HomeNewsNewsCause: Belt 3 of Ho Chi Minh City, Tan Van section

Cause: Belt 3 of Ho Chi Minh City, Tan Van section


10% slower than planned

The Ministry of Transport has just announced the conclusion of Deputy Minister of Transport Le Anh Tuan at the meeting to review the implementation of component project 1A of the construction investment project of Tan Van - Nhon Trach section, phase 1 of Ring Road 3. Ho Chi Minh City.

Reasons why Belt Line 3 of Ho Chi Minh City, Tan Van - Nhon Trach section, is behind schedule - Photo 1.

Construction of Ring Road 3 section Tan Van - Nhon Trach (Photo: My Le).

According to the report of My Thuan Project Management Board, up to now, the construction progress of the entire project has reached 43%, 10,8% slower than plan.

In which package CW1 reached nearly 64% of the plan, package CW2 only reached more than 12% due to not receiving enough construction site and the scarce supply of sand materials.

The Ho Chi Minh City Ring Road 3 project, Tan Van - Nhon Trach section, has a length of more than 8km, passing through Dong Nai province (more than 6km) and Ho Chi Minh City (nearly 2km).

The first point intersects with Provincial Road 25B (Nhon Trach, Dong Nai). The end point intersects with Ho Chi Minh City - Long Thanh - Dau Giay expressway.

The road is invested with a roadbed width of 20,5 - 26 m, including 4 motor vehicle lanes and 2 mixed vehicle lanes, design speed of 80 km/h.

Total project investment capital is about 6.955 billion VND, from ODA loans from the Korean Government through the Economic Development Cooperation Fund and counterpart capital from the Vietnamese Government.

The project will start construction in December 9 and is expected to be completed in May 2022.

To speed up the implementation of the project, the Deputy Minister of Transport requested the My Thuan Project Management Board to continue working with Nhon Trach district, urging to speed up site clearance progress and relocation of technical infrastructure works for handover. entire premises before March 31, 3.

“My Thuan Project Management Board and supervision consultants arrange adequate personnel to regularly and promptly inspect the site, control the progress and quality of construction to ensure compliance with the design and technical instructions given. Browser; Promptly propose solutions to remove difficulties, obstacles or adjustments that arise during the construction process," the Deputy Minister directed.

With specific instructions for package CW1, units are required to adjust the overall and detailed construction progress of the project as a basis for implementation to ensure completion before April 30, 4. under the direction of the Prime Minister.

In particular, contingency time must be taken into account to handle arising problems or unfavorable weather conditions, material supplies, etc. (if any).

My Thuan Project Management Board and supervision consultant are responsible for reviewing the approved technical design documents and technical instructions, the construction sequence of beam structures, and measures to control the construction camber of the main span of Nhon bridge. Trach due to construction not being done at the same time; Urgently complete the construction of the pier body, pier cap beams and leading spans to soon install Super-T beams.

In the CW2 bidding package, the Deputy Minister requested contractors to fully mobilize machinery, equipment, and construction resources right at the locations that had been handed over, to make up for the volume that was behind schedule; Proactively seek legal sources of sand materials to fully and promptly supply the project, with priority given to coordinating construction of sections that require treatment of soft ground with long waiting times for load loading.

Completed adjustment of investment policy for Nhon Trach bridge in May

Referring to the adjustment of the investment policy to add the Nhon Trach bridge unit to the project, the Deputy Minister of Transport assessed that progress is currently very slow.

“Regarding this content, the Government Office has directed implementation from April 4, however, it was not until the end of January 2023 that the Ministry of Transport received the report from the My Thuan Project Management Board.

The additional investment in the Nhon Trach bridge unit is very urgent to ensure synchronous, safe and smooth operation on the entire Ring Road 3 of Ho Chi Minh City according to the expressway scale. 

“My Thuan Project Management Board seriously learned from the slow implementation of adjusting project investment policies; Urgently prepare a report to receive and explain the comments of agencies under the Ministry on the project pre-feasibility study report, complete the dossier, and advise the Ministry of Transport to report to the Government in March. /3.

