Deputy Prime Minister Le Thanh Long: Accelerate construction of expressway through Phu Yen - Khanh Hoa.

Báo Xây dựngBáo Xây dựng12/03/2025

On the afternoon of March 12, the government delegation led by Deputy Prime Minister Le Thanh Long continued its inspection of the Chi Thanh - Van Phong expressway (through Phu Yen) and the Khanh Hoa - Buon Ma Thuot expressway (through Khanh Hoa and Dak Lak ).


Complete land clearance in March.

Acknowledging the efforts of the investor and the construction unit in overcoming difficulties related to site conditions, geology, material limitations, waste disposal sites, and unpredictable weather, Deputy Prime Minister Le Thanh Long also highly appreciated the responsibility of the local authorities in land clearance work.

Phó thủ tướng Lê Thành Long: Tăng tốc thi công cao tốc qua Phú Yên - Khánh Hòa - Đắk Lắk- Ảnh 1.

Deputy Prime Minister Le Thanh Long inspects the progress of the Khanh Hoa - Buon Ma Thuot expressway project.

Looking ahead, the Deputy Prime Minister requested that relevant units coordinate with local authorities to clarify difficulties and obstacles and resolve them promptly. The contractor should take advantage of favorable weather conditions to accelerate construction progress.

Phó thủ tướng Lê Thành Long: Tăng tốc thi công cao tốc qua Phú Yên - Khánh Hòa - Đắk Lắk- Ảnh 2.

Deputy Prime Minister Le Thanh Long presents gifts to workers constructing the expressway through Khanh Hoa province.

"Local authorities must complete land clearance before March 31st. Monthly, provincial leaders need to review the progress of land clearance to provide timely guidance and resolve any obstacles and difficulties."

"Investors and contractors should revise the schedule, find solutions to compensate for the delayed output, and organize construction in '3 shifts, 4 teams' to ensure completion targets are met," the Deputy Prime Minister said, emphasizing: Investors need to direct contractors to implement the project's critical paths, increase personnel, machinery and equipment as needed; strengthen supervision, ensure technical safety, and prevent corruption…

Thousands of workers and engineers are working tirelessly to push the project's progress.

Reporting to the Deputy Prime Minister, the leaders of Project Management Board 7 (the investor of the Chi Thanh - Van Phong expressway project) stated that Phu Yen province has completed land clearance, relocation of technical infrastructure, and handed over the land to the contractor for construction. The reserves of earth fill materials meet the needs.

You may also like
The stunning North-South Expressway winds its way through the mountains and rivers of the Central Highlands.
The stunning North-South Expressway winds its way through the mountains and rivers of the Central Highlands.The Quy Nhon - Chi Thanh section of the North-South Expressway is considered one of the most beautiful routes, a wonderful combination of modern infrastructure and pristine nature.
Establish key research centers and laboratories to serve strategic technologies.
Establish key research centers and laboratories to serve strategic technologies.(Chinhphu.vn) - On the morning of June 23, at the Government headquarters, Deputy Prime Minister Ho Quoc Dung chaired a meeting on the Project for the Development of Key Research, Testing and Laboratory Centers Serving Strategic Technologies.
Vietnam and Canada are boosting defense cooperation in potential areas.
Vietnam and Canada are boosting defense cooperation in potential areas.(Chinhphu.vn) - On June 23, in Hanoi, General Phan Van Giang, Member of the Political Bureau, Deputy Prime Minister, and Minister of National Defence, received the Ambassador Extraordinary and Plenipotentiary of Canada to Vietnam, James Nickel.

However, 2 out of 4 quarries are facing significant difficulties due to the presence of large boulders and loose rocks in the soil. The lengthy procedures for obtaining permits to extract materials consume a large portion of the time needed for roadbed construction and soil stabilization, significantly impacting the project's completion schedule.

Phó thủ tướng Lê Thành Long: Tăng tốc thi công cao tốc qua Phú Yên - Khánh Hòa - Đắk Lắk- Ảnh 3.

Son Hai Construction Company overcomes difficulties regarding land acquisition for the Khanh Hoa - Buon Ma Thuot expressway project.

Overcoming difficulties related to weather and materials, contractors mobilized 44 construction teams, with nearly 1,700 officials, engineers, and workers, and 768 pieces of equipment, meeting the approved construction schedule. Cumulative output to date is 5,654 billion VND, reaching nearly 70% of the construction contract; capital disbursement to date has reached nearly 66%.

"To overcome the difficulties in loading and treating weak soil foundations, the investor has directed contractors to maximize the use of machinery and equipment, increase shifts and work schedules to speed up the excavation of overburden, blast rock, and increase the capacity of soil extraction for road embankment."

