TPO - The Nhổn depot station (Tây Tựu ward, Bắc Từ Liêm district, Hanoi ) of the Nhổn - Hanoi Station inner-city railway project is basically complete. After more than 10 years of construction and more than 4 years of assembling train carriages, nearly a dozen trains are now waiting in the depot.
Covering an area of 15 hectares, the Nhon - Hanoi Station depot complex includes facilities such as an operations control center (OCC), train hangars, maintenance facilities, electrical engineering buildings, and other supporting structures. |
The project commenced on January 12, 2013. According to the initial plan, the constructions here were scheduled to be completed by the end of 2018. |
Ten trains for the Nhon - Hanoi Station urban railway project have been sitting idle in the depot for about four years now. |
The area where the trains are assembled has been energized and is heavily guarded. |
At the end of 2021, 10 trains for the Nhon - Hanoi Station metro project arrived at the depot. The trains were manufactured according to European standards by Alstom (France). |
Recently, trains have been regularly tested and loaded along the elevated section of the line from Nhổn to Cầu Giấy station (in front of the University of Transport and Communications). |
The Nhon - Hanoi Station urban railway line is 12.5 km long, passing through 8 elevated stations and 4 underground stations, of which the elevated section (Nhon - Cau Giay) is 8.5 km long and the underground section (Cau Giay - Hanoi Station) is 4 km long. |
In addition to the engineering structures, the depot grounds also feature a circular regulating lake in the center of the project, 3 meters deep, to regulate rainwater and enhance the landscape. |
The Nhon - Hanoi Station railway project was started in 2009 and was planned for completion in 2015. |
After numerous delays, the project is now projected to be completed in 2029, exactly 20 years after construction began. |
The prolonged project duration has increased costs, with the total proposed investment reaching VND 34,530 billion, an increase of approximately VND 4,905 billion compared to the initial estimate. |
Source: https://tienphong.vn/10-doan-tau-tuyen-nhon-ga-ha-noi-san-ready-to-run-after-many-years-of-waiting-post1640752.tpo