According to the Ministry of Health , the Bach Mai Hospital 2 project and the Viet Duc Friendship Hospital 2 project (in Ninh Binh) will be completed before November 30.
Regarding medical equipment for professional work, Bach Mai Hospital, Branch 2, has completed the purchase contract for 82 devices. The installation is expected to be completed before December 25, and the contractor has committed to deliver the equipment from November 15.

Bach Mai Hospital is currently prioritizing human resource training for its second facility in Ninh Binh.
PHOTO: LIEN CHAU
Contractors in the joint venture will coordinate to test the load and run partial systems when qualified, before connecting and testing the systems. The expected completion date is November 30.
Regarding human resources when Bach Mai Hospital 2 comes into operation, Director of Bach Mai Hospital Dao Xuan Co said that the most important thing is people. The hospital has publicly recruited more than 800 doctors and nurses, of which 600 people in Hanoi volunteered to work at the new facility. The newly recruited personnel will receive additional training at facility 1 in Hanoi before working at facility 2.
"We guarantee the quality of facility 2 is equivalent to facility 1," Mr. Dao Xuan Co affirmed.
Bach Mai Hospital, branch 2 in Liem Tuyen Ward (Ninh Binh) has been invested in a modern and synchronous manner with a scale of 1,000 beds and full specialties equivalent to the main branch. The hospital is urgently reviewing equipment, human resources and operating procedures, expected to be completed before November 15 to submit to the Ministry of Health for approval.
A representative of Bach Mai Hospital said that the progress of completing the second facility in Ninh Binh is being accelerated to be put into operation in 2025, to reduce the load on the central line and improve the quality of medical examination and treatment for people in the Northern Delta region.
Viet Duc Friendship Hospital, Branch 2, has completed the negotiation of the purchase contract for 83 devices and will complete the contract signing before October 30. The installation is expected to be completed before December 25.
Regarding human resources, a representative of Viet Duc Friendship Hospital said that they have implemented a plan to train, recruit, and rotate high-quality staff from facility 1, ensuring professional requirements when facility 2 comes into operation.
Source: https://thanhnien.vn/benh-vien-bach-mai-co-so-2-du-kien-hoat-dong-tu-thang-12-185251030190905949.htm


![[Photo] General Secretary To Lam attends the Vietnam-UK High-Level Economic Conference](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/30/1761825773922_anh-1-3371-jpg.webp)
![[Photo] The Third Patriotic Emulation Congress of the Central Internal Affairs Commission](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/30/1761831176178_dh-thi-dua-yeu-nuoc-5076-2710-jpg.webp)
![[Photo] General Secretary To Lam meets former British Prime Minister Tony Blair](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/30/1761821573624_tbt-tl1-jpg.webp)

![[Photo] Touching scene of thousands of people saving the embankment from the raging water](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/30/1761825173837_ndo_br_ho-de-3-jpg.webp)











































































Comment (0)