Accelerate the completion of coastal road 129.

DNO - On the key construction site of Component Project 1, completing the 129 coastal road (Vo Chi Cong road), the contractor is accelerating construction in areas where land is already available. The appearance of the wide and spacious coastal road, connecting seamlessly from the inner city to the south of Da Nang, is gradually becoming clear, opening up new development opportunities.

Báo Đà NẵngBáo Đà Nẵng06/08/2025

anh-3-1-.jpg
A section of the road through Tam Xuan commune has been paved with asphalt. Photo: CONG TU

The project to complete coastal road 129 (Vo Chi Cong road) consists of two component projects, including: Component Project 1: Completion of coastal road 129 (Vo Chi Cong road); Component Project 2: Road connecting from Vo Chi Cong road to Dong Que Son Industrial Park, linking to National Highway 14H and National Highway 1.

The total investment for the project is over 2,056 billion VND (1,558 billion VND from the central budget; over 498.7 billion VND from the local budget). Of this, Component Project 1 accounts for 1,100 billion VND; Component Project 2 accounts for over 956.7 billion VND.

PHOTO 2
Asphalt concrete pavement section passing through Tam Anh commune. Photo: CONG TU

Component Project 1, part of the DT619 route (Vo Chi Cong road), starts from the intersection with National Highway 40B (in the former Tam Ky city area) to the intersection with the DT620 route (in the former Nui Thanh district area), connecting to the road leading to Chu Lai Airport. The total length of the route is approximately 26.5km.

anh-1-1-.jpg
The asphalt concrete road section passing through Tam Anh commune, viewed from above. Photo: HO QUAN

The investment scale for Component Project 1 includes a secondary urban main street according to TCXDVN 104-2007, with a design speed of 70 km/h. Construction of the roadbed and surface on the remaining right side of the existing route will achieve a cross-section of 25m (with a central median, and a road surface width of 10.25m on each side) for the section from km0+000 to km9+000; and a cross-section width of 38m (central median, road surface width of 10.25m on each side, and sidewalks or shoulders of 7.5m on each side) for the remaining section.

Invest in constructing an additional unit to the right of the existing unit of the 6 bridges on the route, with a scale similar to the existing unit.

After joining the two sections, the bridge's cross-section is 25m wide; of which the carriageway on each side is 9m wide, the central median and safety strip are 2.5m wide, and the pedestrian walkways and railings on each side are 2.25m wide.

You may also like
Special news in the Hanoi Moi newspaper, October 27, 2025.
Special news in the Hanoi Moi newspaper, October 27, 2025.Hanoi pilots a model for providing school lunch services: Ensuring safety, quality, and professionalism; State-owned enterprises - pillars of an independent and self-reliant economy in the new development era; The dangers of weight-loss products containing banned substances; Alley 85, Vo Chi Cong Street (Nghia Do Ward) frequently floods: A renovation plan is needed soon; Operating a two-tiered local government: Innovating the governance model, building a public service apparatus for the people - Part 4: Administrative procedures reaching villages and residential areas… These are some of the noteworthy news items in the printed edition of Hanoi Moi newspaper on October 27, 2025.
Spain vs Austria: La Roja's resilience against Ralf Rangnick's whirlwind of pressing.
Spain vs Austria: La Roja's resilience against Ralf Rangnick's whirlwind of pressing.Spain enters the Round of 16 of the 2026 World Cup with an unbeaten defense, but Austria's energetic pressing style will be the ultimate test of their championship ambitions.
Lenovo ThinkPad P14s Gen 7: A powerful 1.29 kg mobile workstation with AMD Ryzen AI PRO chip.
Lenovo ThinkPad P14s Gen 7: A powerful 1.29 kg mobile workstation with AMD Ryzen AI PRO chip.Lenovo has officially released the ThinkPad P14s Gen 7 globally, combining superior portability with powerful performance from the AMD Gorgon Point chip series. A highlight of the device is its weight of only 1.29 kg, yet it supports RAM upgrades up to 96 GB.
anh-5(1).jpg
Preparations underway for cantilever casting on pier T8 of Tam Tien Bridge. Photo: CONG TU

The project along the route includes investment in a horizontal and vertical drainage system on a scale similar to the existing section; a traffic management system; lighting; and landscaping.

To date, the Tam Tien bridge has had 40 out of 40 girders cast; 5 bridge deck spans completed; the cantilevered sections on pier T7 completed; and the cantilevered section K5 on pier T8 is currently under construction.

The Diem Tra Bridge has had its deck constructed and is currently undergoing finishing work. The Tam Hiep, An Tan 2, Tam Nghia, and Tam Quang bridges are basically complete.

PHOTO 9
Construction site of Tam Tien Bridge. Photo: Ho Quan

Regarding the route, the contractor consortiums are currently constructing the roadbed and surface for 22.4/26.5km of sections where land has been handed over. Asphalt concrete paving has been completed for 11.4/20.7km (excluding the 5.8km section through Tam Hiep Industrial Park and An Hoa Bay, which was completed in phase 1 previously). 42/68 culverts of various types have been completed; and 21,970/38,437m of median strips have been installed.

anh-6(1).jpg
One location has been filled with soil and is awaiting settlement. Photo: CONG TU

Currently, contractors are accelerating the construction of road embankment and weak soil treatment in sections where land handover is scheduled for October 2024 and February 2025 (the loading and settlement waiting period is 565 days - approximately 19 months), as well as laying crushed stone base for asphalt concrete paving.

PHOTO 7
The section of Vo Chi Cong road passing through An Hoa Bay has been completed. Photo: CONG TU.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.
Ambassador Nguyen Quoc Dung visits and works in Minnesota, USA.From June 28-30, the Vietnamese Ambassador to the United States, Nguyen Quoc Dung, paid a visit and worked in Minnesota.
Vietnam encourages US businesses to expand investment in high technology.
Vietnam encourages US businesses to expand investment in high technology.On the morning of June 26th, at the Government Headquarters, Deputy Prime Minister Ho Quoc Dung received Mr. Jeff Place, Supply Chain Director of Coherent Group (USA). During the meeting, the Deputy Prime Minister affirmed that Vietnam encourages US businesses to expand investment, especially in high-tech, innovation, and semiconductor industries.
Encourage U.S. businesses to expand investment in high-tech sectors.
Encourage U.S. businesses to expand investment in high-tech sectors.Deputy Prime Minister Ho Quoc Dung said that Vietnam welcomes US businesses to continue expanding their operations in Vietnam, especially in high-tech industries and sectors with high added value.

Component Project 1, completing coastal road 129 (Vo Chi Cong road), is a key project.

The completed project will expand the road's cross-section from 2 lanes to 6 lanes; the section passing through Tam Hiep Industrial Park to the road leading to Chu Lai Airport will have a cross-section width of up to 38m.

This section of the route will create a continuous, seamless connection from the coastal city center, across the Cua Dai bridge, all the way to the south of Da Nang city.

Source: https://baodanang.vn/tang-toc-hoan-thien-duong-ven-bien-129-3298754.html

Trending by Category

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Procession of the Goddess of Binh Duong

Procession of the Goddess of Binh Duong

Dong Nai City undergoes transformation.

Dong Nai City undergoes transformation.

Technology from the heart

Technology from the heart