Organize scientific construction, speed up the progress of the Northern Expressway


Many problems hinder construction progress

On March 21, continuing his business trip to the Central region, Deputy Minister of Transport Nguyen Duy Lam had a working session with contractors and project consultants of two component projects of the North - South expressway through Ha Tinh.

Organize scientific construction, speed up the progress of the North-South Expressway through Ha Tinh - Photo 1.

Deputy Minister of Transport Nguyen Duy Lam worked with construction units of two projects: Bai Vot - Ham Nghi and Ham Nghi - Vung Ang.

At the meeting, Mr. Do Thanh Chung, Deputy Director of Xuan Truong Construction Enterprise (contractor of Ham Nghi - Vung Ang Expressway) said: Currently nay some Norms and unit prices for labor and machine shifts are not close to reality. The estimated price of materials is not consistent with the local price level, causing a series of contractors to face difficulties... Although specific material mines have been granted to contractors to exploit for the project, up to now there is still no guidance. on how to calculate material prices at the mine.

In addition, the design survey work has some deviations from the field. “Initially, it was planned to use 700.000 m3 of stone from Km560 hill to make concrete stone and grade 1 crushed stone. But in reality, only about 100.000 m3 could be used, causing the unit to fall into a passive state. materials for making bridges and culverts, adjustment documents must be prepared.

Or like the location of Km535 hill, the initial design plan was to dig. But when working, we encountered many hard rocks that had to be blasted. But if you want to blast mines, it takes 3 months to complete the procedures... Worth mentioning, when the weather is good, the unit must go through the procedures. When the procedure was completed, it was raining and windy again. These issues have greatly affected the progress and output of construction," Mr. Chung gave an example. 

Organize scientific construction, speed up the progress of the North-South Expressway through Ha Tinh - Photo 2.

The construction units of the two projects expressed their opinions and problems when constructing the project at the working session.

Mr. Chung hopes that through the meeting, the Ministry of Transport will direct the Project Management Board and Consultants to join hands with the contractors to resolve remaining problems.

Also at the Ham Nghi - Vung Ang expressway project, Mr. Mai Anh Dong - General Director of Joint Stock Company 471 said that the unit is implementing it simultaneously throughout the project. Progress reached 33%. 

Similar to other contractors, the biggest difficulty with 471 is the standard unit price and material adjustment issues.

According to Mr. Dong, looking at the report, it can be seen that the disbursement rate in this project is low, while the actual construction output of the contractor is high. The reason is that the approved output and payment after adjusting the material source are still small. 

Therefore, the contractor requested the Ministry to direct the Project Management Board and consultants to quickly approve, or increase the rate of temporary approval of the work done for the contractor. For locations where technical design must be adjusted or soft soil treatment solutions must be changed, after the Board and consultants approve implementation on the construction site, they also approve and sign the payment dossier appendix to the contractors. bids or updated at fixed intervals to avoid disbursement backlogs.

Organize scientific construction, speed up the progress of the North-South Expressway through Ha Tinh - Photo 3.

The Deputy Minister requested units and contractors not to be subjective because the time to complete the project is approaching while output is still low.

Sharing the contractor's difficulties, Deputy Minister Lam said that the design survey unit needs to be more careful. During the survey process with locations using salvaged materials, the drill bit thickness must be increased to closely assess the geology. As reflected by the contractor, because the design is not close to reality, it leads to having to buy materials from commercial mines and buy commercial concrete, affecting the contractor's construction progress.

On the consulting side, engineer Nguyen Ngoc Dung - Project Manager of package 12 Ham Nghi - Vung Ang (HECO Company) said: During the survey process, due to the limited number of drill bits, it was not possible to fully evaluate the reserves. and quality of materials at the place of use. As soon as a discrepancy was discovered, the consultant worked with the Board to prepare documents and immediately approve adjustments for the contractor.

Mr. Nguyen Thanh Van - Deputy Director of the Department of Construction Investment Management (Ministry of Transport) assessed: Looking at the current progress and the remaining time, the project can completely reach the finish line in June 6. 