The next implementation process needs to coordinate closely with units of the Appraisal Council, especially with the agency in charge of appraisal, the Ministry of Planning and Investment, to promptly report, absorb, and strive to complete. Adjusting investment policies in May 5", leaders of the Ministry of Transport directed.

My Thuan Project Management Board is also required to proactively organize the implementation of the next steps of approving and adjusting investment projects; Negotiate with the sponsor to amend and supplement the loan agreement for the project to speed up implementation progress and soon put the project into construction.



Nguon

Same topic

Mai Dich steel overpass completes the final items to reach the finish line this week

TPO - After nearly a year of construction, two steel overpasses at Mai Dich intersection are rushing to complete the final items. According to the traffic organization plan between Thang Long Project Management Board (Ministry of Transport - investor) and Hanoi Department of Transport, the bridge will be completed before March 1, and put into use from April 31. To facilitate the exam...

A series of projects in Ho Chi Minh City will be accelerated thanks to the new approach

Bridge - Nguyen Khoai road, Belt 2, Moc Bai expressway... are expected to speed up progress when applying the mechanism to shorten compensation and site clearance time. After nearly a decade of "hanging up", the Nguyen Khoai bridge-road project, connecting districts 7, 4 and 1, is expected to start construction at the end of this year and be completed in 2027, helping to reduce traffic pressure in South Saigon in the coming months. background...

Binh Duong invested in 6 underground tunnels instead of building overpasses at ring road 3 intersections in Ho Chi Minh City

Binh Duong invests in 6 underpasses instead of building overpasses at intersections on Ring Road 3 in Ho Chi Minh City. Binh Duong Province will switch to investing in 6 underpasses instead of building overpasses at intersections on Ring Road 3, City. .HCM. Information from the People's Committee of Binh Duong province said that on March 11, Mr. Nguyen Van Loi, Secretary of the Binh Duong Provincial Party Committee worked with Mr. Oh Dongkun, General Director of Becamex Tokyu Company...

Three specific mechanisms help speed up the progress of Ho Chi Minh City Ring Road 3 project

On the afternoon of March 4, the National Assembly's supervision delegation, led by Vice Chairman of the National Assembly Nguyen Duc Hai, had a working session with the Ho Chi Minh City People's Committee on implementing Resolution 3 of the National Assembly on fiscal and monetary policies. supporting the socio-economic development recovery program and Resolution 43 on investment policy for Belt 57 project. Also attending the meeting were representatives...

Highlights

New Posts

Same author

Deputy Director of Thanh Hoa Police became Director of Nam Dinh Police

On the afternoon of March 26, Thanh Hoa Provincial Police held an announcement of the Decision of...

Trillion billion road project connecting Ninh Thuan

Tan Son (Ninh Thuan) - Duc Trong (Lam Dong) inter-regional road project...

How far is the Beltway 4 section through Dan Phuong district under construction?

Evaluation of the construction work of the entire Ring Road project...

Much read

Phu Quoc's 20-year transformation journey: Sweet fruits from the work of 'pulling eagles back to nest'

Considered a "paradise island" with a population of 28 large and small islands, but in the 2000s, people still only knew Phu Quoc as one of the 20 most beautiful pristine beaches in Asia (CNN review). Only with the appearance of a series of large investors with systematic tourism infrastructure development strategies did Phu Quoc truly transform. Shaping a "new destination...

70 years of Dien Bien Phu Victory: President Ho Chi Minh's strategic vision

Fully seven decades have passed, the Dien Bien Phu Victory is forever a shining symbol of the resilient and indomitable Vietnamese people. The historic victory of Dien Bien Phu, the pinnacle of the resistance war against French colonialism, was first of all the victory of the correct and creative political and military policies of the Party, headed by President Ho Chi Minh. . At the end of 1953, in Viet Bac, President...

