enterprises need more "support" to accelerate in the last 3 months of the year

Escaping the "rough waves" of industrial enterprises, they returned to the "runway" of growth. Industrial enterprises strive to restore production after the storm. Pressure still weighs on manufacturing enterprises. According to S&P Global, the Purchasing Managers' Index (PMI) of the Vietnamese manufacturing industry has decreased from 52,4 to 47,3 points...

Vinhomes Golden Avenue – destination for multi-generational families

A pleasant place to live for multi-generational familiesIn modern society, the multi-generational family model helps preserve unique traditional cultural features, when the next generations are passed on experiences from the previous generation. Children will be carefully raised in the company of relatives. The elderly are cared for and accompanied to reduce loneliness and...

Same category

German "giant" in polyurethane (PU) manufacturing industry sets up first factory in Vietnam

With strong growth prospects and increasing market demand in Southeast Asia for products made from polyurethane (PU), pre-polymer and polyester resins, Pearl Group has chosen Vietnam as the production hub for all its business activities in Southeast Asia. This morning (October 10), the group established its first factory in...

National Highway 51 through Dong Nai, Ba Ria

Vietnam Road Administration proposes emergency repairs to National Highway 51 The total cost required to carry out emergency repairs to key locations on the Km1+800 – Km43+190 section of National Highway 51 to ensure traffic safety is 51,6 billion VND. National Highway 51 through Bien Hoa City has been severely damaged for a long time and has not been...

Industrial enterprises need more "support" to accelerate in the last 3 months of the year

Escaping the "rough waves" of industrial enterprises, they returned to the "runway" of growth. Industrial enterprises strive to restore production after the storm. Pressure still weighs on manufacturing enterprises. According to S&P Global, the Purchasing Managers' Index (PMI) of the Vietnamese manufacturing industry has decreased from 52,4 to 47,3 points...

Belgian Ambassador co-chairs press conference of Belgian Cultural and Gastronomy Festival 2024 in Hai Phong

Following the success of previous years, the Belgian Culture and Gastronomy Festival 2024 (B. Fest 2024) will return for the 4th time at the Vietnam-Czech Republic Friendship Cultural Palace, 53 Lach Tray, Hai Phong from October 25 - 27.

How are foreign investment projects profitable and losing?

In 2023, 64 projects were profitable, with a total after-tax profit of 690,4 million USD, an increase of 120,85 million USD, equivalent to 21,22% compared to 2022. In 2023, 87 projects generated revenue - Illustration photo by Duy Linh. Of the 87 revenue-generating projects, 64 were profitable, 23 were...

New Posts

New expectations for the real estate market

Speaking at the opening ceremony of the workshop, Prof. Dr. Pham Hong Chuong - President of the National Economics University said that in the period of 2022 - 2023, the Vietnamese real estate market will face many difficulties and challenges, including causes related to legal problems. However, from 2024, the market...

Prime Minister speaks at ASEAN-Japan Summit, ASEAN + 3 and ASEAN

* At the 27th ASEAN-Japan Summit, leaders of the countries highly appreciated the success of the Summit to celebrate the 50th anniversary of the establishment of ASEAN-Japan relations in Tokyo in December 12, and welcomed the positive developments in the relationship in recent times....

VinaPhone customers in many localities will experience 5G for free

Previously, in March 3, Vietnam Posts and Telecommunications Group (VNPT) successfully won the auction for the C2024 frequency block (2MHz - 3700MHz) for 3800G. Winning the auction for the C5 frequency block is very important, allowing VNPT to have many options for network equipment, deployment costs...

Mr. Pham Ngoc Duong holds the position of Director of the Department of Home Affairs of Hai Phong city.

On the afternoon of October 10, the Standing Committee of Hai Phong City Party Committee convened a conference to announce the decision on the...

New Posts

Dry cough can warn of cancer