The expansion of Provincial Road 825 from Hau Nghia to Provincial Road 822B has disbursed nearly 70% of allocated capital.

Việt NamViệt Nam22/09/2023

Project to expand Provincial Road 825 from Hau Nghia town to Provincial Road 822B with a length of 6.8km

This project was approved by the Provincial People's Committee in Decision No. 2868/QD-UBND dated April 1, 2022. Since the commencement of construction in 2022, 74.5 billion VND of provincial budget capital has been allocated, of which over 50.3 billion VND has been disbursed (reaching 67.5%).

According to the Department of Transport, Package No. 1 (section from DT.823 intersection to Km20+500) with a length of 2.6km is undertaken by Thai Son Corporation Limited Company. Currently, the structure is being cast and the drainage system is being installed, with the implementation value reaching nearly 17%.

Package No. 2 (Km 20+500 to Km 22+830.10), 2.3km long, is undertaken by Dai A Chau Construction and Trading Production Company Limited. The drainage culvert has been completed, and the manhole is being completed, with the implementation value reaching 68%.

Package No. 3 (Km22+830.10 to the end of the route), 2.03km long, is undertaken by Trieu Dai Vu Company Limited. The drainage culvert and curb have been completed, and the manhole is being completed, with the implementation value reaching 48.5%.

Regarding this project, the Provincial People's Committee has approved the extension of Bau Trai culvert. Currently, the Project Management Board is completing the procedures for approval./.

Le Duc