HomeNewsEconomyLong An maximizes the progress of the Ring Road project...

Long An maximizes the progress of Ho Chi Minh City Ring Road 3 project


March 16.3, Reporter Newspaper Youth Field work at the construction site of Ho Chi Minh City Ring Road 3 Project in Ben Luc District (Long An). At the overpass point (belonging to package number 2 - XL2, Tan Buu commune, Ben Luc district), materials, vehicles, and machinery have all been gathered. The contractor divided the construction into 17 phases to speed up progress. However, there are still 4 houses remaining in the construction area.

Long An maximizes the progress of Ho Chi Minh City Ring Road 3 project - Photo 1.

People's houses are still staying in the construction area of ​​Ho Chi Minh City Ring Road 3 project through Tan Buu commune, Ben Luc district, Long An.

Mr. Pham Van Dan, Deputy Commander of the construction unit (under Tan Nam Construction Joint Stock Company) explained that these residential houses have not yet affected the construction progress. Because, the unit is currently drilling bored piles, pouring concrete for the pedestal and abutment body of the highway viaduct and the bridge on the left parallel route. However, to ensure on schedule, the People's Committee of Ben Luc H. (Long An) - the investor of the Land Clearance Subproject (GPMB) must relocate households no later than the end of June 6.2024.

Long An maximizes the progress of Ho Chi Minh City Ring Road 3 project - Photo 2.

The slogan shows the contractor's determination to speed up construction progress

Talk to PV Bao Youth, Mr. Le Thanh Ut, Chairman of the People's Committee of Ben Luc District (Long An), said that it will be implemented according to Resolution 57 of the National Assembly (Resolution 57/2022/QH15) and a number of solutions of the Provincial Party Committee and People's Committee of Long An province. To speed up the progress of the Ho Chi Minh City Ring Road 3 project through Long An province, the People's Committee of Ben Luc H. has cleared the site and basically handed over more than 43 hectares (98,5%) to construction units. Currently, there are still 31/394 households that have not been resettled, so these houses still exist in the project area. 

According to Mr. Ut, the People's Committee of Ben Luc H. is creating maximum conditions for these households to soon stabilize their new homes. In case it is necessary to use the centralized resettlement platform, in June 6.2024, Ben Luc H. will arrange able to understand. However, currently 6/400 households have not agreed to receive compensation due to many reasons and the People's Committee of Ben Luc District is continuing to advocate and resolve the issue.

Long An maximizes the progress of Ho Chi Minh City Ring Road 3 project - Photo 3.

Ho Chi Minh City Ring Road 3 Project has outlined its shape through the area of ​​Ben Luc District

Mr. Tran Thien Truc, Deputy Director of Long An Department of Transport (investor), informed that the Ho Chi Minh City Ring Road 3 project through Long An area is 6,84 km long and belongs to component project 7, 8 (divided into 3 packages XL1, XL2, XL3) with a total investment capital of nearly 4.200 billion VND, starting in June 6.2023. After starting construction, the construction units encountered difficulties with sand sources, leading to slow progress.

By the end of 2023, the shortage of basic sand will be resolved, along with capital being allocated promptly, so contractors will speed up progress to the maximum. Currently, over 25% of the total construction volume has been reached, reaching the approved schedule.

Long An maximizes the progress of Ho Chi Minh City Ring Road 3 project - Photo 4.

Contractors for the Ho Chi Minh City Ring Road 3 project are trying to speed up progress

It is expected that the Ho Chi Minh City Ring Road 3 project through Long An province will open the highway section in October 10.2025 and be completed in 2026.

Ho Chi Minh City Ring Road 3 project has a total length of about 76,34 km, passing through Ho Chi Minh City and 3 provinces of Dong Nai, Binh Duong, Long An, divided into 8 independently operated component projects. . The section passing through Ben Luc District (Long An) has a route length of 6,84 km, the scale of the complete phase is 8 expressway lanes, expressway level of 100 km/h; Parallel road on both sides (urban road with 2 - 3 lanes), urban road level of 60 km/h. Ho Chi Minh City Ring Road 3 is an inter-regional transportation project, along with other roads and transportation projects, connecting to industrial zones and clusters between Long An and the provinces of Binh Duong and Dong Nai. and Ho Chi Minh City… 



Source link

Same topic

Appearance of Binh Duong's 5th city

Ben Cat city in Binh Duong province was established on the basis of the original 234,35 km2 natural area and population of 364.578 people of Ben Cat town. The National Assembly Standing Committee voted to approve the Resolution on the establishment of An Dien and An Tay wards in Ben Cat town and the establishment of Ben Cat city in Binh...

Established two cities in Binh Duong and Tien Giang provinces

The National Assembly Standing Committee voted to approve the establishment of Ben Cat City in Binh Duong province and Go Cong City in Tien Giang province, on the afternoon of March 19. Ben Cat City was established on the basis of Ben Cat town, 3 km234,35 wide, population nearly 2, including 364.600 wards: An Dien, An Tay, Chanh Phu Hoa, Hoa Loi, My Phuoc, Tan Dinh, Thoi Hoa and Phu An commune. This city borders Tan Uyen City,...

