HomeDestinationsHo Chi Minh CityTwo years, nearly 200 public investment projects are late for settlement

Two years, nearly 200 public investment projects are late for settlement


Two years, nearly 200 public investment projects delayed settlement photo 1

The monitoring session took place after the People's Council of Ho Chi Minh City directly supervised 18 units and surveyed 20 projects. Photo: HOANG HUNG

On the afternoon of June 15, the People's Council of Ho Chi Minh City supervised the implementation of public investment in the 6-2021 period for the People's Committee of Ho Chi Minh City. Comrade Nguyen Thi Le, Deputy Secretary of the City Party Committee, Chairman of the People's Council of Ho Chi Minh City is the head of the supervisory delegation.

Nearly 200 projects violated the settlement time

Vice Chairman of the People's Council of Ho Chi Minh City Nguyen Van Dung said that, implementing the supervision program of the People's Council of Ho Chi Minh City, in the past three months, the People's Council of Ho Chi Minh City has supervised at 18 units, departments and branches of districts, project management boards, governing agencies, project investors and conducted actual surveys of 20 public investment projects. Thereby, some difficulties, limitations and recommendations are noted.

Through the actual survey of 20 public investment projects, the head of the Economic - Budget Department of the People's Council of Ho Chi Minh City, Le Truong Hai Hieu, said that one of the difficulties is the payment and settlement. Many projects completed in the medium term so far are still making payments, such as the irrigation project on the right bank of the Saigon River (South of Tra canal) and the irrigation project on the right bank along the Saigon River in Cu Chi district from Provincial Road 8 to Tra canal (North of Tra canal).

Meanwhile, Representative Nguyen Van Dat, deputy head of the Ho Chi Minh City People's Council's Legal Department, after expressing concern with 111 projects at risk of not being completed in the 2021-2025 period, also raised concerns about the final settlement of completed projects.

Representative Nguyen Van Dat cited the report of the People's Committee of Ho Chi Minh City about the very low settlement rate, in 2021 there were 2.208 projects with a value of 121.000 billion VND, but only 923 projects were settled, reaching 41,8%; In 2022, it will only reach 59,63%.

Two years, nearly 200 public investment projects delayed settlement photo 2

Representative Nguyen Van Dat asked questions at the monitoring session. Photo: HOANG HUNG

NE analyzed, through the report, there were about 200 projects violating the settlement time. This puts the responsibility of the People's Committee of Ho Chi Minh City in the direction of the department and the investor. Because, late settlement leads to outstanding debt in capital construction, slow disbursement progress of public investment, slow exploitation of assets formed after investment.

“While this work is very important, why is it slow? How are the units dealing with these settlement violations?", asked Representative Nguyen Van Dat.

On behalf of the People's Committee of Ho Chi Minh City reporting, Deputy Director of the Department of Planning and Investment Pham Trung Kien explained that a number of projects have been completed and put into use, but there are still problems with compensation for site clearance (people have not agreed with the compensation price), so the investor has not been able to prepare project settlement documents.

In addition, during the year, the number of completed projects increased a lot, and there was a situation in the same time period, the number of completed projects submitted to the verification agency and sent to the verifying agency was high, but due to the limited number of officers and employees in charge of verifying the final settlement, the verification of the settlement was delayed.

Besides being a subjective reason, some investors have not focused on finalization of completed projects, so the number of dossiers of late finalization is still high.

Two years, nearly 200 public investment projects delayed settlement photo 3

Deputy Director of Department of Planning and Investment Pham Trung Kien reported to the monitoring team. Photo: HOANG HUNG

Poor coordination, slow ground clearance

Previously, reporting to the supervisory team, Deputy Director of the Department of Planning and Investment Pham Trung Kien said that in the period of 2021-2025, the central budget allocated to Ho Chi Minh City is more than 33.000 billion VND, of which more than 32.100 billion VND has been allocated. The city's budget capital is more than 142.500 billion VND, detailed allocation of nearly 140.000 billion VND.

In the past two years, the disbursement has not been as expected, mainly due to the impact of the epidemic in 2021 and impacts from international conflicts and general economic difficulties of the world and the country. In particular, problems in compensation and site clearance are also a big cause.

Through supervision and professional practice, Representative Tran Van Bay, Deputy Director of the Department of Natural Resources and Environment, said that there are two emerging problems in site clearance. It is a valuation consulting unit, currently the number of businesses with the valuation consulting function is very large, but the reality is that it is fully capable, qualified and has actual valuation activities. There is a project rented 20 times without any units participating, very deadlocked.