"During favorable weather conditions, contractors have increased their earthworks excavation capacity from 13,000 m3/day to 18,000 m3/day," the leader of Project Management Board 7 said.

Representatives of the investor of the Khanh Hoa - Buon Ma Thuot expressway project also stated that, for Component Project 1 (DATP1), in order to complete the first 20km of the route in 2025 as directed by the Prime Minister, the People's Committee of Ninh Hoa town (Khanh Hoa) needs to promptly resolve obstacles and hand over the entire land area.

Regarding DATP2, the investor expressed the desire for the leaders of Dak Lak province to pay attention and direct the early completion of the approval of the adjusted land use plan at the district level, and the conversion of the additional forest land use purpose.

The People's Committee of Khanh Hoa province continues to direct relevant agencies and localities to accelerate the progress of tasks related to the recovery of forest assets, and to promptly hand over the additional land area of ​​nearly 2 hectares to the contractor for the implementation of Project 2.

Regarding DATP3, the investor requests the Department of Agriculture and Environment to advise and report to the People's Committee of Dak Lak province to soon approve additional locations for dumping excess materials (approximately 0.4 million m3 for packages XL02 and XL03), ensuring the project's completion on schedule.

The Chi Thanh - Van Phong component project, passing through Phu Yen province, has a total length of over 48km (through the districts, towns and cities of Tuy An, Tuy Hoa City, Phu Hoa district, Tay Hoa district and Dong Hoa town).

The route starts at the Chi Thanh intersection (located in Chi Thanh town, Tuy An district), connecting to the Quy Nhon - Chi Thanh expressway. The route ends at the intersection with National Highway 1 (located in Hoa Xuan Nam commune, Dong Hoa town), connecting to the northern access road to the Deo Ca tunnel and the Van Phong - Nha Trang expressway.

You may also like
Focus on completing land clearance work and accelerating the construction progress of the Quy Nhon - Pleiku Expressway Project.
Focus on completing land clearance work and accelerating the construction progress of the Quy Nhon - Pleiku Expressway Project.(GLO) - On the afternoon of June 19th, at the headquarters of Binh Khe Commune People's Committee, Vice Chairman of Gia Lai Provincial People's Committee Nguyen Tu Cong Hoang chaired a meeting to address issues related to compensation, support, land clearance, and construction progress of the Quy Nhon - Pleiku expressway project.
Proposal to add the Ha Tinh - Cau Treo expressway route to the planning.
Proposal to add the Ha Tinh - Cau Treo expressway route to the planning.Five new expressways, connecting the northern border region to the Central Highlands and the Cau Treo International Border Gate (Ha Tinh province), are being proposed for inclusion in the Road Network Plan until 2050.
Deputy Prime Minister Le Thanh Long inspects the Bach Mai Hospital Phase 2 Project and Viet Duc Hospital.
Deputy Prime Minister Le Thanh Long inspects the Bach Mai Hospital Phase 2 Project and Viet Duc Hospital.On the afternoon of October 28th, Deputy Prime Minister Le Thanh Long led a working group to inspect the progress of the investment project to build the second facility of Bach Mai Hospital and Viet Duc Hospital in Ninh Binh.

The project has a total investment of nearly 11,000 billion VND, commenced in early 2023 and is expected to be completed in the fourth quarter of 2025.

The Khanh Hoa - Buon Ma Thuot expressway project has a total length of over 117km (with 32.7km passing through Khanh Hoa province and 84km passing through Dak Lak province), and a total investment of nearly 22,000 billion VND.

The starting point is at the intersection of National Highway 26B and National Highway 1 (in Ninh Hoa town, Khanh Hoa province). The end point is on the Ho Chi Minh Highway, eastern bypass of Buon Ma Thuot (in Krong Pak district, Dak Lak province).

The project is divided into 3 sub-projects, with the Khanh Hoa Provincial People's Committee as the managing agency for Sub-project 1 (31.5km long); the Ministry of Construction as the managing agency for Sub-project 2 (nearly 38km long); and the Dak Lak Provincial People's Committee as the managing agency for Sub-project 3 (over 48km long). The project starts from the intersection of National Highway 26B and National Highway 1, in the Nam Van Phong port area (Ninh Hoa).

The investment scale for the road is 4 lanes, with a design speed of 100 km/h.



Source: https://www.baogiaothong.vn/pho-thu-tuong-le-thanh-long-tang-toc-thi-cong-cao-toc-qua-phu-yen-khanh-hoa-dak-lak-192250312094223937.htm

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
hot air balloon festival

hot air balloon festival

The dance of happiness before sunset

The dance of happiness before sunset

Family happiness

Family happiness