Promoting the core role and paving the way for state-owned enterprises in the economy

(Chinhphu.vn) - The Government Office has just issued Notice No. 127/TB-VPCP dated March 23, 3 on the conclusions of the Standing Government at the Spring Meeting with the above typical state-owned enterprises. nationwide. The announcement clearly states that the Government always accompanies businesses, including state-owned enterprises (SOEs); Focus on developing SOEs quickly, sustainably, in the right direction, contributing to implementing the Party's policy of...

Parade of floats before the Avalokiteshvara Festival

7 floats decorated with dragons and lotus flowers, with a statue of Guanyin Buddha on top, paraded through many main streets of Da Nang on the evening of March 25. At more than 3:18 p.m., the convoy departed from the Ngu Hanh Son relic and scenic area, moving on Le Van Hien, Ngu Hanh Son, Ngo Quyen, Dragon Bridge avenues, then looped down to Bach Dang along the Han River and many other routes. Da Nang central street. Leading...

How does the Red Sea crisis impact the global supply chain?

Attacks by Yemen's armed Houthi forces on cargo ships have affected the stability of the Red Sea route and container shipping rates. The security risks of this route have spread to other routes, leading to a chain reaction, disrupting global transportation. With the US and the West attacking the targets of the forces...

Same category

Gia Lai: Training and dissemination of legal education on gender equality

Through the conference, to provide basic legal information on gender equality, gender-based violence and domestic violence prevention..., equipping delegates with basic knowledge about equality. gender equality, so that delegates can proactively and actively propagate to raise awareness of local people about gender equality, contributing to enhancing the position and role...

It is recommended that Hanoi should be piloted to proactively organize specialized agencies

Reporting on a number of major issues explaining, absorbing and revising the Capital Law Project (amended) at the 5th Conference of full-time National Assembly Delegates, Chairman of the Law Committee Hoang Thanh Tung said. , on the organization of urban government, based on the opinions of National Assembly deputies, the Standing Committee and agencies have agreed to absorb and revise the...

National Assembly delegates proposed to legislate highway standards and regulations

Discussing at the meeting, delegate Nguyen Ngoc Son (Hai Duong province's National Assembly delegation) said that the Government is currently submitting amendments to highway technical regulations and standards. Through a survey by the National Assembly's Science, Technology and Environment Committee, there are still many inadequacies in the application of regulations and standards in the road sector. "Currently we have not applied it so we do not know how to operate the standards and regulations...

Awaken and promote the strengths of youth in the Central Agencies Sector

On the afternoon of March 26, at Vietnam Television, the Standing Committee of the Youth Union of Central Agencies organized the 3rd Anniversary of the founding of the Ho Chi Minh Communist Youth Union and a Dialogue between Party Committee Secretaries of the Block of Agencies. Central officials; Standing Secretary of the Central Youth Union with typical officials, union members and youth in 93 with the theme "Developing quality young human resources...

New Posts

70 years of Dien Bien Phu Victory: Back to the revolutionary base area of ​​Muong Phang

In the days of March after 70 years of the Dien Bien Phu Victory, crowded groups of tourists from far away returned to Muong Phang, to the relics of the Dien Bien Phu Campaign Command. Launching the Music Month commemorating the 70th anniversary of the Victory Dien Bien PhuCelebrating the 70th Anniversary of the Dien Bien Phu Victory: Will...

The whole country saves 428.000 kWh of electricity in 1 hour of turning off the lights in response to the 2024 Earth Hour Campaign

On the evening of March 23, 3, in response to the Earth Hour Campaign, many countries and territories around the world along with 20124 provinces and cities of Vietnam responded to the Earth Hour Campaign by taking shortcuts. lights and minimize the use of electrical appliances for 63 hour, from 1:20 p.m. to...

National Assembly delegates proposed to legislate highway standards and regulations

Discussing at the meeting, delegate Nguyen Ngoc Son (Hai Duong province's National Assembly delegation) said that the Government is currently submitting amendments to highway technical regulations and standards. Through a survey by the National Assembly's Science, Technology and Environment Committee, there are still many inadequacies in the application of standards,...

New Posts