Two years, nearly 200 public investment projects delayed settlement photo 4
Representative Tran Van Bay, Deputy Director of Ho Chi Minh City Department of Natural Resources and Environment. Photo: HOANG HUNG

According to him, the department should advise the People's Committee of Ho Chi Minh City to study and propose a mechanism to establish state-owned price appraisal consulting units.

“Currently in the notary sector, the private and public sectors compete fairly with each other. In judgment enforcement, there is a private bailiff. As for price appraisal consulting, this field should also have the participation of the state sector, "said Representative Tran Van Bay.

The second issue, according to Representative Tran Van Bay, is the organizational structure and staffing of the compensation and site clearance committees of the districts. Many localities established this Committee with a strong force, but after that, the number of projects decreased, the human resources were also dispersed. Many places also do not have money to pay salaries to members of the Board, because it is an autonomous unit, receiving 2% of the compensation budget, so without a project, there is no salary. While this is a difficult task, it takes practical experience to be able to do it.

The Delta believes that this consolidation will be very necessary when coming here, Ho Chi Minh City will carry out major projects such as renovating Xuyen Tam canal, building highways...

Disbursement of medium-term public investment capital 2021-2025:

(unit: billion VND)

Year 2021

Year 2022

Year 2023

(as of May 31)

total capital

19.721

61,1%

26.635

71,3%

9.230

13,5%

Central capital

9.230

34,8%

1.548

62,44%

6.487

43,3%

Local capital

18.680

63,82%

25.086

71,9%

2.742

5,1%

Also related to the work of compensation for site clearance, Representative Huynh Thanh Hung, Deputy Head of the Economic - Budget Department of the People's Council of Ho Chi Minh City mentioned the slow relocation of technical infrastructure for project construction. In which, the construction project of the intersection of Nguyen Van Linh - Nguyen Huu Tho had to wait for 15 months for approval to relocate the infrastructure, leading to delayed construction. Since then, NE raised the issue of coordination between agencies.

Sharing the same view on coordination between agencies, Representative Do Thi Minh Quan, Chief of Office of the People's Council of Ho Chi Minh City, said that through working sessions, the department suggested that it be necessary to determine the responsibilities of districts where there is little interest in site clearance. But in fact, when going to supervise, the district said that in the process of implementing this work, there were many documents sent to the department asking for support. That is, the coordination between departments and districts in site clearance needs to be done more closely.





Nguon

Same topic

Strengthen supervision and speed up the progress of projects serving people's livelihood

According to Chairman of Hoa Vang District People's Committee Phan Van Ton, in 2 and 2022, Hoa Vang is assigned to implement 2023 group C projects, of which 8 projects have been completed, 2 projects are under construction. In 6, it will be assigned to be the investor of 2024 projects, with a total budget of nearly 39 billion VND. Currently, there are 70 projects that are behind schedule for over 2 years, both...

Proposing a synchronous investment plan for Dong Dang expressway

Proposed synchronous investment plan for Dong Dang - Tra Linh expressway with 4 lanes. Expansion of Dong Dang - Tra Linh expressway to reach the planned scale of 4 lanes, roadbed width of 17m is proposed to be implemented as a project. The project is independent from the phase 1 project that is being invested. Mix...

Support to ensure construction of Package A1-1 Ben Luc - Long Thanh Expressway

Support to ensure the construction of Package A1-1 for Ben Luc - Long Thanh Expressway Construction of Package A1-1, Ben Luc - Long Thanh Expressway Project, intersection area with Ho Chi Minh City - China Expressway Luong in Long An province is being obstructed, contractors cannot access the construction site. Construction of line section...

Hop Long is the longest viaduct on Dien Chau Expressway

Than Vu 2 Bridge has a total length of nearly 1.300m, is a land overpass...

Organize scientific construction, speed up the progress of the Northern Expressway

Many problems hinder construction progress. On March 21, the business trip continued...

Highlights

New Posts

Same author

The woman "exploded" the procedures to study abroad and appropriated more than 8 billion VND

Nguyen Phuong Thanh "exploded" that she had a relationship at the US Consulate General, potentially helping Mr. G. get approval for procedures to study abroad. Trusting, Mr. G. gave Thanh nearly 4,6 billion VND and 153.000 USD. At the same time, Thanh promised to help and asked Mr. G. many times to give Thanh money to take care of the procedures. Mr. G. believes in the words of...

