Updated date: 12/07/2023 12:53:07
This morning, July 12, the Ministry of Industry and Trade announced the inspection conclusions for a series of companies, groups and functional units under the Ministry of Industry and Trade related to the situation of power shortages and power cuts in many places in the past time. .
Electricity workers repair and maintain lines
Facing the situation of large-scale interruption of power supply, especially in the North from the end of May to the middle of June, following the direction of the Prime Minister at Official Dispatch No. 5/CD-TTg dated 6 On June 517, 6, the Minister of Industry and Trade established an extraordinary specialized inspection team on the management and administration of electricity supply of the Electricity of Vietnam (EVN) and related units (the period from June 6, 2023). January 1, 1 to June 2021, 1) at Decision No. 6/QD-BCT dated June 2023, 1377 and established a team to supervise inspection activities at Decision No. 8/QD-BCT dated June 6 2023.
Based on the inspection team's report and appraisal results, on July 10, the Minister of Industry and Trade issued Conclusion No. 7/KL-BCT on the management and administration of electricity supply of EVN and other power plants. units involved in power supply.
This morning, July 12, the Ministry of Industry and Trade held a meeting to publicize the full text of the inspection conclusion in accordance with regulations.
Recently, electricity was cut off in many localities, making people angry
The inspection conclusion pointed out the shortcomings, limitations, shortcomings and violations in the direction and administration of power supply in the 2021-2023 period of EVN and related units.
Firstly, slow investment and completion of power source and grid; slow troubleshooting of unit units of some thermal power plants, reducing power supply capacity.
Secondly, not strictly complying with Directive No. 29/CT-TTg of the Prime Minister, decisions, directives and directing documents of the Minister of Industry and Trade on electricity supply plan, fuel supply chart. raw materials for power production to be passive in the preparation of the power source, reducing the reserve for energy security.
Third, moderation and operation of the power system is unbalanced in mobilizing different types of power sources in many times.
Fourth, violations in the direction, administration, scheduling and operation of the national power system in the dry season in 2023.
Fifth, to interrupt power supply on a large scale, especially in the North from the second half of May to the middle of June; Sudden and unannounced power cuts cause public outrage, affecting people's lives, production and business activities and investment attraction environment.
From the shortcomings, limitations, shortcomings and violations mentioned above, the Ministry of Industry and Trade has proposed the Committee for the Management of State Capital at Enterprises (according to the decentralization of state management) based on the conclusion of inspection and direction. , organize the review, clarify responsibilities and handle or recommend strict handling according to the Party's regulations and the State's laws for EVN's Member Council and relevant individuals.
According to the conclusion of the inspection, directing, organizing the review, clarifying responsibilities and handling or recommending strict handling according to the Party's regulations and the State's laws for the Board of General Directors. directors, advisory boards, member units and individuals and groups concerned.
Vietnam Coal - Mineral Industries Group (TKV) and Vietnam Oil and Gas Group (PVN), based on inspection conclusions, direct TKV Power Corporation and PetroVietnam Power Corporation to organize Reviewing, clarifying responsibilities and handling or recommending strict handling according to the Party's regulations and State's law for related violators and individuals.
Department of Electricity and Renewable Energy, Electricity Regulatory Authority, Department of Safety Techniques and Industrial Environment, Department of Petroleum and Coal (Ministry of Industry and Trade) based on inspection conclusions, organize a serious review, draw profound experience in performing inspection and supervision functions in the assigned field, and handle the responsibility for the wrongdoing collectives and individuals (if any).
The Ministry of Industry and Trade requires EVN, PVN, TKV and relevant units to seriously implement measures in the management and administration of power supply mentioned in the inspection conclusion, and proactively overcome shortcomings and limitations. timely, not to power shortage, save electricity in the near future.
According to VAN PHUC (SGGP)