Dam Ha District has identified public investment as one of the key breakthroughs that needs to be focused on, in order to create momentum for economic growth and contribute to the province's 14% growth target in 2025.
Dam Ha district has forests, a sea, and a large area of agricultural and forestry land. In the context of each locality, department, and sector having to work twice or three times as hard to boost economic growth in 2025, the district is joining this vibrant "flow," accelerating the disbursement of public investment capital, creating momentum for economic growth.
Mr. Hoang Vinh Khuyen, Chairman of the District People's Committee, said: In 2025, the district plans to allocate over 410 billion VND in public investment capital, detailed for 31 ongoing projects and works, 11 new projects, and 7 projects in the investment preparation phase. The locality is determined to disburse 100% of the planned capital as soon as possible to boost the local economy, thereby creating momentum for economic growth in other sectors and contributing to achieving the district's economic growth target of over 18% in 2025.
The District People's Committee established a special task force to disburse public investment funds as directed by the Provincial People's Committee. Specific tasks were assigned to the team members to directly and regularly inspect, monitor, and urge the implementation of each project, resolving any difficulties or obstacles that may arise. Weekly meetings were held to review the tasks set for the week and address any problems that occurred during implementation.
Adhering closely to the district's development goals and orientations for 2025, the District Investment and Construction Project Management Board, along with the contractors, have promptly coordinated, exchanged information, mobilized technical equipment and personnel to return to the construction site, and accelerated construction.
The Binh Ho 1 flood bypass project in Quang Lam commune commenced in early November 2024 and is planned for completion in November 2025. The road is over 2km long and includes the construction of access roads and bridges. Upon completion, the project will alleviate traffic difficulties and disruptions on the route during the rainy season. The District People's Committee has directed the consortium of contractors to urgently implement construction measures to exceed the schedule and avoid being affected by the upcoming rainy season.
Mr. Luu Thai Duong, Commander of Son Ha Joint Stock Company, said: Currently, the joint venture contractor has nearly 40 engineers and technical workers, and 15 pieces of equipment and machinery deployed on the construction site along the entire route. To date, the project has achieved over 35% of its volume, including 1km of road excavation and base laying, and 0.3km of concrete road surface pouring; the bridge abutments and piers have been completed, and bridge girder casting is underway. The company is determined to complete the project by June 2025.
The Quang Lam Commune Kindergarten project involves the construction of three two-story buildings, ensuring all essential conditions are met to serve the learning and training needs of the students. With no land acquisition issues, the consortium of contractors has been able to quickly bring in machinery, equipment, and personnel to carry out construction simultaneously on all buildings. To date, the project has reached over 30% completion, with the basic completion of the retaining wall, fence, and site leveling; and the construction of two school buildings with an area of 440m² . The first floor's structural work is complete, the columns and pillars of the second floor have been poured, and the second floor roof slab is currently under construction; the office building has an area of 382 m². The first floor's structure is complete, and construction of the second floor's columns and pillars is underway. The consortium of contractors is determined to complete the entire project before the start of the 2025-2026 school year.
Thanks to solutions implemented early, in the first two months of 2025, the district's public investment disbursement rate reached 4.5%, placing it among the highest-performing localities in the province (the provincial average is 2.5%). The district is determined to achieve 100% of its public investment disbursement plan by the end of the year, creating momentum for an increase in the value of agricultural, forestry, and fisheries production by over 14.5%; the value of industrial, handicraft, and construction production by over 23.5%; and revenue from trade, services, and tourism by over 16%.
Manh Truong
Source






Comment (0)