However, Mr. Van also expressed concern when the contractors set a schedule that was not linked to the overall construction method and the site. 

“Units need to review the overall situation, construction plans must be linked to the site. At the same time, continue to review and handle problems that arise after the route is formed, such as: Drainage system, traffic safety system, intersections... The process must be consistent in terms of documents and procedures. , control the origin and quality of materials for the project," Mr. Van said and added: As for the issue of material prices at the mine, the Construction Investment Management Department has worked with the Department of Construction Economics (Ministry of Construction). Construction) for early review and guidance on how to calculate prices.

Project quality is a decisive factor for the survival of an enterprise and the political life of project managers

Recognizing the efforts of the contractors at both North-South expressway projects through Ha Tinh, Deputy Minister Nguyen Duy Lam emphasized: The contractors participating in the project were carefully selected by the Ministry of Transport, and are capable, experienced units and especially those who have participated in previous expressway projects. Being selected is an honor but also a responsibility.

Organize scientific construction, speed up the progress of the North-South Expressway through Ha Tinh - Photo 4.

The North-South Expressway project passing through Ha Tinh still has some grid technical infrastructure problems.

This project started construction in January 1, with some packages being 2023-1 months later. But after 2 months (nearly half of the project implementation time), the contractors have only achieved about 14% of the workload (about 1% for Xuan Truong alone). 

“We are also striving to complete the project ahead of schedule, reaching the target date of June 30, 6. Thus, the project construction time is only 2025 months, with a lot of work remaining. We have overcome the most difficult things in the early stages, now we have to try harder and harder" - the Deputy Minister said and asked the contractor to re-aware of his responsibilities. 

“Contractors who are trusted and selected must fulfill their commitments to the investor and the Ministry of Transport. No matter how you do it, you still have to put quality first. It is necessary to determine that quality is a decisive factor for the survival of the enterprise and the political life of project managers. Contractors must be very careful, this is a direct contractor project, so everything must be done in a concise manner, and the documents and procedures must be in the correct order and complete," the Deputy Minister emphasized. 

Xuan Truong private enterprise constructs the Ham Nghi - Vung Ang project.

For more information, the Deputy Minister said: The Ministry of Transport is directing relevant units to remove difficulties for contractors and coordinate with the Ministry of Construction to soon issue a new set of regulations on unit price norms. 

However, the contractor himself must make efforts in advance, based on weather conditions and construction site conditions, to work overtime and develop a construction plan to suit reality. The project's time is running out, so the contractor must speed up the progress now. At the same time, prepare supplies and materials, don't let them get pushed to the last stage.

The Deputy Minister also required consulting units to highlight their roles and responsibilities to promptly support contractors in handling arising problems and approving documents. Project Management Boards continue to closely monitor localities to completely resolve site problems.

“The Minister has directed that with 12 North-South expressway component projects phase 2, when the road is put into operation, rest stops, smart traffic operation centers, and feeder roads must be completed at the same time. Therefore, from now on, the Project Management Board must develop an implementation plan," the Deputy Minister noted. 

Reporting to the Deputy Minister and the working group, Mr. Ho Ngoc Loan - Deputy Director of Thang Long Project Management Board (Project Investor - Ministry of Transport) said: At the Bai Vot - Ham Nghi project up to now, the total The output value of the two contractors VINACONEX and Corporation 319 Ministry of Defense has reached 1.317 billion/4.873 billion (27%). The Board has disbursed 100% of the planned capital allocated in 2023 and 46% (607 billion VND) of the planned capital allocated in 2024.

Ham Nghi - Vung Ang project, to date the project progress has reached 21,81% (output 1.377,04 billion/ 6.314,48 billion VND). Of which, the XL11 package, constructed by the joint venture Xuan Truong - Tu Lap - 471, reached 815/3.534 billion VND (equivalent to 23,07%). In this package, contractors Tu Lap and 471 completed the construction, meeting or exceeding the set schedule. Only Xuan Truong reached 19%.

Package XL12 of Xuan Truong - Construction 368 joint venture has completed construction reaching 562/2.780 billion VND (reaching 20,22%). Contractor 368 Construction Company reached 42,5%, Xuan Truong reached nearly 17% (slow 2,6%). The disbursement rate of the project in 2024 is 138/1.437 billion VND, reaching about 9%.

