Vietnam.vn - Nền tảng quảng bá Việt Nam

What does the project investor say?

VTC NewsVTC News28/10/2023


After VTCNews reported that 4 households in residential group No. 2, Xuan Phuong ward (Nam Tu Liem district, Hanoi ) had to be urgently evacuated when their houses cracked and tilted due to the impact of digging the basement foundation for the project of the Radioactive and Rare Earth Geological Federation, the leader of this unit admitted part of the responsibility.

Responding to VTC News, Mr. Nguyen Dac Son, Deputy Head of the Radioactive and Rare Earths Geological Federation, said that the project to build technical facilities for the Radioactive and Rare Earths Geological Federation was directly assigned by the Ministry of Natural Resources and Environment and the General Department of Geology and Minerals of Vietnam to the Federation as the investor with a public investment capital of 99 billion VND.

4 houses in residential group 2, Xuan Phuong ward were heavily affected.

4 houses in residential group 2, Xuan Phuong ward were heavily affected.

Mr. Son said that on March 23, the contractor started mass pile driving. Three days later, on March 26, the project affected some nearby houses. Some houses had cracks, so the construction had to be temporarily stopped.

At this time, the construction unit is considering the option of driving sheet piles around the project to minimize the impact on neighboring households.

Solid house suddenly cracks and ready to collapse in Hanoi: What does the project investor say? - 2
Solid house suddenly cracks open and about to collapse in Hanoi: What does the project investor say? - 3

Long cracks run along the interior walls of the houses of four households that were severely affected by the construction unit carrying out the basement excavation project for the construction of technical facilities of the Radioactive and Rare Earth Geological Federation.

Mr. Nguyen Dac Son assessed that pile driving has many impacts on surrounding houses. In addition to the cause of deep pile driving, he said that people digging house foundations, farming and building "protruding" also affects the construction.

“Up to now, the Federation has held 7 meetings to work with the people, including the ward People's Committee and residential groups, not that it did not work. By the end of August, after many meetings to resolve and resolve the issue, the people agreed to continue construction.

The investor committed that after stabilizing the basement, they would invite insurance and appraisal units to conduct detailed appraisals of each household, from there assess the current state of impact on each house and then propose solutions to each household. All meeting commitment minutes are clear, we are very receptive", Mr. Son said.

Mr. Nguyen Dac Son, Deputy Head of the Federation of Radioactive and Rare Geology.

Mr. Nguyen Dac Son, Deputy Head of the Federation of Radioactive and Rare Geology.

The Deputy Head of the Rare Earth Geology Federation said that after a 5-month suspension, on August 30, the project began digging the basement, but the rain affected some households.

The excavation of the basement foundation caused landslides, creating a geological slide frame, causing houses adjacent to the construction area to crack, tilt, sink, and move horizontally towards the construction site. Therefore, on August 25, the construction was suspended.

Immediately afterwards, the Urban Construction Order Team of Nam Tu Liem District and representatives of the People's Committee of Xuan Phuong Ward inspected, made a record of the scene, and agreed to request the Federation to stop construction until now.

“We are representatives of the investor, project management board, contractor, and supervisory unit who have worked with local authorities and affected people to agree on the next plan and measures.

In the immediate future, after 4 households with unsafe houses at high risk of collapse had to relocate, we agreed on a plan to support them with 3 months of rent and 1 month of deposit. Specifically, large families will receive 17 million VND per month in support. A family with 2 spouses will receive 7 million VND per month in rent support,” said Mr. Son.

The investor representative said that in both incidents, the unit reported to the Ministry of Natural Resources and Environment and the General Department of Geology and Minerals of Vietnam about the current status and progress of the settlement. Worried about the risk of houses collapsing, the investor asked the contractor to urgently implement an anti-tilt plan.

“Last weekend, we collected data and invited the appraisal unit to evaluate the method to see if it was safe. Since September 1, the contractor has hired an independent unit to monitor the impact on the houses, according to the regulation, measuring by machine every 3 days. We set up a team to go to the households every day to check the current status of the cracks to see if there is any impact,” said Mr. Son.

In response to the people's request to invite an independent appraisal unit to assess the level of damage to the households adjacent to the project, agree on a repair and restoration plan to restore the original state before continuing construction..., Mr. Son said that the investor will invite an appraisal unit to each house to agree with the households on a repair plan.

Another representative of the investor said: “We know that many people’s lives have been disrupted and affected. We must be responsible for the projects of the households, and will find the best solutions with enough scientific basis to ensure the projects are safe for everyone to live in. At this time, we are no longer thinking about profits or progress, but only thinking about how to ensure safety.”

Regarding the solution in the coming time, Mr. Nguyen Dac Son added that the unit will organize a workshop with the participation of experts to respond to the contractor, thereby providing a plan to ensure a scientific basis.

Mr. Son emphasized: "Anyone who does construction wants to do it smoothly, however the responsibility belongs to all related units such as: Investor, project management board, supervisor, contractor. If anything happens, we ask the four units to sit with us, even the participating insurance companies are responsible."

Ngo Nhung



Source

Comment (0)

No data
No data

Same tag

Same category

Keeping the spirit of Mid-Autumn Festival through the colors of the figurines
Discover the only village in Vietnam in the top 50 most beautiful villages in the world
Why are red flag lanterns with yellow stars popular this year?
Vietnam wins Intervision 2025 music competition

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product