Directing the project site, the Chairman of the Provincial People's Committee assigned specific tasks to localities and relevant departments, including focusing on resolving difficulties in land clearance; contractors should proactively secure materials for construction, and take advantage of favorable weather conditions to accelerate progress.
The goal set by the Chairman of the Provincial People's Committee, Nguyen Hoai Anh, is to ensure that 100% of public investment funds are disbursed according to the plan before December 31, 2026. Along with this, special attention must be paid to the quality of construction, labor safety, and the safety of people in the project area.
We all know that boosting public investment will be a crucial driving force and stimulus for the economy , building infrastructure for development in the coming years. However, disbursing this "seed capital" has never been easy. Over the years, many public investment projects have been stalled for extended periods, some projects have struggled to reach completion even after commencement, and funding for many projects has had to be carried over to the following year...
According to a report from the Department of Finance, as of May 22, 2026, the disbursement progress of the province's public investment plan for 2026 has not yet met the requirements of Plan No. 36/KH-UBND dated February 10, 2026, issued by the Chairman of the Provincial People's Committee. In particular, 14 out of 17 project owners in the province have not met the disbursement schedule as stipulated, including 7 project owners who have not yet disbursed any of their 2026 investment plan.
The directives issued by the head of the Provincial People's Committee during this field inspection should not be interpreted as isolated orders directed only at the investors, project management boards, and contractors directly managing and constructing the projects that the Chairman of the Provincial People's Committee has inspected.
Six months have passed, and there isn't much time left, while the disbursement rate of public investment funds that we must complete within the remaining time is very large.
It should also be noted that the remaining six months will be a period of very harsh weather conditions. In addition, there are many other tasks that must be completed on time. Therefore, the directive from the Chairman of the Provincial People's Committee is a political order, a very practical requirement, given that public investment is assessed to play a crucial role in "carrying" and promoting the province's growth to achieve "double-digit" targets in 2026 and throughout the 2026-2030 term. The demands of the task, along with the predicted many challenges, require each sector, each locality, and each investor to make appropriate calculations to resolutely complete the public investment plan and disburse public investment funds.
Thai Minh