According to Mr. Loan, Ha Tinh province has done a good job in site clearance as well as providing mines to contractors for construction. The problem here is that contractors must have a reasonable and scientific way of arranging construction so as not to affect the progress.

After the Deputy Minister's inspection trip as well as today's meeting, representatives of the contractors pledged to arrange enough machinery and human resources for construction; In addition, the units will meet to agree on a methodical and scientific organization of construction on the route.



Nguon

Same topic

Proposal for appraisal of the Hoang Lien Pass road tunnel project worth VND 3.300 billion

Proposal for appraisal of the Hoang Lien Pass road tunnel project worth 3.300 billion VND. The Hoang Lien Pass road tunnel project is located on National Highway 4D connecting Lai Chau with Lao Cai, with a length of 8,8 km, including 2,63 km tunnel. Perspective of Hoang Lien road tunnel. Construction investment project management board of...

What is the scenario for the real estate market in the near future?

Apartment prices increased sharply in the first 2 months of the year According to the latest data from Batdongsan.com.vn, the average selling price of apartments in Hanoi in the first 2 months of this year increased by 17% compared to the same period in 2023. According to the latest data from Batdongsan.com.vn, the average selling price of apartments in Hanoi in the first 2 months of this year increased by 17% compared to the same period in 2023. In fact...

Awarding the Ly Tu Trong Award to 100 outstanding Youth Union officials in 2024

At the ceremony, Deputy Prime Minister Tran Hong Ha affirmed that the Ly Tu Trong Award not only honors and praises outstanding role models but also encourages and encourages millions of youth union members nationwide to practice virtue, practice talent, and take the lead, volunteer to commit, bring youth and desire to contribute, contribute...

Proposing a synchronous investment plan for Dong Dang expressway

Proposed synchronous investment plan for Dong Dang - Tra Linh expressway with 4 lanes. Expansion of Dong Dang - Tra Linh expressway to reach the planned scale of 4 lanes, roadbed width of 17m is proposed to be implemented as a project. The project is independent from the phase 1 project that is being invested. Mix...

Support to ensure construction of Package A1-1 Ben Luc - Long Thanh Expressway

Support to ensure the construction of Package A1-1 for Ben Luc - Long Thanh Expressway Construction of Package A1-1, Ben Luc - Long Thanh Expressway Project, intersection area with Ho Chi Minh City - China Expressway Luong in Long An province is being obstructed, contractors cannot access the construction site. Construction of line section...

Highlights

New Posts

Same author

Expectations for Gia Nghia Expressway

Building synchronous traffic infrastructure On the afternoon of March 23, Dak Provincial People's Committee...

The project to raise the clearance of bridges in the Mekong Delta encountered difficulties because of land problems

On March 23, Deputy Minister of Transport Nguyen Xuan Sang and his delegation...

The Prime Minister directed to speed up the progress of allocation and disbursement of public investment capital

Official telegram sent to ministers, heads of ministerial-level agencies,...

Much read

Vietnam is an open country in terms of digital institutions

According to Minister Nguyen Manh Hung, Vietnam is an open country in institution building and listening to business opinions, especially foreign businesses. On the afternoon of March 21, at the headquarters of the Ministry of Information and Communications, Minister Nguyen Manh Hung had a meeting with the US-ASEAN Business Council (USABC) delegation. This is the group of businesses that has the most contributions to the Ministry of Information and Communications on issues of institution building,...

Taiwan will provide free semiconductor training to Vietnamese students

Vietnamese students are also paid during their studies and after graduation will work for Taiwanese semiconductor companies. Workers in a semiconductor factory in Taiwan - Photo: PD Talking to Tuoi Tre Online, Mr. Han Korea Dieu - head of the Taipei Economic and Cultural Office in Ho Chi Minh City - said that Taiwan's Ministry of Education has just announced "Special education program...

