Million dollar robot to construct Nhon metro tunnel

Báo Đại Đoàn KếtBáo Đại Đoàn Kết28/08/2024


How many meters has the million-dollar robot dug to construct the Nhon - Ga metro tunnel?

Video of the "Lightning Speed" robot TBM 1 digging the Nhon - Hanoi Railway Station tunnel. Source: Hanoi Urban Railway Management Board.
tbm-le-khanh1.jpg
According to the Hanoi Urban Railway Management Board (MRB), each tunnel digging TBM robot costs from 10-15 million USD on the world market.
dsc08951.jpg
According to the Hanoi Urban Railway Project Management Board, as of August 28, the tunnel boring robot TBM 1 of the Nhon - Hanoi Railway Station metro project has dug about 125m. Each day, it maintains a stable 10-12m/day and night. The tunnel boring machine goes from station S9 (Kim Ma) straight towards underground station S10 (Cat Linh). The machine is guaranteed to go in the right direction based on the total station system placed along the route, combined with sensors on the drill bit.
dsc09041.jpg
Currently, there are 150 engineers and workers at the construction site from Vietnam, Italy, India, Ecuador, Colombia and China.
dsc08885.jpg
At the drill head, the waste soil from the excavation is transported out via a conveyor belt.
dsc09073.jpg
The containers of waste soil are then lifted by crane to the surface and dumped into a holding tank located next to the underground station.
dsc09063.jpg
In the opposite direction, the crane lowered the concrete slabs of the tunnel lining into the underground station.
dsc08922.jpg
The tunnel panels are then brought back inside, via rails.
dsc09020.jpg
Every 1.5m of excavation, the drill stopped to install the tunnel lining.
Six concrete lining panels will be fitted together to form a circle.
Six concrete lining panels will be fitted together to form a circle.
dsc08871.jpg
Engineer Vu Trung Hieu - supervisor of the Nhon - Hanoi Railway Station tunnel excavation shared: "The tunnel drilling process has not encountered orphaned rock geology, but encountering hard clay while drilling also takes a lot of time. Because during the drilling process, we often have to stop for cleaning."
The geology at this level is mainly clay. The excavator has to continuously spray water to soften the soil so it can be moved out.
The geology is mainly clay. Excavators have to constantly spray water to soften the soil so it can be moved out.
After TBM 1 dug 240m, the second TBM named
After TBM 1 has dug 240m, TBM 2, named "Bold", will start operating. Both machines will operate in parallel and take about 16 months to complete the entire 4km tunnel from station S9 (Kim Ma) to station S12 (Hanoi Railway Station).
Robot đào hầm chuẩn bị khởi động thi công dự án Nhổn - ga Hà Nội


Source: https://daidoanket.vn/robot-trieu-do-thi-cong-ham-metro-nhon-ga-ha-noi-da-dao-duoc-bao-nhieu-met-10288935.html

Comment (0)

No data
No data

Same tag

Same category

Village in Da Nang in top 50 most beautiful villages in the world 2025
Lantern craft village is flooded with orders during the Mid-Autumn Festival, making as soon as orders are placed.
Precariously swinging on the cliff, clinging to the rocks to scrape seaweed jam at Gia Lai beach
48 hours of cloud hunting, rice field watching, chicken eating in Y Ty

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product