Korea: Medical professors are ready to resign en masse

On March 24, South Korean officials said the months-long confrontation between the government and doctors is expected to worsen as medical school professors resign en masse. According to the Korean National Medical School Professors Council, professors of medical schools nationwide will begin submitting their resignations on March 3 and will reduce...

The Russian President declared March 24 a day of national mourning

On March 23, speaking on national television after the attack at the Crocus City Hall theater in Moscow, Russian President Vladimir Putin announced that March 3 would be a day of national mourning, commemorating the victims of the massacre. this bloody terrorist attack. According to Russia's TASS news agency, a new updated report from the Russian Investigation Committee said the number of victims...

Much read

Same category

Ho Chi Minh City attracts high-tech investors

Ho Chi Minh City - the major economic center of Vietnam, with a population of more than 10 million people, contributing up to 25% of GDP and 30% of budget revenue, is the city with the highest labor productivity in Vietnam, where leading industry experts gather, with a smart education system, providing high-quality human resources to meet the needs of high-tech industries...

Binh Phuoc: A baby girl was born in a rare "wrapping of cashews"

Late on June 15, information from Hoan My Binh Phuoc Hospital, Tien Hung commune, Dong Xoai city, Binh Phuoc province said that on the same afternoon, the hospital performed a rare birth, the baby was born intact. Amniotic capsule (catheter capsule). Quang Ngai police help pregnant woman who was abandoned by the garage. The woman gave birth to her baby in the bathroom, her health has stabilized. Saved the life of the fetus that "got out" of the abdomen because the woman...

Honoring the art of Cham pottery and opening the Ninh Thuan Grape - Wine Festival in 2023

SGGPO June 15, 06 2023:23 On the evening of June 02, in Phan Rang - Thap Cham City (Ninh Thuan province), the People's Committee of Ninh Thuan province coordinated with the Ministry of Culture, Sports and Tourism to solemnly organize a ceremony to welcome the UNESCO certificate. List of "Ceramic art of the Cham people in the List of intangible cultural heritage in need of urgent protection" and opening the Ninh Thuan Grape - Vang Festival in 15. Attending the ceremony was the President of...

Quang Ngai: The historic site of the Van Tuong victory has deteriorated

SGGPO June 15, 06 2023:21 The Van Tuong Victory Historical Relic Complex has been recognized as a National Monument since 38 in Binh Hai commune and Binh Hoa commune, Binh Son district, Quang Ngai province. However, since then, many relics in Binh Hoa commune have not been maintained, repaired, or cared for and have seriously degraded and damaged. On the concrete road between rice fields,...

Quang Binh: Arrested a person who received 2,7 billion VND to run a sentence

SGGPO June 15, 06 2023:18 On June 55, Mr. Le Hong Viet, Chairman of the People's Committee of Quang Phuong commune (Quang Trach district, Quang Binh province) confirmed that a person in the area was arrested by the authorities for broker running the case. Accordingly, the Supreme People's Procuracy Criminal Investigation Department sent people to Quang Phuong commune and read the arrest warrant for Mr. Nguyen Duc Thuan (born 15, residing in Phap Ke village, Quang Phuong commune), supervisor...

New Posts

Prosecuting a female director in Ha Nam for buying and selling false invoices worth 730 billion VND

On the evening of March 24, information from the Ha Nam Provincial Police, the Security Investigation Agency, and the Provincial Police have just prosecuted the case and decided to prosecute Le Thi Hau (born 3, residing in Hoang Ward). Dong, Duy Tien town, Ha Nam) and 1980 other defendants to investigate...

Vice Chairman of the National Assembly, Senior Lieutenant General Tran Quang Phuong attended the Opening Session of the IPU-148 General Assembly

Taking place from March 23-27.3, the IPU-148 General Assembly has the theme "Parliamentary diplomacy: building bridges for peace and development". Delegates will participate in...

Go to the registration site as fast as lightning because you're afraid of being scammed

"This is the online registration number. Today, quite a few parents came to register for admission directly," a representative of the production unit of Fast as Lightning season 5 told Tuoi Tre Online. Perhaps.. .

Positive outlook for Vietnam's economy

Vietnam's economy is considered by experts to be on the right track with positive long-term prospects. ...

New Posts