Many projects and initiatives were awarded the Ho Hao Hon Award: Harmonizing the Breath of Life

Dozens of playgrounds for children in difficult circumstances in remote areas are formed from post-production materials; Applying digital transformation to learning political theory lessons for union members and young people; The Ho Chi Minh Heritage Bookcase with children has been implemented from 1999 to present; or the "Spring Bus" program bringing tens of thousands...

Head of the Central Committee for Foreign Affairs meets with senior leaders of the Communist Party of China

On March 22, within the framework of his visit to China, Secretary of the Party Central Committee and Head of the Central Committee for Foreign Affairs Le Hoai Trung had meetings with senior leaders of the Communist Party of China. According to a Vietnam News Agency correspondent in Beijing, on March 3, within the framework of a working visit to China, Secretary of the Party Central Committee and Head of the Central Foreign Affairs Commission Le Hoai Trung had meetings with Standing Committee members. ...

The National Assembly supervision team works with the Government on many important issues

The National Assembly's supervision team working with the Government will evaluate the implementation of Resolution No. 43/2022/QH15 on fiscal and monetary policies to support the recovery program, socio-economic development and other issues. Resolutions of the National Assembly on a number of important national projects. Deputy Prime Minister Tran Luu Quang and delegates at the meeting. Photo: Trong Quynh/VPQH On March 22.3, at the National Assembly House,...

Same category

Prime Minister Pham Minh Chinh surveyed works and projects in Tien Giang province

* Go Cong sea dike, Tien Giang province has a total length of 15,8km; is responsible for ensuring the safety of life and property of the State and about 600 thousand households, protecting nearly 54 thousand hectares of natural land, including about 43 thousand hectares of arable land in coastal districts and towns of the province. including: Go Cong Dong, Go Cong Tay, Go Cong town and part of Cho Gao district....

Vietnam sends condolences on the terrorist attack in Russia

On March 23, Acting President Vo Thi Anh Xuan sent a telegram of condolences to Russian President Vladimir Putin after the terrorist attack on the evening of March 3 that left 22 people dead and many others injured. Previously, a group of gunmen believed to belong to the terrorist organization self-proclaimed Islamic State (IS) opened fire on civilians in the lobby of Crocus City Hall shopping center in Moscow....

A new path for Dak Nong after 20 years of re-establishing the province

Dak Nong closely combines economic development with socio-cultural development, ensuring progress and social justice, promoting unique cultural values, and the revolutionary history of the land and people. Dak Nong, creating harmonious and sustainable development. Especially in a locality with 40 ethnic groups living together, the province needs to focus resources...

The bookstore in Binh Phuoc collapsed after the fire, many properties were burned

Video: Bookstore in Binh Phuoc collapsed after the fire. On the evening of March 23, the police force of Phuoc Long town (Binh Phuoc province) announced that they were blocking the scene to investigate the fire that occurred at the Tuan Minh bookstore in the town. Phuoc Long commune. Initial information, around 3:19 p.m., some people saw smoke rising inside Tuan Minh bookstore (Long Phuoc ward, Phuoc Long town, Binh Phuoc province). Afterward,...

Attack in Moscow: There is currently no information on casualties related to Vietnamese people

The representative of the Vietnamese Embassy in Russia said there is currently no information on casualties related to Vietnamese people in the attack in Moscow. Authorities were deployed at the scene of the attack on the "Crocus City Hall" shopping center in Moscow, Russia on the evening of March 22, 3. Photo: THX/TTXVN After the attack occurred at the Crocus City Hall building in the shopping and performing arts center...

New Posts

"Connecting strength - Connecting love"

On March 23, at Luong Yen Secondary School (Hai Ba Trung District, Hanoi), the Children's Media Center (Ho Chi Minh Communist Youth Union Central Committee) coordinated with Save the Children (SCI) to organize Media program with the theme "Connecting strength - Connecting love". The event was organized by the members themselves...

Dalat purple phoenix - the beauty of nostalgia

Coming to Da Lat on this occasion, visitors will admire the purple color of poinciana flowers dyeing all the roads and street corners. This is a typical flower of Da Lat with a beauty that evokes memories and dreams, making people and tourists everywhere ecstatic. Origin of...

New Posts