From November 1st, Ca Mau Airport will be closed for upgrades.

On August 5th, the Chairman of the People's Committee of Ca Mau province directed specialized units and localities in the area to proactively coordinate with the Vietnam Airports Corporation (ACV) on the plan to commence the expansion and upgrading of Ca Mau Airport.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng05/08/2025

Ca Mau Airport
Ca Mau Airport

According to ACV, the commencement of Package 12, which includes the construction and supply and installation of equipment for runways, taxiways, aircraft parking areas, and auxiliary facilities (part of the Ca Mau Airport Expansion and Upgrade Project), is scheduled for August 19th. The construction period is 14 months.

During the construction period, Ca Mau Airport will be closed for 12 months, from November 1, 2025 to October 31, 2026 .

You may also like
Announcing the decision and plan for regular monitoring of the resolution of difficulties and obstacles for stalled and long-standing projects in Nghe An.
Announcing the decision and plan for regular monitoring of the resolution of difficulties and obstacles for stalled and long-standing projects in Nghe An.On the afternoon of June 4th, the Central Inspection Committee held a conference to announce the decision and plan for regular monitoring of the resolution of difficulties and obstacles for stalled and long-standing projects in Nghe An province.

ACV stated that it will direct the construction contractor to accelerate progress and shorten the construction time as much as possible to bring Ca Mau Airport back into operation soon, minimizing the impact on the local economy and society.

b1dc42ba4c25c57b9c34.jpg
The runway at Ca Mau Airport will be upgraded and expanded.

The project to expand and upgrade Ca Mau Airport was approved by the Prime Minister in Decision No. 1188/QD-TTg dated October 15, 2024, with the goal of investing in the expansion and upgrading of Ca Mau Airport to ensure the operation of A320, A321 and equivalent aircraft; creating momentum for economic, cultural and social development, while ensuring national security and defense of Ca Mau province and the region.

ACV is the investor. The project has a total investment of approximately 2,400 billion VND.

You may also like
The Provincial Party Committee's Task Force No. 2 is implementing the task of reviewing and resolving obstacles in projects that are behind schedule.
The Provincial Party Committee's Task Force No. 2 is implementing the task of reviewing and resolving obstacles in projects that are behind schedule.On the afternoon of June 4th, the Provincial Party Committee's Task Force No. 2, tasked with reviewing, urging, and directing the resolution of difficulties and obstacles related to slow-progressing, delayed, and stalled projects in the province, held a meeting to discuss several key issues for the coming period. Comrade Vu Quyet Tien, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial Fatherland Front Committee, and Head of Task Force No. 2, chaired the meeting.

Source: https://www.sggp.org.vn/tu-ngay-1-11-san-bay-ca-mau-dong-cua-de-nang-cap-post806957.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Eyes

Eyes

Human kindness on the highway

Human kindness on the highway

COMPUTER SCIENCE

COMPUTER SCIENCE