TPO – Tam Trinh Street construction project was approved by the City People's Committee. Hanoi approved in 2012. The route has a length of over 3.500m with a total investment of 2.066 billion VND, expected to be completed in 2019. However, after 12 years the project has still not been completed due to related problems. to land clearance.
Recently, Hoang Mai District People's Committee held a conference to announce legal documents for site clearance for the Tam Trinh Road Construction Project.
According to Hoang Mai District People's Committee, in addition to adjusting the project name and project implementation period (2016 - 2026), the City People's Committee also adjusted the project scale.
Accordingly, the project will build a synchronous road with a length of about 3.557,7m. The entire route's cross section is 40m according to the red line approved by the City People's Committee.
In 2012, City People's Committee. Hanoi has approved the Tam Trinh Street construction project, assigning Hoang Mai District People's Committee as the investor. The route has a length of over 3.500m, with a total investment of 2.066 billion VND. The starting point connects to Minh Khai street, the ending point intersects Ring Road 3, implementation period is 3 years (2016 - 2019). |
Regarding the capital source for project implementation, there has also been an adjustment, the city budget advances and refunds revenue from land use fees in Hoang Mai district to create capital for project implementation. In addition, 1.000 billion VND from the remaining salary reform source of Hoang Mai district budget will be used.
On October 17, 10, Hoang Mai district held a groundbreaking ceremony to build and expand Tam Trinh street. However, during the implementation process, many households in the land clearance area in Yen So and Mai Dong wards did not receive compensation and refused to hand over the land areas within the recovered boundaries. |
The Government Inspectorate conducted a comprehensive inspection of the Nguyen Tam Trinh street project and adjacent projects with a 15m extension, the section passing through groups 1, 3 and 27, Yen So ward, Hoang Mai district. On December 7, 12, the Government Inspectorate issued Conclusion No. 2021/KL-TTCP on the project's land acquisition boundaries as a basis for the City as a legal basis for project implementation. |
Based on Conclusion No. 345/KL-TTCP, City People's Committee. Hanoi has issued Decision 6444/QD-UBND adjusting the Tam Trinh Road construction investment project including 5 main issues. |
Currently, Tam Trinh Street is a bottleneck, making traffic difficult, especially during rush hours. |
People want Hoang Mai district to soon implement the Tam Trinh road construction project. However, there are still some problems related to site clearance. |
Hoang Mai District People's Committee is coordinating with the People's Committees of relevant wards to strengthen propaganda and encourage people to hand over the site so that the project can be completed in 2026. |