Vietnam.vn - Nền tảng quảng bá Việt Nam

Construction of Nguyen Trai Bridge has reached 36% of the planned schedule.

To date, the construction volume for the two packages of the Nguyen Trai Bridge project (Hai Phong) has reached 1,362.3 billion VND, equivalent to 36% of the plan.

Báo Hải PhòngBáo Hải Phòng23/11/2025

nguyen-trai-1-(1).jpg
The construction package for the bridge, access roads, and interchange has reached 67% of the contract value.

As of November 20th, the construction volume for the two packages of the Nguyen Trai bridge project reached 1,362.3 billion VND, equivalent to 36% of the plan.

Specifically, the contract for the construction of the approach bridge, access roads, and interchange is valued at VND 1,435 billion. The construction unit is simultaneously deploying 14 pile foundation and bridge pier construction teams on both banks of the Thuy Nguyen and Ngo Quyen districts. To date, 308 out of 340 pile foundations have been completed; 21 out of 29 branch bridge abutments and piers have been completed, along with 20 out of 20 approach bridge abutments and piers, and 21 out of 26 retaining wall sections have been completed. The embankment for the approach road has been constructed, with a total value of VND 949 billion, equivalent to 67% of the plan. This is a contract where city leaders requested a reduction in construction time of 11 months compared to the original contract.

nguyen-trai-2-(1).jpg
Construction progress on the main cable-stayed bridge package is being accelerated by the contractor in order to strive for the project to be put into operation on National Day, September 2nd, 2027.
You may also like
Why is the Ho Chi Minh Highway project through Tuyen Quang and Thai Nguyen provinces behind schedule?
Why is the Ho Chi Minh Highway project through Tuyen Quang and Thai Nguyen provinces behind schedule?The Ho Chi Minh Highway construction project, specifically the Cho Chu-Trung Son Junction section, is behind schedule and cannot be completed as planned, so the Ministry of Construction has postponed the completion deadline.
Bidding is open for the construction of the Ring Road 3 through Dong Anh, worth over 1.655 billion VND.
Bidding is open for the construction of the Ring Road 3 through Dong Anh, worth over 1.655 billion VND.According to information from the National Bidding Network, the Project Management Board for Investment and Infrastructure in Phuc Thinh Commune (Hanoi City) is issuing tender documents for Package No. 24 of the Investment and Construction Project of Ring Road 3 section through Dong Anh District, with a value of over 1,655.8 billion VND.
Accelerate the progress of key projects and ensure 100% disbursement of public investment capital.
Accelerate the progress of key projects and ensure 100% disbursement of public investment capital.After inspecting several public investment projects in the province, the Chairman of the Provincial People's Committee, Nguyen Hoai Anh, directly instructed the removal of difficulties and obstacles related to land clearance and material sources, and requested the units to accelerate construction progress and ensure the disbursement plan for 2026 is met.

With the main cable-stayed bridge construction contract valued at VND 2.367 billion, the contractor has completed 84 out of 88 bored piles, 2 piers (T10 and T13), and the foundation of tower pier T11. Currently, the contractor is deploying two teams to construct bored piles for tower pier T12 and the main body of tower pier T11. The completed volume of the contract has reached VND 413.3 billion, equivalent to 18% of the plan.

By the end of November 20th, contractors had disbursed over 98% of the allocated capital for 2025.

According to the design, the Nguyen Trai Bridge spanning the Cam River is a permanent structure with a length of 1,476.4 m. The main bridge section, 550.6 m long, is a cable-stayed bridge, with the main span having one plane of cables and the side spans having two planes of cables. The tower height is 111 m. The length of the approach bridge on the Thuy Nguyen district side is 459 m, and the length of the approach bridge on the Ngo Quyen district side is 466.8 m.

The main bridge is 26.5 m wide, and the approach bridge is 23.5 m wide, comprising 4 lanes for motorized vehicles and 2 lanes for mixed traffic. The design speed for the main bridge is 80 km/h; the design load is HL93; the navigable clearance is BxH=165x25 m.

The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.
The Ministry of Foreign Affairs received a copy of the Letter of Credence for the U.S. Ambassador to Vietnam.On the afternoon of July 2nd, at the Ministry of Foreign Affairs headquarters, Mr. Le Cong Dung, Director of the State Protocol and Foreign Interpretation Department, received a copy of the Letter of Credence from Ms. Jennifer Wicks, Ambassador of the United States of America to Vietnam.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.From June 28-30, the Vietnamese Ambassador to the United States, Nguyen Quoc Dung, paid a visit and worked in Minnesota.
Vietnam encourages US businesses to expand investment in high technology.
Vietnam encourages US businesses to expand investment in high technology.On the morning of June 26th, at the Government Headquarters, Deputy Prime Minister Ho Quoc Dung received Mr. Jeff Place, Supply Chain Director of Coherent Group (USA). During the meeting, the Deputy Prime Minister affirmed that Vietnam encourages US businesses to expand investment, especially in high-tech, innovation, and semiconductor industries.
PHAM CUONG

Source: https://baohaiphong.vn/thi-cong-cau-nguyen-trai-dat-36-ke-hoach-527513.html

Trending by Category

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
SPRING FESTIVAL

SPRING FESTIVAL

Overcoming difficulties, finding complete joy.

Overcoming difficulties, finding complete joy.

The beauty of making a living on the lagoons of the ancient capital of Hue.

The beauty of making a living on the lagoons of the ancient capital of Hue.