Million-dollar robots are being used in the construction of the Nhổn metro tunnel.

Báo Đại Đoàn KếtBáo Đại Đoàn Kết28/08/2024


How many meters has the million-dollar robot excavated for the Nhon - Hanoi metro tunnel construction?

Video of the "Superfast" TBM 1 robot digging the Nhon - Hanoi Station tunnel. Source: Hanoi Urban Railway Management Board.
tbm-le-khanh1.jpg
According to the Hanoi Urban Railway Management Board (MRB), each tunnel boring machine (TBM) costs between 10 and 15 million USD on the world market.
dsc08951.jpg
According to information from the Hanoi Urban Railway Project Management Board as of August 28th, the TBM 1 tunnel boring machine of the Nhon - Hanoi Station metro project has excavated approximately 125 meters. It maintains a stable progress of 10-12 meters per day and night. The tunnel boring machine is moving from station S9 (Kim Ma) straight towards the underground station S10 (Cat Linh). The machine's accurate direction is ensured by a total station system placed along the route, combined with sensors at the drill bit.
dsc09041.jpg
Currently, there are 150 engineers and workers on the construction site from Vietnam, Italy, India, Ecuador, Colombia, and China.
dsc08885.jpg
At the drill tip, excavated soil is transported out via a conveyor belt.
dsc09073.jpg
Then, the containers of excavated soil are lifted to the surface by a crane and dumped into a holding tank located next to the subway station.
dsc09063.jpg
Conversely, cranes lower concrete tunnel lining panels down to the underground station.
dsc08922.jpg
These tunnel lining panels are then lowered inside, via rails.
dsc09020.jpg
Every 1.5 meters of excavation, the drill would pause to install the tunnel lining.
Six concrete slabs for the tunnel lining will be fitted together to form a circle.
Six concrete slabs for the tunnel lining will be fitted together to form a circle.
dsc08871.jpg
Engineer Vu Trung Hieu, who supervised the excavation of the Nhon - Hanoi Station tunnel, shared: "The tunnel drilling process hasn't encountered any isolated rock formations yet, but we've encountered hard clay soil, which has taken a lot of time. Because during the drilling process, we often have to stop to clean up."
The soil at this level is primarily clay. Excavators must constantly spray water to soften the soil so it can be transported out.
The soil is predominantly clay. Excavators must constantly spray water to soften the soil so it can be moved out.
After TBM 1 had drilled 240m, the second TBM, named...
After TBM 1 has excavated 240m, TBM 2, named "Bold," will begin operation. Both machines will operate in parallel and it will take approximately 16 months to complete the entire 4km tunnel from station S9 (Kim Ma) to station S12 (Hanoi Station).
Robot đào hầm chuẩn bị khởi động thi công dự án Nhổn - ga Hà Nội


Source: https://daidoanket.vn/robot-trieu-do-thi-cong-ham-metro-nhon-ga-ha-noi-da-dao-duoc-bao-nhieu-met-10288935.html

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Twin spheres in the early morning sun

Twin spheres in the early morning sun

The one who brings green to life

The one who brings green to life

Ho Chi Minh Cultural Festival

Ho Chi Minh Cultural Festival