According to the People's Committee of Ca Mau province, the investment project to upgrade and expand the U Minh - Khanh Hoi road (U Minh district, Ca Mau province) has a total investment of 760,2 billion VND by the Construction Project Management Board. Ca Mau province traffic program is the investor, project implementation schedule is from 2021 - 2025.
Problems with land, risk of slow progress
The total length of the route is 18,13km, affecting 1.983 households, individuals and 8 organizations. The locality has handed over the site of 10,1/18,13km to the investor for construction (reaching 55,7% of the total route length).
Currently, U Minh District People's Committee has approved compensation and support plans for 1.889/1.983 households and 5/8 organizations; The remaining 94/1.983 affected households, individuals and 3/8 organizations have had their compensation and support plans prepared and evaluated for approval.
To date, the district has paid money according to the approved plan to 1.219/1.889 households and 5/8 organizations. There are 670/1.889 households whose plans have been approved but have not agreed to receive money or hand over the premises.
The reason for the land problem is that during the implementation of the project, some households and individuals also requested and proposed compensation and support for the land area of the canal and the existing roadside. Status (each side 1,25m) U Minh - Khanh Hoi route.
In addition, some households also requested an increase in compensation land prices. Some households requested compensation and support to run out of housing, because the remaining portion could not be repaired to live in. And some households suggested re-checking the measurement, counting, and unit prices of houses and architectural works.
Completely handle people's petitions
In response to the people's petition to request compensation and support for the canal land and the existing sidewalk (1,25m on each side) of the U Minh - Khanh Hoi route, the People's Committee of Ca Mau province said that it is is public land managed by the State.
“Therefore, the lack of land compensation for this land is in accordance with the provisions of current law (due to not meeting the compensation conditions as prescribed in Clause 4, Article 82 of the 2013 Land Law).
The State continues to manage and use the remaining land within a range of about 25m (8m road and canal from 12,5 - 20m) as public works according to planning", Ca Mau Provincial People's Committee affirmed.
Also according to the People's Committee of Ca Mau province, in order for the management, use of land and issuance of land use rights certificates (LURCs) of people to ensure the provisions of the law, the Chairman of this Provincial People's Committee assigned the Department of Natural Resources and Environment The school presides and coordinates with U Minh District People's Committee and relevant agencies and units to urgently inspect and review according to regulations.
Specifically, for 114 Land Use Rights Certificates issued around 1995, the current status of the land plot remains intact, with land use term until 2021. 358 Land Use Rights Certificates have been renewed or revised for the area of canals and vehicle roads. and the land being managed and used.
From there, organize propaganda and mobilize people to renew or amend land use rights certificates or extend land use term in accordance with the provisions of law.
Regarding the recommendations of households and individuals on compensation and support for all houses, because the remaining house cannot be repaired for living and re-checking the measurement, counting, and unit prices of houses and works architectural objects, the Chairman of the People's Committee of Ca Mau province requested the Department of Construction to preside over and coordinate with relevant departments, branches, units and the People's Committee of U Minh district to urgently inspect, review and handle each case completely. specifically as soon as possible to accelerate project implementation progress.
Regarding the proposal to increase compensation and support prices, the People's Committee of Ca Mau province said that the specific land price for calculating compensation and support has been implemented by the competent authority in accordance with the order, documents and procedures according to regulations.
“Therefore, we request the People's Committee of U Minh district to preside over and coordinate with relevant agencies and units to organize propaganda and mobilize people to understand and comply with the provisions of law and hand over the premises. for the State to implement the project to ensure project progress according to regulations", the Chairman of Ca Mau Provincial People's Committee clearly directed.