Accelerating towards the finish line of the first 20km of the Khanh Hoa - Buon Ma Thuot expressway.

Despite challenging weather conditions, contractors are mobilizing maximum manpower and equipment to accelerate construction and complete the remaining components of the Khanh Hoa - Buon Ma Thuot expressway project.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng16/10/2025

A bustling atmosphere prevails at the Khánh Hòa - Buôn Ma Thuột expressway construction site. Photo by: HIẾU GIANG

On October 16th, Mr. Pham Van Hoa, Deputy Director of the Project Management Board for Investment and Construction of Agricultural and Transportation Projects in Khanh Hoa Province (the investor of component 1 of the Khanh Hoa - Buon Ma Thuot expressway project), stated that the project's progress is meeting requirements. The first 20km of the route is expected to be completed by December 19th, 2025, as directed by the Prime Minister.

cao tốc Khánh Hòa - Buôn Ma Thuột
The section of the Khanh Hoa - Buon Ma Thuot expressway project passes through Hoa Tri commune, Khanh Hoa province. Photo: Hieu Giang

From May 2025 to the present, the unpredictable weather on the construction site, including sunshine and rain, has affected the construction progress, especially for packages 2 and 3. To overcome these difficulties, the investor has directed the contractor to concentrate machinery, equipment, and personnel to organize construction in "3 shifts, 4 teams" to meet the schedule.

dasua-7328.jpg
cao tốc Khánh Hòa - Buôn Ma Thuột
Workers from Son Hai Group Co., Ltd. are installing safety and noise barriers at the beginning of the expressway. Photo: Hieu Giang
cao tốc Khánh Hòa - Buôn Ma Thuột
Construction Package No. 1, undertaken by Son Hai Group Co., Ltd., has so far reached 78.85% of the contract value, exceeding the plan by 2.41%. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
Package No. 1, comprising 20km, has been registered as part of the 3,000km expressway project to be completed by the end of 2025, as directed by the Prime Minister . Photo: Hieu Giang
You may also like
A pair of rest stops were inaugurated on the North-South Expressway section passing through Thanh Hoa.
A pair of rest stops were inaugurated on the North-South Expressway section passing through Thanh Hoa.Investing in rest stops along the North-South expressway meets the needs of transporters for fuel, services, and amenities, promotes local products, and contributes to socio-economic development.
Details of 5 TOD (Transit-Oriented Development) zones along Metro Line 2 in Ho Chi Minh City with approved planning boundaries.
Details of 5 TOD (Transit-Oriented Development) zones along Metro Line 2 in Ho Chi Minh City with approved planning boundaries.The Ho Chi Minh City People's Committee has just issued a decision approving the planning boundaries for TOD (Transit-Oriented Development) areas around the stations of Metro Line 2 (Ben Thanh - Tham Luong section), with 5 planned areas totaling hundreds of hectares.
Khanh Hoa - Buon Ma Thuot Expressway: The most complex section of the Phuong Hoang tunnel xuyên through the mountains.
Khanh Hoa - Buon Ma Thuot Expressway: The most complex section of the Phuong Hoang tunnel xuyên through the mountains.The 1.7km-long Phoenix Tunnel, part of the nearly 22 trillion VND expressway project, has officially opened, paving the way for connecting the Central Highlands with the South Central Coast by 2027.
cao tốc Khánh Hòa - Buôn Ma Thuột
In the scorching midday sun, hundreds of engineers and workers are busily carrying out construction. Photo: Hieu Giang
cao tốc Khánh Hòa - Buôn Ma Thuột
Construction of median strips using automated equipment to meet quality standards. Photo: HIEU GIANG
dasua-0031.jpg
The machine that pours seamless concrete median strips saves construction time and increases productivity. Photo: HIEU GIANG

Mr. Vu Huu Khoa, Deputy Director of Khanh Hoa Road Management and Construction Joint Stock Company, said that in construction package No. 1 (the first 22km of the route), there are 9 bridges that the company is responsible for constructing.

To date, the unit has basically completed 8 bridges, and the Song Cai bridge is expected to be completed in November this year, 3 months ahead of schedule. The contractor is making efforts to mobilize machinery and equipment to accelerate progress.

cao tốc Khánh Hòa - Buôn Ma Thuột
The Song Cai Bridge was constructed by Khanh Hoa Road Management and Construction Joint Stock Company. Photo: Hieu Giang
cao tốc Khánh Hòa - Buôn Ma Thuột
The bridge girder is 38 meters long and weighs 72 tons. This is the last bridge under construction package number 1. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
The DT6 overpass on the expressway is gradually taking shape. Photo: HIEU GIANG
You may also like
Khanh Hoa: Over 140 violations detected and handled annually, nearly 5,000 swiftlets rescued.
Khanh Hoa: Over 140 violations detected and handled annually, nearly 5,000 swiftlets rescued.In Khanh Hoa, through coordinated patrol and control efforts, Khanh Hoa Swiftlet Company detects and handles an average of 140-160 violations annually, promptly rescuing 4,000-5,000 swiftlets.
Department of Roads: Sets deadline for rest stop projects on North-South Expressway.
Department of Roads: Sets deadline for rest stop projects on North-South Expressway.(PLVN) - Faced with the situation of many rest stop projects on the Eastern North-South Expressway being behind schedule, the Department of Roads (Ministry of Construction) has issued a document requesting Project Management Boards, Road Management Zones, and investors to take decisive measures to accelerate construction progress.
Toll collection will begin on component projects of the North-South Expressway (Eastern section) from July 15th.
Toll collection will begin on component projects of the North-South Expressway (Eastern section) from July 15th.The Vietnam Road Administration is currently installing equipment and coordinating with project management boards to complete the project and begin collecting tolls on some routes starting July 15, 2026.

Component Project 1 of the Khanh Hoa - Buon Ma Thuot Expressway project has 3 construction packages; the total value of work completed to date is approximately VND 2,275 billion, reaching 62.86% of the contract value, exceeding the plan by 3.19%.

Besides construction package No. 1, which is 22km long and being constructed by Son Hai Group Co., Ltd., construction package No. 2 (10km in the middle of the route) is being implemented by the Phuong Nam - Bac Trung Nam - Dong Duong Joint Venture, and has so far reached 45.58% of the contract value; construction package No. 3 (construction of the Km30 bridge and the Cua Dong bridge) is being implemented by Truong Son Construction Corporation, and has so far reached 51% of the contract value.

Phase 1 of the Khanh Hoa - Buon Ma Thuot expressway project has a total length of 117.5km, with 4 lanes and a roadbed width of 17m. Upon completion, it will shorten the distance from Khanh Hoa province to the administrative and political center of Dak Lak province from approximately 200km to 117km.

Source: https://www.sggp.org.vn/tang-toc-ve-dich-20km-dau-tuyen-cao-toc-khanh-hoa-buon-ma-thuot-post818374.html

Trending by Tag

Trending by Category

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Coloring time

Coloring time

The tourist attraction of Van Thanh flower village.

The tourist attraction of Van Thanh flower village.

Childhood Smile

Childhood Smile