Growing beautiful orchids like movies, Binh Duong farmers pay themselves high salaries, selling 1.500-2.000 pots/month

The demand for orchids is increasing, many farmers have boldly invested towards the goal of family economic development. Mr. Ngo Thanh Tung lives in group 3, Ba Phai hamlet, Long Nguyen commune, Bau Bang district (Binh Duong province)...

The Ministry of Transport recommends that localities manage highways with smart traffic

The Ministry of Transport has just sent a document to the People's Committees of provinces, cities and the Committee...

No minimum 4-lane highway requirement

At the meeting, reporting a number of major issues on the explanation, reception and revision of the draft Road Law, Chairman of the National Assembly's National Defense and Security Committee Le Tan Toi...

Highlights

New Posts

Same author

Much read

The fleet of commercial aircraft registered with Vietnamese nationality is decreasing

The number of aircraft registered with Vietnamese nationality as of March 15, 3 is 2024, of which there are 222 commercial aircraft, down 203 aircraft compared to February 6 and down 2 aircraft over the same period. 2024. It is forecasted that domestic airline ticket supply and prices will be quite tense during the summer peak of 21. According to...

The green color spread widely, banking stocks, securities, and retail led the way

The green color spread widely, banking, securities, and retail stocks led. The increasing momentum spread in most stock codes along with the rise of banking, securities, and retail groups helped VN-Index increase by 18 points. . Impressive increase Despite a large number of stocks in the previous extraordinary trading session on March 18 returning...

Ho Chi Minh City does not take tax incentives to attract investment

After more than 6 months of implementing Resolution 98/2023/QH15 on piloting a number of specific mechanisms and policies to develop Ho Chi Minh City, the locality has initially attracted a number of strategic investors to pour capital into projects. high-tech projects in the right direction. Investors still want tax incentives One of the most important issues...

Find breakthrough solutions to accelerate economic development

Finding breakthrough solutions to accelerate socio-economic development. The Editorial Team of the Socio-Economic Subcommittee of the 5th Party Congress held its first session to discuss the Draft Outline of the Five-Year Evaluation Report. current 10-year Socio-Economic Development Strategy 2021-2030. The general view is that there needs to be a breakthrough solution to complete at...

Where did 30 batches of durian exported to China come from that were contaminated with cadmium?

When Brazil enters the harvest season, what will the price of Robusta coffee be? Coffee prices in the weekend session were under downward pressure when inventories on the floor were high. From April 4, when Brazil enters the harvest season, Robusta coffee prices may decrease. Exporting agricultural products to the United States: Notes for Vietnamese businesses The opportunity for Vietnamese agricultural products to export to the United States is huge. To conquer...

Same category

Inauguration of a 1.443 billion VND industrial factory in Thanh Hoa

SAB Vietnam Industrial Factory, invested by SAB Vietnam Industrial Company Limited, has an area of ​​66,44 hectares, with a total investment capital of 1.443,220 billion VND. On March 20, at Bim Son Industrial Park, Bim Son town, Thanh Hoa province, SAB Vietnam Industrial Co., Ltd. under Weixing Group held a ceremony...

Sasco sets a profit target of 343 billion VND

Sasco plans to increase revenue by 5% to VND 2.903 billion and pre-tax profit to increase by 3% to VND 343 billion despite predicting that business activities may be affected by armed conflict, inflation, and rising fuel prices. High. Board of Directors of Tan Son Nhat Airport Aviation Services Joint Stock Company (Sasco, stock code: SAS)...

Youth Union of Thanh Hoa Customs Department is excited about Youth Month activities

(HQ Online) - Celebrating the 93rd anniversary of the founding of the Ho Chi Minh Communist Youth Union (March 26, 3 - March 1931, 26), the Youth Union of Thanh Hoa Customs Department has many meaningful activities , practical, contributing to creating a vibrant competitive atmosphere to successfully complete assigned tasks. Thanh Hoa Customs: Crude oil accounts for more than 3% of total Customs budget revenue...

Implementation of construction of Quang Tri 500 kV transformer station and connection lines

Deployment of construction of Quang Tri 500 kV transformer station and connection lines On March 20, 3, in Hai Lang district, Quang Tri province, EVNNPT and the Central Power Project Management Board (CPMB) organized the implementation Start construction of Quang Tri 2024 kV transformer station and connection line from Quang Tri - Vung Ang - Da Nang branch. ...

New Posts

Hoi An is the safest place to travel alone in the world, with the cheapest cost in Asia

Hoi An ancient town (Quang Nam, Vietnam) was honored to top the list of the safest solo travel destinations in the world compiled by the American website Smoky Mountains. According to the website, Hoi An has a crime rate of 6,25, compared to Peru's Lima, which has the highest crime rate...

Should you apply anti-peeping glass to your iPhone?

Anti-peeping tempered glass is no longer strange to smartphone users today. Anti-peeping tempered glass is a tempered film for phone screens. It has the effect of limiting the visibility of surrounding people within a 90-degree viewing angle. Thing...

Domestic coffee prices set an all-time record high, approaching 100.000 VND/kg

Coffee price today March 24: Trading around the record mark of 3 VND/kg At the end of the weekend trading session, Robusta coffee price...

Unexpectedly, the photo of a plate of spinach received more than 30.000 likes on social networks

Recently, netizens shared screenshots from a Locket account named Huong. This account captures the process of boiling water spinach and a plate of vegetables...

New Posts