 |
| Tran Bien Ward has completed land clearance to implement the Nguyen Binh Khiem Extended Road Construction Project (connecting Huynh Van Nghe Road with the Dong Nai River embankment road). |
Reasons for the "holding back" of capital flows.
According to the Department of Finance, in 2026, the remaining public investment capital plan for Dong Nai city, to be allocated in detail to projects, is over 25.8 trillion VND. Of this, the capital allocated to commune-level People's Committees is over 6.3 trillion VND. As of June 17th, the total public investment capital allocated to commune-level People's Committees that has been disbursed is nearly 671 billion VND, reaching 10.5% of the allocated capital plan. This rate is significantly lower than the city's average disbursement rate at the same time, which is nearly 31%. Notably, 80 out of 95 communes and wards have a disbursement rate lower than the city's average.
Mr. Tran Anh Tu, Deputy Director of the Department of Finance, said: Projects invested by communes and wards are all new projects being implemented in the area. Therefore, in the first months of the year, localities mainly focused on completing dossiers and procedures for investment preparation, leading to slow disbursement of public investment capital and a low disbursement rate.
Mr. Tang Quoc Lap, Chairman of the Long Khanh Ward People's Committee, said: In 2026, the city allocated nearly 59.8 billion VND to the locality. This capital was allocated to new projects, with no ongoing projects. Therefore, the locality had to carry out investment preparation and bidding procedures to select contractors for the projects. To date, although the contractor selection process has been basically completed, the locality has not yet disbursed the funds.
According to City Party Committee member and Vice Chairman of the City People's Committee Ho Van Ha, in order to accelerate the disbursement of public investment capital allocated to commune-level People's Committees, the end of September 2026 is the deadline for completing the preparation of construction drawings and cost estimates for public investment projects where commune-level People's Committees are the investors.
You may also like

Boosting GrowthWith the high growth target set for 2026, national target programs continue to play a crucial lever role. However, the implementation in the first few months of the year shows that, without promptly addressing bottlenecks in mechanisms and implementation, this capital flow is unlikely to achieve the expected effectiveness. In Minh Hung commune, the total public investment capital is over 91 billion VND, including capital allocated by the City People's Committee and capital from land use revenue. Currently, the disbursement rate of local capital is below 20% of the plan. According to Mr. Le Khac Dong, Chairman of the Minh Hung Commune People's Committee, the total public investment capital of the locality in 2026 is allocated to 14 projects. To date, 9 projects have achieved a disbursement rate, and 5 projects are in the contractor selection process. However, among the projects in the area, some road construction projects are still facing land acquisition issues due to the relocation of electrical infrastructure. Other projects are experiencing difficulties in the supply of construction stone materials, affecting construction progress and capital disbursement.
Quickly remove the "bottlenecks".
According to the Deputy Secretary of the City Party Committee and Chairman of the City People's Committee, Nguyen Van Ut: Currently, a large number of communes and wards still have disbursement rates below the city's average. The problems affecting disbursement progress stem from the fact that communes and wards are still confused about the orientation of public investment projects, and the process of advising the People's Committees of communes and wards on preparing investment projects is still lengthy. In particular, localities have not yet identified a list of key projects to prioritize in terms of capital allocation.
To expedite the disbursement of funds by local authorities, the City People's Committee has requested that communes and wards promptly develop plans, timelines, and commitments regarding the disbursement schedule and submit them to the Department of Finance for compilation. The City People's Committee will monitor the implementation by communes and wards based on the commitments, plans, and timelines that have been registered.
Chairman of Tran Bien Ward People's Committee, Nguyen Duy Tan, said: The ward is focusing on accelerating the appraisal and approval of projects to ensure their early implementation. Simultaneously, additional personnel will be added to expedite these tasks, thereby promoting the disbursement of funds. "Tran Bien Ward is committed to disbursing 70% of the planned funds by September 30th and essentially completing the disbursement of all public investment funds for 2026 by the end of November 2026," Mr. Nguyen Duy Tan stated.
According to the leaders of Dong Phu Ward People's Committee, out of the 5 projects allocated funding in 2026, 4 have already commenced construction, and the remaining project will also start in June 2026. The locality is striving to achieve a 50% disbursement rate by the end of June and complete the disbursement of all planned funds for 2026 by the end of October.
You may also like

Training on product and goods traceability in 2026On June 24th, the Department of Science and Technology of Dong Nai City organized a training course on product and goods traceability for 2026 for representatives of city departments and agencies; People's Committees of communes and wards; businesses, cooperatives, OCOP entities, and production and business establishments in the area. Pham Tung
Source: https://baodongnai.com.vn/kinh-te/ha-tang-du-an/202606/thuc-day-giai-ngan-von-dau-tu-cong-giao-cap-xa-1673476/